Premises: 300 EAST 41 STREET MANHATTAN BIN: 1090732    Block: 1333    Lot: 49

To start overview at new date, select Month:   Day:   Year:  

         

FILE DATE JOB # DOC # JOB TYPE JOB STATUS STATUS DATE LIC # APPLICANT IN AUDIT ZONING APPROVAL
05/29/2025 123022816 03 A2 D A/P ENTIRE 06/02/2025 WARNER NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021

01/17/2025 121187759 23 NB P APPROVED 01/23/2025 GOODWIN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021

09/06/2024 121187759 22 NB P APPROVED 09/24/2024 0071860 PE WARNER AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 02
 Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021

09/03/2024 121187759 21 NB P APPROVED 09/24/2024 GOODWIN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021

06/20/2024 140625189 07 A2 P APPROVED 06/25/2024 WARNER NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01 HEREWITH FILING A COMBINED SPRINKLER AND ST
 Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021

06/18/2024 121187759 20 NB P APPROVED 07/23/2024 GOODWIN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021

06/07/2024 121187759 19 NB P APPROVED 07/09/2024 0071860 PE WARNER AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 02
 Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021

02/02/2024 140625214 02 A2 P APPROVED 02/23/2024 0071860 PE WARNER NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF 001 thru 021

11/28/2023 140639307 02 A3 P APPROVED 11/30/2023 O'CONNOR NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

10/06/2023 121187759 18 NB P APPROVED 11/20/2023 0071860 PE WARNER AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 02
 Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021

10/05/2023 121187759 17 NB P APPROVED 11/20/2023 GOODWIN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021

10/02/2023 140625189 06 A2 P APPROVED 11/28/2023 WARNER NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021

09/14/2023 140883970 02 A3 P APPROVED 09/14/2023 0099166 PE GAJJAR NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS 001 thru 002

09/06/2023 121187759 16 NB P APPROVED 10/03/2023 GOODWIN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021

08/22/2023 123022816 02 A2 P APPROVED 01/31/2025 0071860 PE WARNER NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021

08/11/2023 123022825 02 A2 P APPROVED 04/03/2024 0071860 PE WARNER NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): BAS,SC1,ROF

07/10/2023 140625189 05 A2 P APPROVED 07/12/2023 0071860 PE WARNER NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021

06/29/2023 123016958 03 A2 P APPROVED 03/28/2024 0071860 PE WARNER NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF 001 thru 021

06/14/2023 121187759 15 NB P APPROVED 07/07/2023 GOODWIN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021

07/06/2022 121187759 14 NB P APPROVED 08/05/2022 GOODWIN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021

11/12/2020 121187759 13 NB P APPROVED 01/29/2021 0021478 RA GOODWIN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021

07/10/2020 121187759 12 NB P APPROVED 07/07/2023 0071860 PE WARNER AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 02
 Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021

07/09/2020 140625189 04 A2 P APPROVED 10/09/2020 SHASSIAN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021

03/20/2020 140892675 01 A2 X SIGNED OFF 05/14/2025 0060597 PE SHAPIRO NOT APPLICABLE
 INSTALLATION OF PERIMETER PLATFORM & PROTECTION AS PER PLANS FILED HEREWIT
 Work on Floor(s): 004 thru 016

01/17/2020 140883970 01 A3 X SIGNED OFF 09/15/2023 0099166 PE GAJJAR NOT APPLICABLE
 INSTALLATION OF 6000 LBS CAPACITY MATERIAL ONLY HOIST DURING NEW BUILDING
 Work on Floor(s): SC1,CEL,BAS 001 thru 002

12/11/2019 140880474 01 A3 X SIGNED OFF 09/14/2023 0099166 PE GAJJAR NOT APPLICABLE
 INSTALLATION OF 6000 LBS CAPACITY MATERIAL ONLY HOIST DURING NEW BUILDING
 Work on Floor(s): SC1,CEL,BAS 001 thru 002

12/03/2019 140871368 02 A3 P APPROVED 12/05/2019 GAJJAR NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

10/31/2019 140875462 01 A3 X SIGNED OFF 09/18/2023 0099166 PE GAJJAR NOT APPLICABLE
 INSTALLATION OF TEMPORARY LOADING DOCK AS PER DRAWINGS. TEMPORARY LOADING
 Work on Floor(s): OSP

10/29/2019 123126660 02 A2 P APPROVED 11/08/2019 SHINFELD NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF 001 thru 021

10/18/2019 140873963 01 A3 X SIGNED OFF 09/18/2023 0099166 PE GAJJAR NOT APPLICABLE
 INSTALLATION OF A TEMPORARY RAMP AS PER DRAWINGS. TEMPORARY RAMP SHALL COM
 Work on Floor(s): OSP

09/30/2019 140871368 01 A3 X SIGNED OFF 09/18/2023 0099166 PE GAJJAR NOT APPLICABLE
 INSTALLATION OF DUAL 7000 LBS CAPACITY PERSONNEL/MATERIAL HOISTS INCLUDING
 Work on Floor(s): OSP

08/01/2019 123016958 02 A2 P APPROVED 02/22/2023 0092471 PE SHASSIAN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF 001 thru 021

07/10/2019 140625189 03 A2 P APPROVED 12/30/2019 SHASSIAN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021

07/09/2019 121187759 11 NB P APPROVED 12/10/2019 GOODWIN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021

01/02/2019 121187759 10 NB P APPROVED 02/28/2019 0066684 PE GOOD AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 06
 Work on Floor(s): SC1,CEL,BAS,OSP

10/29/2018 123126660 01 A2 X SIGNED OFF 02/10/2025 0062199 PE SHINFELD NOT APPLICABLE
 INSTALLATION OF A TEMPORARY DRY STANDPIPE WITH AIR PRESSURIZATION ALARM SY
 Work on Floor(s): SC1,CEL,BAS,ROF 001 thru 021

07/13/2018 121187759 09 NB P APPROVED 12/17/2018 GOODWIN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021

07/11/2018 121187759 08 NB P APPROVED 12/05/2018 0092471 PE SHASSIAN AMENDED 12/06/2019
 POST APPROVAL AMENDMENT FOR 02
 Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021

07/06/2018 140625189 02 A2 P APPROVED 10/02/2018 SHASSIAN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021

04/18/2018 123022816 01 A2 R PERMIT-ENTIRE 10/16/2018 0071860 PE WARNER NOT APPLICABLE
 INSTALLATION OF REPEATER AUXILIARY RADIO COMMUNICATION SYSTEM WITH PASSIVE
 Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021



If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.

BIS Menu  |  Marquee Query  |  ECB Violations  |  Applications  |  Back