| 05/29/2025 |
123022816 |
03 |
A2 |
D A/P ENTIRE |
06/02/2025 |
|
WARNER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021
|
| 01/17/2025 |
121187759 |
23 |
NB |
P APPROVED |
01/23/2025 |
|
GOODWIN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021
|
| 09/06/2024 |
121187759 |
22 |
NB |
P APPROVED |
09/24/2024 |
0071860 PE |
WARNER |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021
|
| 09/03/2024 |
121187759 |
21 |
NB |
P APPROVED |
09/24/2024 |
|
GOODWIN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021
|
| 06/20/2024 |
140625189 |
07 |
A2 |
P APPROVED |
06/25/2024 |
|
WARNER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 HEREWITH FILING A COMBINED SPRINKLER AND ST
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021
|
| 06/18/2024 |
121187759 |
20 |
NB |
P APPROVED |
07/23/2024 |
|
GOODWIN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021
|
| 06/07/2024 |
121187759 |
19 |
NB |
P APPROVED |
07/09/2024 |
0071860 PE |
WARNER |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021
|
| 02/02/2024 |
140625214 |
02 |
A2 |
P APPROVED |
02/23/2024 |
0071860 PE |
WARNER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF 001 thru 021
|
| 11/28/2023 |
140639307 |
02 |
A3 |
P APPROVED |
11/30/2023 |
|
O'CONNOR |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 10/06/2023 |
121187759 |
18 |
NB |
P APPROVED |
11/20/2023 |
0071860 PE |
WARNER |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021
|
| 10/05/2023 |
121187759 |
17 |
NB |
P APPROVED |
11/20/2023 |
|
GOODWIN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021
|
| 10/02/2023 |
140625189 |
06 |
A2 |
P APPROVED |
11/28/2023 |
|
WARNER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021
|
| 09/14/2023 |
140883970 |
02 |
A3 |
P APPROVED |
09/14/2023 |
0099166 PE |
GAJJAR |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS 001 thru 002
|
| 09/06/2023 |
121187759 |
16 |
NB |
P APPROVED |
10/03/2023 |
|
GOODWIN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021
|
| 08/22/2023 |
123022816 |
02 |
A2 |
P APPROVED |
01/31/2025 |
0071860 PE |
WARNER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021
|
| 08/11/2023 |
123022825 |
02 |
A2 |
P APPROVED |
04/03/2024 |
0071860 PE |
WARNER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): BAS,SC1,ROF
|
| 07/10/2023 |
140625189 |
05 |
A2 |
P APPROVED |
07/12/2023 |
0071860 PE |
WARNER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021
|
| 06/29/2023 |
123016958 |
03 |
A2 |
P APPROVED |
03/28/2024 |
0071860 PE |
WARNER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF 001 thru 021
|
| 06/14/2023 |
121187759 |
15 |
NB |
P APPROVED |
07/07/2023 |
|
GOODWIN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021
|
| 07/06/2022 |
121187759 |
14 |
NB |
P APPROVED |
08/05/2022 |
|
GOODWIN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021
|
| 11/12/2020 |
121187759 |
13 |
NB |
P APPROVED |
01/29/2021 |
0021478 RA |
GOODWIN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021
|
| 07/10/2020 |
121187759 |
12 |
NB |
P APPROVED |
07/07/2023 |
0071860 PE |
WARNER |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021
|
| 07/09/2020 |
140625189 |
04 |
A2 |
P APPROVED |
10/09/2020 |
|
SHASSIAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021
|
| 03/20/2020 |
140892675 |
01 |
A2 |
X SIGNED OFF |
05/14/2025 |
0060597 PE |
SHAPIRO |
|
NOT APPLICABLE
|
|
INSTALLATION OF PERIMETER PLATFORM & PROTECTION AS PER PLANS FILED HEREWIT
|
|
Work on Floor(s): 004 thru 016
|
| 01/17/2020 |
140883970 |
01 |
A3 |
X SIGNED OFF |
09/15/2023 |
0099166 PE |
GAJJAR |
|
NOT APPLICABLE
|
|
INSTALLATION OF 6000 LBS CAPACITY MATERIAL ONLY HOIST DURING NEW BUILDING
|
|
Work on Floor(s): SC1,CEL,BAS 001 thru 002
|
| 12/11/2019 |
140880474 |
01 |
A3 |
X SIGNED OFF |
09/14/2023 |
0099166 PE |
GAJJAR |
|
NOT APPLICABLE
|
|
INSTALLATION OF 6000 LBS CAPACITY MATERIAL ONLY HOIST DURING NEW BUILDING
|
|
Work on Floor(s): SC1,CEL,BAS 001 thru 002
|
| 12/03/2019 |
140871368 |
02 |
A3 |
P APPROVED |
12/05/2019 |
|
GAJJAR |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 10/31/2019 |
140875462 |
01 |
A3 |
X SIGNED OFF |
09/18/2023 |
0099166 PE |
GAJJAR |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY LOADING DOCK AS PER DRAWINGS. TEMPORARY LOADING
|
|
Work on Floor(s): OSP
|
| 10/29/2019 |
123126660 |
02 |
A2 |
P APPROVED |
11/08/2019 |
|
SHINFELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF 001 thru 021
|
| 10/18/2019 |
140873963 |
01 |
A3 |
X SIGNED OFF |
09/18/2023 |
0099166 PE |
GAJJAR |
|
NOT APPLICABLE
|
|
INSTALLATION OF A TEMPORARY RAMP AS PER DRAWINGS. TEMPORARY RAMP SHALL COM
|
|
Work on Floor(s): OSP
|
| 09/30/2019 |
140871368 |
01 |
A3 |
X SIGNED OFF |
09/18/2023 |
0099166 PE |
GAJJAR |
|
NOT APPLICABLE
|
|
INSTALLATION OF DUAL 7000 LBS CAPACITY PERSONNEL/MATERIAL HOISTS INCLUDING
|
|
Work on Floor(s): OSP
|
| 08/01/2019 |
123016958 |
02 |
A2 |
P APPROVED |
02/22/2023 |
0092471 PE |
SHASSIAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF 001 thru 021
|
| 07/10/2019 |
140625189 |
03 |
A2 |
P APPROVED |
12/30/2019 |
|
SHASSIAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021
|
| 07/09/2019 |
121187759 |
11 |
NB |
P APPROVED |
12/10/2019 |
|
GOODWIN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021
|
| 01/02/2019 |
121187759 |
10 |
NB |
P APPROVED |
02/28/2019 |
0066684 PE |
GOOD |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 06
|
|
Work on Floor(s): SC1,CEL,BAS,OSP
|
| 10/29/2018 |
123126660 |
01 |
A2 |
X SIGNED OFF |
02/10/2025 |
0062199 PE |
SHINFELD |
|
NOT APPLICABLE
|
|
INSTALLATION OF A TEMPORARY DRY STANDPIPE WITH AIR PRESSURIZATION ALARM SY
|
|
Work on Floor(s): SC1,CEL,BAS,ROF 001 thru 021
|
| 07/13/2018 |
121187759 |
09 |
NB |
P APPROVED |
12/17/2018 |
|
GOODWIN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,TOW 001 thru 021
|
| 07/11/2018 |
121187759 |
08 |
NB |
P APPROVED |
12/05/2018 |
0092471 PE |
SHASSIAN |
|
AMENDED 12/06/2019
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SC1,CEL,BAS,TOW,ROF 001 thru 021
|
| 07/06/2018 |
140625189 |
02 |
A2 |
P APPROVED |
10/02/2018 |
|
SHASSIAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,BAS,ROF,OSP,TOW 001 thru 021
|
| 04/18/2018 |
123022816 |
01 |
A2 |
R PERMIT-ENTIRE |
10/16/2018 |
0071860 PE |
WARNER |
|
NOT APPLICABLE
|
|
INSTALLATION OF REPEATER AUXILIARY RADIO COMMUNICATION SYSTEM WITH PASSIVE
|
|