| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 12/14/2022 |
121189846 |
18 |
NB |
P APPROVED |
12/28/2022 |
|
MAKOOI |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,SUB,ROF 001 thru 006
|
| 11/10/2022 |
121189846 |
17 |
NB |
P APPROVED |
12/01/2022 |
0071681 PE |
TUCCI |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,SUB,ROF 001 thru 006
|
| 08/26/2020 |
121189846 |
16 |
NB |
P APPROVED |
11/04/2022 |
0071681 PE |
TUCCI |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,SUB,ROF 001 thru 006
|
| 10/09/2019 |
121189846 |
15 |
NB |
P APPROVED |
10/11/2019 |
0071681 PE |
TUCCI |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,SUB,ROF 001 thru 006
|
| 09/05/2019 |
122494158 |
02 |
A3 |
P APPROVED |
12/18/2019 |
0034686 RA |
MAKOOI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 06/26/2019 |
121189846 |
14 |
NB |
P APPROVED |
10/04/2019 |
0071681 PE |
TUCCI |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,SUB,ROF 001 thru 006
|
| 06/21/2019 |
140855947 |
01 |
A2 |
X SIGNED OFF |
09/30/2019 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
INSTALLATION OF MINI CRANE AS PER PLAN FILED HEREWITH. NO CHANGE IN USE, E
|
|
Work on Floor(s): GRD,OSP 001 thru 003
|
| 06/03/2019 |
140848162 |
01 |
A2 |
X SIGNED OFF |
07/20/2020 |
0071681 PE |
TUCCI |
|
NOT APPLICABLE
|
|
FILING BOILER APPLICATION AS PER PLANS FILED HEREWITH IN CONJUNCTION WITH
|
|
Work on Floor(s): ROF
|
| 04/04/2019 |
123758503 |
01 |
SC |
U COMPLETED |
05/21/2019 |
0034686 RA |
MAKOOI |
|
NOT APPLICABLE
|
|
APPLICATION FILED FOR CONDO TAX LOT SUBDIVISION OF COMMERCIAL CONDOMINIUM
|
| 03/05/2019 |
123754927 |
01 |
A3 |
J P/E DISAPPROVED |
03/11/2019 |
0034686 RA |
MAKOOI |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 08/12/2020 FILING FIRE PROTECTION PLAN IN CONJUNCTION WITH N
|
|
Work on Floor(s): CEL,SUB,ROF 001 thru 006
|
| 11/20/2018 |
121189846 |
13 |
NB |
P APPROVED |
05/17/2019 |
0034686 RA |
MAKOOI |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,SUB,ROF 001 thru 006
|
| 07/30/2018 |
121189846 |
12 |
NB |
P APPROVED |
09/05/2018 |
0060005 PE |
WEXLER |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 06/18/2018 |
123550442 |
01 |
A2 |
R PERMIT-ENTIRE |
07/26/2018 |
0071681 PE |
TUCCI |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 08/17/2022 INSTALLATION OF SPRINKLER-STANDPIPE SYSTEM IN SUB
|
|
Work on Floor(s): SUB,CEL
|
| 01/30/2018 |
121189846 |
11 |
NB |
P APPROVED |
04/03/2018 |
0060005 PE |
WEXLER |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 01/02/2018 |
121189846 |
10 |
NB |
P APPROVED |
05/14/2018 |
0071681 PE |
TUCCI |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 11/29/2017 |
121189846 |
09 |
NB |
P APPROVED |
12/21/2017 |
|
FISCHER |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 07/12/2017 |
121189846 |
08 |
NB |
P APPROVED |
08/31/2017 |
0068605 PE |
PILLORI |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 03/06/2017 |
121189846 |
07 |
NB |
P APPROVED |
06/26/2017 |
|
FISCHER |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 02/23/2017 |
121189846 |
06 |
NB |
P APPROVED |
03/17/2017 |
0060005 PE |
WEXLER |
|
AMENDED 12/21/2017
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 02/15/2017 |
123021559 |
01 |
A3 |
X SIGNED OFF |
10/04/2019 |
0066720 PE |
HUANG |
|
NOT APPLICABLE
|
|
INSTALLATION OF WOOD FENCE ON PERIMETER OF SITE IN CONJUNCTION WITH NB JOB
|
|
Work on Floor(s): OSP
|
| 04/12/2016 |
140479373 |
01 |
A3 |
R PERMIT-ENTIRE |
05/02/2016 |
0075478 PE |
ESTEVEZ |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 10/21/2019 CONSTRUCTION FENCE FOR DEMOLITION AND NB WORK
|
|
Work on Floor(s): 0SP
|
| 04/01/2016 |
122750549 |
01 |
A3 |
X SIGNED OFF |
07/20/2020 |
0087797 PE |
HELMAN |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF DEBRIS CHUTE AS PER PLANS. NO CHANGE IN USE, EGRE
|
|
Work on Floor(s): 001 thru 006
|
| 03/20/2016 |
140343395 |
02 |
A3 |
P APPROVED |
03/22/2016 |
|
SOLTANIZ |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF TEMPORARY PIPE SCAFFOLD AT
|
|
Work on Floor(s): BAS,ROF 001 thru 006
|
| 01/06/2016 |
121189846 |
05 |
NB |
R PERMIT-ENTIRE |
12/28/2016 |
0068605 PE |
PILLORI |
|
AMENDED 12/21/2017
|
|
SUBSEQUENT FILING TO TAKE RESPONSIBILITY FOR SUPPORT OF EXCAVATION WORK IN
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 12/02/2015 |
122621038 |
01 |
A2 |
X SIGNED OFF |
03/23/2021 |
0071681 PE |
TUCCI |
|
NOT APPLICABLE
|
|
SPRINKLER/STANDPIPE INSTALLATION IN CONJUNCTION WITH NB# 121189846. NO CHA
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 006
|
| 10/23/2015 |
121189846 |
04 |
NB |
R PERMIT-ENTIRE |
12/28/2016 |
0060005 PE |
WEXLER |
|
AMENDED 12/21/2017
|
|
SUBSEQUENT FILING FOR FOUNDATION/FOOTINGS/EARTHWORK TO NB # 121189846.
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 10/23/2015 |
121189846 |
03 |
NB |
R PERMIT-ENTIRE |
12/22/2017 |
0071681 PE |
TUCCI |
|
AMENDED 12/21/2017
|
|
SUBSEQUENT MECHANICAL/PLUMBING WORKTYPE FILING TO NB# 121189846
|
|
Work on Floor(s): CEL,SUB,ROF 001 thru 006
|
| 10/20/2015 |
122494176 |
01 |
A2 |
X SIGNED OFF |
09/07/2022 |
0071681 PE |
TUCCI |
|
NOT APPLICABLE
|
|
MANUAL, AUTOMATIC SMOKE/HEAT/CO DETECTION AND SPRINKLER WITH POST FIRE SMO
|
|
Work on Floor(s): CEL,ROF,SUB 001 thru 006
|
| 10/09/2015 |
122494158 |
01 |
A3 |
X SIGNED OFF |
10/05/2022 |
0034686 RA |
MAKOOI |
|
NOT APPLICABLE
|
|
BUILDERS PAVEMENT PLAN IN CONJUNCTION WITH NB # 121189846 FOR 375 LF.
|
|
Work on Floor(s): OSP
|
| 10/07/2015 |
121189846 |
02 |
NB |
R PERMIT-ENTIRE |
12/28/2016 |
0060005 PE |
WEXLER |
|
AMENDED 12/21/2017
|
|
SUBSEQUENT FILING TO NEW BUILDING FILING FOR STRUCTURAL WORKTYPE.
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 09/28/2015 |
122539351 |
01 |
A2 |
X SIGNED OFF |
09/09/2022 |
0065570 PE |
SHAMES |
|
NOT APPLICABLE
|
|
FILING FOR CUTTING/CAPPING OF STANDPIPES TO COMPLY WITH LOCAL LAW 60 OF 20
|
|
Work on Floor(s): BAS 001 thru 006
|
| 09/16/2015 |
121189846 |
01 |
NB |
R PERMIT-ENTIRE |
11/07/2019 |
0034686 RA |
MAKOOI |
|
AMENDED 12/21/2017
|
|
NEW SEVEN (7) STORY COMMUNITY FACILITY BUILDING
|
|
Work on Floor(s): CEL,SUB,ROF 001 thru 006
|
| 05/05/2015 |
140343395 |
01 |
A3 |
X SIGNED OFF |
05/01/2020 |
0080350 PE |
SOLTANIZ |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AT VARIOUS LEVEL FOR FULL DEMOLITI
|
|
Work on Floor(s): BAS,ROF 001 thru 006
|
| 04/30/2015 |
140341618 |
01 |
A3 |
X SIGNED OFF |
05/01/2020 |
0080350 PE |
SOLTANIZ |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE
|
|
Work on Floor(s): OSP
|
| 04/03/2015 |
140327082 |
01 |
A3 |
R PERMIT-ENTIRE |
04/07/2015 |
0080350 PE |
SOLTANIZ |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/19/2018 INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHE
|
|
Work on Floor(s): OSP
|
| 03/20/2015 |
122344702 |
01 |
A2 |
R PERMIT-ENTIRE |
03/20/2015 |
0087797 PE |
SANTIAGO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/18/2018 DEMOLITION OF 2 STORY REAR BRICK EXTENSION USING
|
|
Work on Floor(s): 001 thru 002
|
| 10/27/1999 |
102435054 |
01 |
A2 |
R PERMIT-ENTIRE |
11/04/1999 |
0040279 PE |
Flynn |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/18/2018 Filing for facade restoration as shown on plans f
|
|
Work on Floor(s): 001 thru 006
|
| 08/30/1999 |
102471362 |
01 |
A3 |
J P/E DISAPPROVED |
09/02/1999 |
0068836 PE |
DEFELIPP |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/18/2018 BUILDERS PAVEMENT PLAN,TOTAL STREET FRON TAGE 77.
|
|
Work on Floor(s): GRD
|
| 07/06/1999 |
102560284 |
01 |
A3 |
R PERMIT-ENTIRE |
07/09/1999 |
|
BUTTNER |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/18/2018 INSTALLATION OF A HEAVY DUTY SHED 133' DURING DEM
|
|
Work on Floor(s): GRD,S
|
| 04/23/1999 |
102048623 |
01 |
A1 |
P APPROVED |
04/23/1999 |
0018973 RA |
RAMPULLA |
Y |
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/18/2018 NO WORK TO BE DONE. FILED TO INDICATE NEW TAX LOT
|
|
Work on Floor(s): CEL 001 thru 006
|