| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 12/29/2021 |
121190139 |
10 |
NB |
P APPROVED |
02/04/2022 |
0060293 PE |
ETTINGER |
|
AMENDED 04/30/2020
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF,UDG 001 thru 022
|
| 11/18/2021 |
123457302 |
02 |
A2 |
P APPROVED |
09/22/2022 |
|
ETTINGER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF AUTOMATIC SMOKE/HEAT DETECT
|
|
Work on Floor(s): CEL,ROF 001 thru 022
|
| 11/08/2021 |
140775953 |
02 |
A2 |
P APPROVED |
11/10/2021 |
|
ETTINGER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 022
|
| 09/23/2021 |
121190139 |
09 |
NB |
P APPROVED |
11/09/2021 |
0060293 PE |
ETTINGER |
|
AMENDED 04/30/2020
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF,UDG 001 thru 022
|
| 08/20/2021 |
121190139 |
08 |
NB |
P APPROVED |
09/03/2021 |
|
LEYVA |
|
AMENDED 04/30/2020
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 022
|
| 04/29/2021 |
140750355 |
02 |
A2 |
P APPROVED |
06/02/2021 |
|
ETTINGER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF
|
| 09/17/2020 |
121190139 |
07 |
NB |
P APPROVED |
09/30/2020 |
0060293 PE |
ETTINGER |
|
AMENDED 04/30/2020
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF,UDG 001 thru 022
|
| 08/13/2020 |
140812663 |
05 |
A3 |
P APPROVED |
09/02/2020 |
|
BLINN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 06/15/2020 |
140812663 |
04 |
A3 |
P APPROVED |
07/10/2020 |
|
BLINN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 04/01/2020 |
123750574 |
03 |
A2 |
P APPROVED |
05/21/2020 |
|
VALJATO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 005 thru 006
|
| 11/20/2019 |
121190139 |
06 |
NB |
P APPROVED |
04/30/2020 |
|
LEYVA |
|
AMENDED 04/30/2020
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 022
|
| 08/08/2019 |
123750574 |
02 |
A2 |
P APPROVED |
08/12/2019 |
|
VALJATO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 005 thru 006
|
| 07/19/2019 |
140812663 |
03 |
A3 |
P APPROVED |
07/19/2019 |
|
BLINN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 06/14/2019 |
123750574 |
01 |
A2 |
X SIGNED OFF |
04/08/2021 |
0082512 PE |
VALJATO |
|
NOT APPLICABLE
|
|
ROOF PROTECTION IN CONJUNCTION WITH NB 121190139. THIS APPLICATION INVOLVE
|
|
Work on Floor(s): 005 thru 006
|
| 10/24/2018 |
140812663 |
02 |
A3 |
P APPROVED |
11/05/2018 |
|
BLINN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 10/17/2018 |
140812663 |
01 |
A3 |
X SIGNED OFF |
03/23/2021 |
0078402 PE |
BLINN |
|
NOT APPLICABLE
|
|
INSTALLATION OF DUAL 6000 LBS CAPACITY PERSONAL/MATERIAL HOIST DURING NEW
|
|
Work on Floor(s): OSP
|
| 08/20/2018 |
123529574 |
01 |
A2 |
X SIGNED OFF |
06/23/2021 |
0060293 PE |
ETTINGER |
|
NOT APPLICABLE
|
|
APPLICATION FILED FOR UNDERGROUND PLUMBING WORK IN CONJUNCTION WITH NB#121
|
|
Work on Floor(s): CEL,UDG
|
| 06/15/2018 |
140775962 |
01 |
A2 |
X SIGNED OFF |
10/06/2021 |
0060293 PE |
ETTINGER |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY AIR PRESSURIZED ALARM SYSTEM FOR DRY STANDPIPE S
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 022
|
| 08/07/2018 |
140775953 |
01 |
A2 |
R PERMIT-ENTIRE |
12/17/2019 |
0060293 PE |
ETTINGER |
|
NOT APPLICABLE
|
|
SPRINKLER & STANDPIPE WORK FILED IN CONJUNCTION WITH NB# 121190139
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 022
|
| 04/24/2018 |
123457302 |
01 |
A2 |
R PERMIT-ENTIRE |
11/29/2018 |
0060293 PE |
ETTINGER |
|
NOT APPLICABLE
|
|
INSTALLATION OF AUTOMATIC SMOKE/HEAT DETECTIN AND SPRINKLER FIRE ALARM SYS
|
|
Work on Floor(s): CEL,ROF 001 thru 022
|
| 04/24/2018 |
123457151 |
01 |
A2 |
J P/E DISAPPROVED |
04/10/2020 |
0060293 PE |
ETTINGER |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 08/28/2022 INSTALLATION OF REPEATER AUXILLARY RADIO COMMUNIC
|
|
Work on Floor(s): CEL,ROF 001 thru 022
|
| 03/22/2018 |
140750355 |
01 |
A2 |
X SIGNED OFF |
01/12/2022 |
0060293 PE |
ETTINGER |
|
NOT APPLICABLE
|
|
INSTALL NEW BOILER(S) IN CONJUNCTION WITH NB# 121190139
|
|
Work on Floor(s): ROF
|
| 06/02/2017 |
121190139 |
04 |
NB |
R PERMIT-ENTIRE |
07/11/2019 |
0060293 PE |
ETTINGER |
|
AMENDED 04/30/2020
|
|
MECHANICAL AND PLUMBING WORK AS SHOWN ON PLANS
|
|
Work on Floor(s): CEL,ROF,UDG 001 thru 022
|
| 06/02/2017 |
121190139 |
03 |
NB |
R PERMIT-ENTIRE |
02/28/2019 |
0078732 PE |
THOMANN |
|
AMENDED 04/30/2020
|
|
SOE WORK AS SHOWN ON PLANS FILED
|
|
Work on Floor(s): CEL,OSP,001
|
| 12/22/2015 |
122643041 |
01 |
A2 |
X SIGNED OFF |
10/20/2021 |
0057530 PE |
MARCUS |
|
NOT APPLICABLE
|
|
CONSTRUCTION OF INITIAL FOOTINGS & FOUNDATIONS IN CONJUNCTION WITH NB#1211
|
|
Work on Floor(s): OSP
|
| 12/03/2015 |
121190139 |
05 |
NB |
R PERMIT-ENTIRE |
02/28/2019 |
0057530 PE |
MARCUS |
|
AMENDED 04/30/2020
|
|
STRUCTURAL SUPERSTRUCTURE WORK AS SHOWN ON PLANS FILED
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
| 11/13/2015 |
121190139 |
02 |
NB |
R PERMIT-ENTIRE |
02/28/2019 |
0057530 PE |
MARCUS |
|
AMENDED 04/30/2020
|
|
FOUNDATION WORK AS SHOWN ON PLANS FILED
|
|
Work on Floor(s): CEL,001,OSP
|
| 11/05/2015 |
121190139 |
01 |
NB |
R PERMIT-ENTIRE |
10/25/2021 |
0021712 RA |
LEYVA |
|
AMENDED 04/30/2020
|
|
NEW RESIDENTIAL BUILDING
|
|
Work on Floor(s): CEL,ROF 001 thru 022
|
| 11/04/2015 |
140424823 |
01 |
A3 |
X SIGNED OFF |
01/31/2022 |
0064477 PE |
MCCOY |
|
NOT APPLICABLE
|
|
BUILDERS PAVEMENT PLAN FILED IN CONJUNCTION WITH NB 121190139
|
|
Work on Floor(s): OSP
|
| 07/10/2015 |
122400222 |
01 |
DM |
E AP-NPE |
07/10/2015 |
OT |
SHAMASH |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/05/2021 FULL DEMOLITION OF A FOUR STORY MULTI-FAMILY WALK
|
|
Work on Floor(s): 001 thru 004
|
| 06/16/2015 |
140362006 |
01 |
A3 |
R PERMIT-ENTIRE |
06/16/2016 |
0080350 PE |
SOLTANIZ |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY PIPE SCAFFOLD 42'HIGH ORIGINATING OFF SHED FOR
|
|
Work on Floor(s): ROF 002 thru 004
|
| 06/16/2015 |
140361926 |
01 |
A3 |
R PERMIT-ENTIRE |
06/17/2016 |
0080350 PE |
SOLTANIZ |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE
|
|
Work on Floor(s): OSP
|
| 06/16/2015 |
140361819 |
01 |
A3 |
H P/E IN PROCESS |
06/16/2015 |
0080350 PE |
SOLTANIZ |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/16/2015 INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHE
|
|
Work on Floor(s): OSP
|
| 05/24/2012 |
121024578 |
03 |
A2 |
P APPROVED |
05/29/2012 |
|
MAK |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 11/05/2021
|
|
Work on Floor(s): 2ND
|
| 04/09/2012 |
121024578 |
02 |
A2 |
P APPROVED |
05/11/2012 |
|
MAK |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 11/05/2021
|
|
Work on Floor(s): 2ND
|
| 03/29/2012 |
121024578 |
01 |
A2 |
R PERMIT-ENTIRE |
05/11/2012 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/05/2021 GENERAL CONSTRUCTION TO INCLUDE NEW PARTITION, RE
|
|
Work on Floor(s): 2ND
|
| 09/27/2011 |
120839432 |
01 |
A2 |
Q PERMIT-PARTIAL |
09/30/2011 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/05/2021 GENERAL CONSTRUCTION TO INCLUDE NEW PARTITION, RE
|
|
Work on Floor(s): 3RD
|
| 04/13/2011 |
120659493 |
01 |
A2 |
R PERMIT-ENTIRE |
04/13/2011 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/05/2021 GENERAL CONSTRUCTION TO INCLUDE NEW PARTITION. NO
|
|
Work on Floor(s): 1ST
|
| 04/05/1994 |
100797112 |
01 |
A2 |
R PERMIT-ENTIRE |
04/13/1994 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
ADMIN CLOSED 11/05/2021 REPLACE GAS BOILER AND CONNECT TO EXISTI NG GAS SE
|
|
Work on Floor(s): CEL
|