| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 11/16/2023 |
121190745 |
25 |
NB |
P APPROVED |
11/20/2023 |
|
GERVASI |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 04/07/2023 |
121190745 |
24 |
NB |
P APPROVED |
04/17/2023 |
|
GERVASI |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 06
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 12/23/2022 |
121190745 |
23 |
NB |
P APPROVED |
01/05/2023 |
|
GERVASI |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 09/19/2022 |
140635267 |
05 |
A2 |
P APPROVED |
10/27/2022 |
|
GERVASI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP,PT1,ROF 001 thru 034
|
| 09/15/2022 |
121190745 |
22 |
NB |
P APPROVED |
10/05/2022 |
0082938 PE |
GERVASI |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 06
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 05/26/2022 |
121190745 |
21 |
NB |
P APPROVED |
07/25/2022 |
0082938 PE |
GERVASI |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 03/18/2022 |
121190745 |
20 |
NB |
P APPROVED |
03/30/2022 |
|
DAVIDSON |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 11/09/2021 |
121190745 |
19 |
NB |
P APPROVED |
12/29/2021 |
|
DAVIDSON |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 10/20/2021 |
141002723 |
02 |
A3 |
P APPROVED |
10/22/2021 |
|
MASONE |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 11/01/2022
|
|
Work on Floor(s): CEL,RF, PT1 001 thru 035
|
| 09/15/2021 |
140635267 |
04 |
A2 |
P APPROVED |
10/12/2021 |
|
GERVASI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP,PT1,ROF 001 thru 034
|
| 08/10/2021 |
121190745 |
18 |
NB |
P APPROVED |
08/13/2021 |
|
DAVIDSON |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 08/02/2021 |
140635267 |
03 |
A2 |
P APPROVED |
08/03/2021 |
|
GERVASI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP,PT1,ROF 001 thru 034
|
| 07/29/2021 |
121190745 |
17 |
NB |
P APPROVED |
08/09/2021 |
|
DAVIDSON |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 07/29/2021 |
140954947 |
02 |
A3 |
P APPROVED |
07/30/2021 |
|
JAMIL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 001 thru 035
|
| 06/28/2021 |
121190745 |
16 |
NB |
P APPROVED |
07/07/2021 |
0082938 PE |
GERVASI |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 06
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 06/24/2021 |
121209557 |
01 |
SC |
U COMPLETED |
08/16/2021 |
0018047 RA |
DAVIDSON |
|
NOT APPLICABLE
|
|
SUBDIVIDE EXISTING TAX LOT INTO ONE-HUNDRED AND ONE (101) CONDO TAX LOTS.
|
| 05/28/2021 |
140635267 |
02 |
A2 |
P APPROVED |
06/29/2021 |
|
GERVASI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP,PT1,ROF 001 thru 034
|
| 05/27/2021 |
141002723 |
01 |
A3 |
P APPROVED |
05/27/2021 |
0084951 PE |
MASONE |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/01/2022 TENANT PROTECTION PLAN FOR FLOORS 001-35,CEL,RF,
|
|
Work on Floor(s): CEL,RF, PT1 001 thru 035
|
| 09/21/2020 |
140954947 |
01 |
A3 |
X SIGNED OFF |
03/06/2023 |
0017617 RA |
JAMIL |
|
NOT APPLICABLE
|
|
ERECT, MAINTAIN AND DISMANTLE SWING SCAFFOLDING AS PER PLANS FILED HEREWIT
|
|
Work on Floor(s): ROF 001 thru 035
|
| 09/09/2019 |
121190745 |
15 |
NB |
P APPROVED |
10/11/2019 |
|
DAVIDSON |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 08/13/2019 |
140864198 |
01 |
A2 |
X SIGNED OFF |
01/30/2023 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
INSTALLATION AND USE OF TEMPORARY LOADING PLATFORM AS PER PLAN FILED HEREW
|
|
Work on Floor(s): ROF 005 thru 036
|
| 06/25/2019 |
140855858 |
01 |
A3 |
X SIGNED OFF |
03/08/2021 |
0071719 PE |
UDDIN |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY DUAL CARS PERSONNEL/MATERIAL HOISTS AS PER PLANS
|
|
Work on Floor(s): OSP
|
| 04/03/2019 |
121190745 |
14 |
NB |
P APPROVED |
05/20/2019 |
|
DAVIDSON |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 03/19/2019 |
123434612 |
01 |
A2 |
X SIGNED OFF |
05/15/2023 |
0080484 PE |
CHELLIAH |
|
NOT APPLICABLE
|
|
INSTALLATION OF A REPEATER AUXILIARY RADIO COMMUNICATION SYSTEM WITH A PAS
|
|
Work on Floor(s): CEL,PT1,ROF 001 thru 035
|
| 02/04/2019 |
121190745 |
13 |
NB |
P APPROVED |
02/05/2019 |
0098231 PE |
MOORMANN |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 07
|
|
Work on Floor(s): OSP
|
| 11/01/2018 |
121190745 |
12 |
NB |
P APPROVED |
11/13/2018 |
|
DAVIDSON |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 09/17/2018 |
123531259 |
01 |
A2 |
X SIGNED OFF |
05/09/2023 |
0082938 PE |
GERVASI |
|
NOT APPLICABLE
|
|
FILING INSTALLATION OF TEMPORARY STANDPIPE SYSTEM IN CONJUNCTION WITH NEW
|
|
Work on Floor(s): CEL,PT1,ROF 001 thru 035
|
| 12/21/2017 |
121190745 |
11 |
NB |
P APPROVED |
04/09/2018 |
0073403 PE |
HAYDA |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 12/18/2017 |
121190745 |
10 |
NB |
P APPROVED |
04/09/2018 |
0082938 PE |
GERVASI |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 06
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 12/12/2017 |
121190745 |
09 |
NB |
P APPROVED |
04/09/2018 |
0082938 PE |
GERVASI |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 12/12/2017 |
121190745 |
08 |
NB |
P APPROVED |
04/09/2018 |
|
DAVIDSON |
|
AMENDED 04/09/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1 001 thru 035
|
| 07/07/2017 |
123045748 |
01 |
DM |
X SIGNED OFF |
12/18/2018 |
0087797 PE |
HELMAN |
|
NOT APPLICABLE
|
|
FULL DEMOLITION OF THREE STORY STRUCTURE BEHIND 368 3RD AVE, UNDER BLOCK:8
|
|
Work on Floor(s): 001 thru 003
|
| 06/19/2017 |
123037640 |
01 |
DM |
X SIGNED OFF |
12/18/2018 |
0087797 PE |
HELMAN |
|
NOT APPLICABLE
|
|
FULL DEMOLITION OF FIVE STORY APARTMENT BUILDING, USING HAND HELD EQUIPMEN
|
|
Work on Floor(s): CEL 001 thru 005
|
| 06/19/2017 |
123037631 |
01 |
DM |
X SIGNED OFF |
12/18/2018 |
0087797 PE |
HELMAN |
|
NOT APPLICABLE
|
|
FULL DEMOLITION OF FOUR STORY STRUCTURE USING HAND HELD EQUIPMENT AND MECH
|
|
Work on Floor(s): CEL 001 thru 004
|
| 06/14/2017 |
121190745 |
07 |
NB |
X SIGNED OFF |
12/13/2023 |
0098231 PE |
MOORMANN |
|
AMENDED 04/09/2018
|
|
SUPPORT OF EXCAVATION WORK ASSOCIATE WITH NEW BUILDING CONSTRUCTION.
|
|
Work on Floor(s): OSP
|
| 05/31/2017 |
140650025 |
01 |
A2 |
X SIGNED OFF |
10/13/2022 |
0082938 PE |
GERVASI |
|
NOT APPLICABLE
|
|
INSTALLATION OF EMERGENCY GENERATOR. NO CHANGE IN OCCUPANCY, USE OR EGRESS
|
|
Work on Floor(s): ROF
|
| 05/31/2017 |
140649993 |
01 |
A2 |
X SIGNED OFF |
10/13/2022 |
0082938 PE |
GERVASI |
|
NOT APPLICABLE
|
|
INSTALLATION OF BOILER. NO CHANGE IN OCCUPANCY, USE OR EGRESS. FILED IN
|
|
Work on Floor(s): 034
|
| 04/28/2017 |
123088755 |
01 |
A2 |
X SIGNED OFF |
10/18/2023 |
0082938 PE |
GERVASI |
|
NOT APPLICABLE
|
|
INSTALLATION OF AUTOMATIC SMOKE/HEAT/CO DETECTION AND SPRINKLER FIRE ALARM
|
|
Work on Floor(s): CEL,PT1,ROF 001 thru 035
|
| 04/27/2017 |
140635267 |
01 |
A2 |
X SIGNED OFF |
10/18/2023 |
0082938 PE |
GERVASI |
|
NOT APPLICABLE
|
|
INSTALLATION OF SPRINKLER AND STANDPIPE SYSTEMS, FILED IN CONJUNCTION WITH
|
|
Work on Floor(s): CEL,OSP,PT1,ROF 001 thru 034
|
| 04/26/2017 |
140634552 |
01 |
A3 |
X SIGNED OFF |
11/10/2022 |
0016077 RA |
SULLIVAN |
|
NOT APPLICABLE
|
|
BUILDERS PAVEMENT PLAN. FILED IN CONJUNCTION WITH NB #121190745
|
|
Work on Floor(s): OSP
|