Premises: 114 MULBERRY STREET MANHATTAN BIN: 1090225    Block: 205    Lot: 8

To start overview at new date, select Month:   Day:   Year:  

         

FILE DATE JOB # DOC # JOB TYPE JOB STATUS STATUS DATE LIC # APPLICANT IN AUDIT ZONING APPROVAL
11/25/2020 140941818 02 A2 P APPROVED 11/29/2020 HELD NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,001

08/20/2020 140941818 01 A2 X SIGNED OFF 11/30/2020 0022194 RA HELD NOT APPLICABLE
 PARTITION WORK AT VACANT COMMERCIAL SPACE FOR RETAIL USE. NO CHANGE TO US
 Work on Floor(s): CEL,BAS,001

10/22/2019 140612013 02 A3 P APPROVED 10/23/2019 MAKOOI NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

09/17/2019 121191334 15 NB P APPROVED 09/19/2019 MAKOOI AMENDED 12/13/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

07/01/2019 121191334 14 NB P APPROVED 07/01/2019 0034686 RA MAKOOI AMENDED 12/13/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

03/25/2019 121191334 13 NB P APPROVED 03/27/2019 0068464 PE RINI III AMENDED 12/13/2018
 POST APPROVAL AMENDMENT FOR 03
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

01/28/2019 121191334 12 NB P APPROVED 02/06/2019 0068464 PE RINI III AMENDED 12/13/2018
 POST APPROVAL AMENDMENT FOR 03
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

01/10/2019 121191334 11 NB P APPROVED 01/11/2019 0068464 PE RINI III AMENDED 12/13/2018
 POST APPROVAL AMENDMENT FOR 03
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

12/28/2018 140618865 02 A2 P APPROVED 01/14/2019 RINI III NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

12/26/2018 121191334 10 NB P APPROVED 01/08/2019 0068464 PE RINI III AMENDED 12/13/2018
 POST APPROVAL AMENDMENT FOR 03
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

11/27/2018 121191334 09 NB P APPROVED 12/04/2018 FISCHER AMENDED 12/13/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

04/20/2018 121191334 08 NB P APPROVED 05/02/2018 FISCHER AMENDED 12/13/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

10/10/2017 123160462 01 A3 X SIGNED OFF 02/14/2019 0088950 PE ACAR NOT APPLICABLE
 INSTALLATION OF A HEAVY DUTY SIDEWALK SHED APPROXIMATELY 70'LONG AS PER PL
 Work on Floor(s): 001

03/20/2017 140618865 01 A2 X SIGNED OFF 05/13/2019 0068464 PE RINI III NOT APPLICABLE
 INSTALLATION OF SPRINKLER AND STANDPIPE SYSTEM. NO CHANGE IN OCCUPANCY, US
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

03/20/2017 122996320 01 A2 X SIGNED OFF 04/09/2019 0068464 PE RINI III NOT APPLICABLE
 INSTALLATION OF AUTOMATIC SMOKE/HEAT DETECTION AND SPRINKLER FIRE ALARM SY
 Work on Floor(s): CEL,ROF 001 thru 007

03/02/2017 140612013 01 A3 X SIGNED OFF 02/04/2020 0034686 RA MAKOOI NOT APPLICABLE
 BUILDERS PAVEMENT PLAN. FILED IN CONJUNCTION WITH NB #121191334
 Work on Floor(s): OSP

02/17/2017 121191334 07 NB X SIGNED OFF 02/21/2020 0084812 PE PAPP, JR AMENDED 12/13/2018
 SUPPORT OF EXCAVATION WORK ASSOCIATED WITH NEW BUILDING CONSTRUCTION.
 Work on Floor(s): OSP

02/17/2017 121191334 06 NB X SIGNED OFF 02/21/2020 0062780 PE GOLDMAN AMENDED 12/13/2018
 FOUNDATION WORK ASSOCIATED WITH NEW BUILDING
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

02/17/2017 121191334 05 NB X SIGNED OFF 02/21/2020 0062780 PE GOLDMAN AMENDED 12/13/2018
 STRUCTURAL WORK ASSOCIATED WITH NEW BUILDING CONSTRUCTION
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

02/17/2017 121191334 04 NB X SIGNED OFF 02/21/2020 0068464 PE RINI III AMENDED 12/13/2018
 UNDERGROUND PLUMBING WORK ASSOCIATED WITH NEW BUILDING CONSTRUCTION
 Work on Floor(s): CEL

02/17/2017 121191334 03 NB X SIGNED OFF 02/21/2020 0068464 PE RINI III AMENDED 12/13/2018
 FULL BUILDING PLUMBING WORK ASSOCIATED WITH NEW BUILDING CONSTRUCTION
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

02/17/2017 121191334 02 NB X SIGNED OFF 02/21/2020 0068464 PE RINI III AMENDED 12/13/2018
 MECHANICAL WORK ASSOCIATED WITH NEW BUILDING CONSTRUCTION.
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

12/07/2016 121191334 01 NB X SIGNED OFF 02/21/2020 0034686 RA MAKOOI AMENDED 12/13/2018
 ERECT NEW BUILDING
 Work on Floor(s): CEL,BAS,ROF 001 thru 007

09/14/2015 122525393 01 A3 R PERMIT-ENTIRE 07/14/2016 0023219 RA VACCARIE NOT APPLICABLE
 JOB WITHDRAWN 06/10/2019 FILING TO ERECT A TEMPORARY 40'X40' TENT IN EXIST
 Work on Floor(s): OSP

09/12/1996 101396614 01 A2 R PERMIT-ENTIRE 09/13/1996 0054064 PE CHOY NOT APPLICABLE
 JOB WITHDRAWN 06/10/2019 TO ERECT TEMP FENCE IN EXISTING VACANT LOT. NO CH
 Work on Floor(s): GRD