| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 06/08/2022 |
121186590 |
20 |
NB |
J P/E DISAPPROVED |
08/15/2022 |
0030327 RA |
CHEUK |
|
GRANTED 07/21/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,SC2,CEL,ROF 001 thru 019
|
| 01/27/2021 |
121186590 |
19 |
NB |
P APPROVED |
02/08/2021 |
|
JACOBS |
|
GRANTED 07/21/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,SC2,CEL,ROF 001 thru 019
|
| 12/17/2019 |
140879529 |
01 |
A2 |
X SIGNED OFF |
12/14/2020 |
0037995 RA |
RODENBEC |
|
NOT APPLICABLE
|
|
INSTALL NEW PARTITIONS AND FINISHES ON PARTIAL CELLAR AND 1ST FLOOR FOR ME
|
|
Work on Floor(s): CEL,001
|
| 12/02/2019 |
123792921 |
02 |
A2 |
X SIGNED OFF |
10/27/2020 |
0026066 RA |
REGAN |
|
NOT APPLICABLE
|
|
HEREWITH FILING TENANT PROTECTION PLAN. NO CHANGE TO USE, EGRESS OR OCCUPA
|
|
Work on Floor(s): SC1,SC2,CEL,001
|
| 12/02/2019 |
123792921 |
01 |
A2 |
X SIGNED OFF |
10/27/2020 |
0009723 RA |
JACOBS |
|
NOT APPLICABLE
|
|
REMOVE AND INSTALL PARTITIONS, FLOORING, CEILINGS AND DOORS. NO CHANGE IN
|
|
Work on Floor(s): SC1,SC2,CEL,001
|
| 11/27/2019 |
121186590 |
18 |
NB |
P APPROVED |
02/11/2020 |
|
JACOBS |
|
GRANTED 07/21/2015
|
|
POST APPROVAL AMENDMENT FOR 01 SEE SECTION #12 & 24.
|
|
Work on Floor(s): SC1,SC2,CEL,ROF 001 thru 019
|
| 06/24/2019 |
140294964 |
03 |
A2 |
P APPROVED |
07/25/2019 |
|
GERVASI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,SC2,CEL,ROF 001 thru 019
|
| 03/19/2019 |
140250047 |
04 |
A2 |
P APPROVED |
05/10/2019 |
|
GERVASI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,SC1,SC2 001 thru 019
|
| 02/13/2019 |
122925996 |
02 |
A3 |
P APPROVED |
02/14/2019 |
0095914 PE |
DALY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 05/29/2018 |
121186590 |
17 |
NB |
P APPROVED |
05/29/2018 |
|
JACOBS |
|
GRANTED 07/21/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,SC2,CEL,ROF 001 thru 019
|
| 05/22/2018 |
140767944 |
01 |
A3 |
X SIGNED OFF |
02/22/2019 |
0087583 PE |
HERNANDE |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY ROOF/ OVERHEAD PROTECTION AT THE ADJACENT PROPER
|
|
Work on Floor(s): OSP
|
| 02/07/2018 |
122832346 |
06 |
A3 |
P APPROVED |
02/13/2018 |
|
HERNANDE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 01/08/2018 |
123133803 |
01 |
A2 |
P APPROVED |
01/08/2018 |
0082938 PE |
GERVASI |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 02/09/2018 FILING HEREWITH INSTALLING SPRINKLER HEADS ALONG
|
|
Work on Floor(s): 9TH
|
| 01/08/2018 |
123163664 |
02 |
A2 |
Q PERMIT-PARTIAL |
01/23/2018 |
0082938 PE |
GERVASI |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 02/09/2018 MECHANICAL MODIFICATIONS. INSTALLATION OF PLUMBIN
|
|
Work on Floor(s): 9TH
|
| 01/08/2018 |
123163664 |
01 |
A2 |
X SIGNED OFF |
02/14/2019 |
0009723 RA |
JACOBS |
|
NOT APPLICABLE
|
|
FILING HEREWITH A TEMPORARY USE PERMIT FOR A SALES OFFICE AND MODEL APARTM
|
|
Work on Floor(s): 1ST,9TH
|
| 10/27/2017 |
122832337 |
03 |
A3 |
P APPROVED |
10/30/2017 |
|
HERNANDE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 10/24/2017 |
121186590 |
16 |
NB |
P APPROVED |
11/21/2017 |
|
JACOBS |
|
GRANTED 07/21/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,SC2,CEL,ROF 001 thru 019
|
| 10/20/2017 |
123173154 |
01 |
A3 |
X SIGNED OFF |
02/12/2019 |
0009723 RA |
JACOBS |
|
NOT APPLICABLE
|
|
MARQUEE FILED FOR DEPARTMENT OF FINANCE BILLING ALL WORK TO BUILD THE MARQ
|
|
Work on Floor(s): 1ST
|
| 10/10/2017 |
121186590 |
15 |
NB |
P APPROVED |
10/20/2017 |
0082938 PE |
GERVASI |
|
GRANTED 07/21/2015
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SC1,SC2,CEL,ROF 001 thru 019
|
| 10/03/2017 |
123159553 |
01 |
A2 |
X SIGNED OFF |
11/01/2019 |
0009723 RA |
JACOBS |
|
NOT APPLICABLE
|
|
TENANT PROTECTION PLAN AS PER DRAWINGS FILE HEREWITH. NO CHANGE IN USE, EG
|
|
Work on Floor(s): SC2,SC, CEL,ROF 001 thru 019
|
| 09/15/2017 |
140250047 |
03 |
A2 |
P APPROVED |
10/04/2017 |
|
GERVASI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,SC1,SC2 001 thru 019
|
| 09/15/2017 |
123114174 |
01 |
A2 |
X SIGNED OFF |
05/31/2018 |
0065403 PE |
GERMAIN |
|
NOT APPLICABLE
|
|
INSTALL (3) NEW GAS FIRED HOT WATER BOILERS WITH INTEGRAL BURNERS, IN
|
|
Work on Floor(s): SC2
|
| 08/17/2017 |
121226351 |
01 |
A3 |
X SIGNED OFF |
02/08/2019 |
0095914 PE |
DALY |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEEDLE BEAM SCAFFOLDING SYSTEM AS PER DRAWINGS. NEEDLE BEA
|
|
Work on Floor(s): 013,014
|
| 08/07/2017 |
122832346 |
05 |
A3 |
P APPROVED |
08/08/2017 |
|
HERNANDE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 02/02/2017 |
122925996 |
01 |
A3 |
X SIGNED OFF |
02/14/2019 |
0095914 PE |
DALY |
|
NOT APPLICABLE
|
|
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPT
|
|
Work on Floor(s): OSP
|
| 01/05/2017 |
140525475 |
02 |
A3 |
P APPROVED |
01/11/2017 |
|
VALJATO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 019
|
| 12/21/2016 |
122904232 |
01 |
A2 |
X SIGNED OFF |
08/03/2018 |
0086645 PE |
PIMENTEL |
|
NOT APPLICABLE
|
|
CONCRETE COLUMNS CHOPPED AT 1ST FLOOR AND REPLACED BY NEW COLUMNS AS SHOWN
|
|
Work on Floor(s): 1ST
|
| 10/27/2016 |
140568525 |
01 |
A3 |
X SIGNED OFF |
02/26/2019 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
INSTALLATION OF LOADING PLATFORM AS PER PLANS FILED HEREWITH. NO CHANGE IN
|
|
Work on Floor(s): OSP 003 thru 013 015 thru 018
|
| 10/17/2016 |
122787314 |
02 |
A3 |
P APPROVED |
10/18/2016 |
0087583 PE |
HERNANDE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 10/12/2016 |
122832346 |
04 |
A3 |
P APPROVED |
02/09/2017 |
|
HERNANDE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 10/11/2016 |
122832346 |
03 |
A3 |
P APPROVED |
10/12/2016 |
0087583 PE |
HERNANDE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 09/20/2016 |
122832337 |
02 |
A3 |
P APPROVED |
09/22/2016 |
|
MCERLEAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 09/19/2016 |
140525475 |
01 |
A3 |
X SIGNED OFF |
02/28/2019 |
0082512 PE |
VALJATO |
|
NOT APPLICABLE
|
|
INSTALLATION OF CONCRETE PUMP IN CONJUNCTION WITH NB 121186590. THIS
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 019
|
| 09/11/2016 |
122832346 |
02 |
A3 |
P APPROVED |
09/12/2016 |
|
MCERLEAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF A HEAVY DUTY SIDEWALK SHED
|
|
Work on Floor(s): 001
|
| 07/14/2016 |
122832337 |
01 |
A3 |
X SIGNED OFF |
02/20/2018 |
0087583 PE |
HERNANDE |
|
NOT APPLICABLE
|
|
INSTALLATION OF A CONSTRUCTION FENCE AS PER PLANS DURING NB CONSTRUCTION.N
|
|
Work on Floor(s): 001
|
| 07/14/2016 |
122832346 |
01 |
A3 |
X SIGNED OFF |
02/20/2018 |
0087583 PE |
HERNANDE |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED APPROXIMATELY 180'LONG AS PER P
|
|
Work on Floor(s): 001
|
| 06/03/2016 |
140250047 |
02 |
A2 |
P APPROVED |
08/23/2016 |
|
GERVASI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,SC1,SC2 001 thru 019
|
| 05/31/2016 |
122787314 |
01 |
A3 |
X SIGNED OFF |
02/20/2018 |
0087583 PE |
HERNANDE |
|
NOT APPLICABLE
|
|
INSTALLATION OF A STROS 7000D(MODEL NOV 3242 UFC-11)PERSONNEL/MATERIAL HOI
|
|
Work on Floor(s): OSP
|
| 05/27/2016 |
121186590 |
14 |
NB |
P APPROVED |
06/06/2016 |
0082938 PE |
GERVASI |
|
GRANTED 07/21/2015
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SC1,SC2,CEL,ROF 001 thru 019
|
| 05/24/2016 |
121186590 |
13 |
NB |
P APPROVED |
06/06/2016 |
|
JACOBS |
|
GRANTED 07/21/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,SC2,CEL,ROF 001 thru 019
|