| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 09/18/2024 |
121190317 |
15 |
NB |
P APPROVED |
09/20/2024 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL 001 thru 022
|
| 02/23/2024 |
121190317 |
14 |
NB |
P APPROVED |
04/16/2024 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL 001 thru 022
|
| 01/05/2023 |
140478141 |
03 |
A2 |
P APPROVED |
01/23/2023 |
|
KAUFMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 022
|
| 10/06/2022 |
140493366 |
02 |
A3 |
P APPROVED |
10/13/2022 |
|
AHEAD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 10/06/2022 |
140537211 |
02 |
A3 |
P APPROVED |
10/26/2022 |
|
AHEAD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 10/05/2022 |
140485767 |
02 |
A3 |
P APPROVED |
10/13/2022 |
0104414 PE |
AHEAD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 10/05/2022 |
140498030 |
03 |
A3 |
P APPROVED |
10/13/2022 |
0104414 PE |
AHEAD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 10/05/2022 |
140485776 |
03 |
A3 |
P APPROVED |
10/13/2022 |
|
AHEAD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 07/19/2022 |
122877832 |
02 |
A2 |
P APPROVED |
08/25/2022 |
|
PATTERSO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 012
|
| 11/12/2021 |
121190317 |
13 |
NB |
P APPROVED |
11/16/2021 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 022
|
| 11/12/2021 |
121190317 |
12 |
NB |
P APPROVED |
11/16/2021 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF,SUB,MEZ 001 thru 022
|
| 11/09/2021 |
121190317 |
11 |
NB |
P APPROVED |
11/16/2021 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL 001 thru 022
|
| 03/12/2020 |
121190317 |
10 |
NB |
P APPROVED |
08/17/2020 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL 001 thru 022
|
| 10/15/2019 |
121190317 |
09 |
NB |
P APPROVED |
12/09/2019 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 022
|
| 07/31/2019 |
121190317 |
08 |
NB |
P APPROVED |
09/20/2019 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL 001 thru 022
|
| 05/06/2019 |
140846878 |
01 |
A2 |
H P/E IN PROCESS |
05/06/2019 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
ADMIN CLOSED 07/05/2019 PROPOSED USE OF MINI CRANE AS PER PLANS. THERE IS
|
|
Work on Floor(s): 001 thru 021
|
| 01/30/2019 |
140827407 |
01 |
A2 |
X SIGNED OFF |
05/20/2022 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
PROPOSED USE OF MINI CRANE AS PER PLANS. THERE IS NO CHANGE IN USE, EGRESS
|
|
Work on Floor(s): 001 thru 021
|
| 06/13/2018 |
140774758 |
01 |
A3 |
X SIGNED OFF |
10/15/2020 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF ROOF PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR
|
|
Work on Floor(s): OSP
|
| 05/12/2018 |
140765571 |
01 |
A3 |
X SIGNED OFF |
03/16/2020 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, E
|
|
Work on Floor(s): OSP
|
| 03/16/2018 |
140748797 |
01 |
A3 |
X SIGNED OFF |
10/15/2020 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF WATER-FILLED BARRICADES AS PER PLANS. NO CHANGE IN USE, EG
|
|
Work on Floor(s): OSP
|
| 11/10/2017 |
140478141 |
02 |
A2 |
P APPROVED |
12/10/2019 |
|
KAUFMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 HEREBY FILING FOR NEW SPRINKLER & STANDPIPE
|
|
Work on Floor(s): CEL,ROF 001 thru 022
|
| 11/08/2017 |
121190317 |
07 |
NB |
P APPROVED |
12/22/2017 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF,SUB,MEZ 001 thru 022
|
| 10/25/2017 |
121190317 |
06 |
NB |
P APPROVED |
12/22/2017 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 022
|
| 09/27/2017 |
121190317 |
05 |
NB |
P APPROVED |
12/22/2017 |
|
KAUFMAN |
|
GRANTED 12/18/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL 001 thru 022
|
| 05/01/2017 |
140615047 |
01 |
A2 |
X SIGNED OFF |
08/31/2022 |
0017030 RA |
KAUFMAN |
|
NOT APPLICABLE
|
|
HEREBY FILING FOR EMERGENCY GENERATOR IN CONJUNCTION WITH NB#121190317
|
|
Work on Floor(s): CEL,ROF 001 thru 022
|
| 12/21/2016 |
140498030 |
02 |
A3 |
P APPROVED |
12/22/2016 |
|
ODIGIE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 12/12/2016 |
140485776 |
02 |
A3 |
P APPROVED |
12/12/2016 |
|
ODIGIE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 11/21/2016 |
122951822 |
01 |
A2 |
X SIGNED OFF |
12/20/2023 |
0092183 PE |
PATTERSO |
|
NOT APPLICABLE
|
|
FILING FOR TEMP EGRESS DOOR TO BE INSTALLED AND USING DURING DEMOLITION IN
|
|
Work on Floor(s): 001
|
| 11/01/2016 |
140567287 |
01 |
A3 |
X SIGNED OFF |
10/14/2022 |
0071719 PE |
UDDIN |
|
NOT APPLICABLE
|
|
INSTALLATION OF SINGLE BETA-MAX 2000 LB HOIST AS PER PLANS DURING CONSTRUC
|
|
Work on Floor(s): OSP
|
| 08/26/2016 |
122877832 |
01 |
A2 |
X SIGNED OFF |
05/13/2024 |
0092183 PE |
PATTERSO |
|
NOT APPLICABLE
|
|
FILED HEREWITH TO INSTALL TEMPORARY STANDPIPE IN CONJUNCTION WITH DEMO
|
|
Work on Floor(s): CEL 001 thru 012
|
| 08/19/2016 |
140537211 |
01 |
A3 |
X SIGNED OFF |
10/31/2022 |
0104414 PE |
AHEAD |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. ALL WORK SHALL BE ACCORDING TO
|
|
Work on Floor(s): OSP
|
| 07/21/2016 |
140521683 |
01 |
A2 |
X SIGNED OFF |
07/08/2022 |
0017030 RA |
KAUFMAN |
|
NOT APPLICABLE
|
|
HEREBY FILING FOR NEW BOILERS IN CONJUNCTION WITH NEW BUILDING # 121190317
|
|
Work on Floor(s): ROF
|
| 07/18/2016 |
122834326 |
01 |
A2 |
X SIGNED OFF |
08/01/2017 |
0092183 PE |
PATTERSO |
|
NOT APPLICABLE
|
|
PROPOSED PARTIAL REMOVAL OF EXTERIOR MASONRY WALL TO INSTALL HOIST AND SLA
|
|
Work on Floor(s): CEL 001 thru 012
|
| 07/14/2016 |
121190317 |
04 |
NB |
X SIGNED OFF |
10/25/2024 |
0078732 PE |
THOMANN |
|
GRANTED 12/18/2016
|
|
HEREBY FILING FOR RELATED SOE WORK FOR NEW BUILDING
|
|
Work on Floor(s): OSP
|
| 05/20/2016 |
140498030 |
01 |
A3 |
X SIGNED OFF |
10/24/2022 |
0104414 PE |
AHEAD |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD & SYSTEM STAIRS AS PER PLANS. ALL WORK SHALL
|
|
Work on Floor(s): OSP
|
| 05/19/2016 |
140494720 |
01 |
A2 |
X SIGNED OFF |
01/25/2023 |
0017030 RA |
KAUFMAN |
|
NOT APPLICABLE
|
|
HEREBY FILING FOR NEW TEMPORARY STANDPIPE SYSTEM AS PER LOCAL LAW 63&64 OF
|
|
Work on Floor(s): CEL,OSP,ROF 001 thru 022
|
| 05/11/2016 |
122736094 |
01 |
A2 |
R PERMIT-ENTIRE |
05/26/2016 |
0092183 PE |
PATTERSO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/22/2023 FILED HEREWITH TO REMOVE SPRINKLER HEADS IN CONJU
|
|
Work on Floor(s): CEL 001 thru 003
|
| 05/11/2016 |
140493366 |
01 |
A3 |
X SIGNED OFF |
10/14/2022 |
0104414 PE |
AHEAD |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AS PER PLANS. FENCE SHALL COM
|
|
Work on Floor(s): OSP
|
| 04/20/2016 |
140485776 |
01 |
A3 |
X SIGNED OFF |
10/24/2022 |
0104414 PE |
AHEAD |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AND ROOF PROTECTION AS PER PLANS.
|
|
Work on Floor(s): OSP
|
| 04/20/2016 |
140485767 |
01 |
A3 |
X SIGNED OFF |
10/24/2022 |
0104414 PE |
AHEAD |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AND ROOF PROTECTION AS PER PLANS.
|
|
Work on Floor(s): OSP
|