| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 09/09/2020 |
140946010 |
01 |
A2 |
P APPROVED |
02/22/2021 |
0076216 PE |
DEGIORGI |
|
NOT APPLICABLE
|
|
INSTALL DEPLOYABLE ALUMINUM STACKABLE FLOOD BARRIER WALL. INSTALL DEPLOYAB
|
|
Work on Floor(s): GRD
|
| 05/15/2014 |
122010536 |
01 |
A2 |
X SIGNED OFF |
11/03/2014 |
0086641 PE |
RAMNARIN |
|
NOT APPLICABLE
|
|
EGRESS PLAN FOR EXISTING UNDERGROUND TUNNEL
|
|
Work on Floor(s): OSP
|
| 03/11/2014 |
121944566 |
01 |
A2 |
P APPROVED |
08/13/2014 |
0068348 PE |
FEENEY |
|
NOT APPLICABLE
|
|
HEREWITH FILING FOR HEATING SYSTEM IMPROVEMENTS AND RELATED PLUMBING AND
|
|
Work on Floor(s): OSP,1ST
|
| 07/06/2009 |
120095798 |
01 |
A2 |
J P/E DISAPPROVED |
07/15/2009 |
0019372 RA |
SILVER |
|
NOT APPLICABLE
|
|
REMOVE AND REPLACE NON-BEARING PARTITIONS, WINDOWS, DOORS, INSULATED METAL
|
|
Work on Floor(s): 001,ROF
|
| 11/19/1992 |
100453288 |
01 |
A3 |
J P/E DISAPPROVED |
11/20/1992 |
|
BRUGGER |
|
NOT APPLICABLE
|
|
NO WORK TO BE DONE.
|
|
Work on Floor(s): 3
|
| 10/21/1992 |
100496919 |
01 |
A2 |
J P/E DISAPPROVED |
10/23/1992 |
0NY1930 RA |
DEL TIN |
|
NOT APPLICABLE
|
|
CONSTRUCT NEW LOCKER RM AND TOILET AND STORAGE LEVEL. REVISE PLUMBING,
|
|
Work on Floor(s): GRD
|