05/15/2012 |
120835150 |
03 |
A2 |
P APPROVED |
06/05/2012 |
|
SMITH |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 008,009,010
|
10/20/2011 |
120835150 |
02 |
A2 |
X SIGNED OFF |
07/23/2012 |
0088975 PE |
SMITH |
|
NOT APPLICABLE
|
|
FILE MECHANICAL AND SPINKLER WORK FOR 8TH, 9TH AND 10TH FLOORS
|
|
Work on Floor(s): 008,009,010
|
09/22/2011 |
120835150 |
01 |
A2 |
X SIGNED OFF |
07/23/2012 |
0021910 RA |
KAYE |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION OF EXISTING 8TH, 9TH AND 10TH FLOORS. NO CHANGE TO USE
|
|
Work on Floor(s): 008,009,010
|
05/12/2011 |
120691331 |
01 |
A3 |
R PERMIT-ENTIRE |
05/12/2011 |
0049458 PE |
TUNG |
|
NOT APPLICABLE
|
|
INSTALL PIPE SCAFFOLD 7LF X 55'H ON BACK OF BUILDING. DURING REMEDIAL REPA
|
|
Work on Floor(s): OSP
|
02/28/2011 |
110468574 |
02 |
A3 |
P APPROVED |
03/02/2011 |
|
PITERA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
02/18/2011 |
120614638 |
01 |
SC |
U COMPLETED |
03/09/2011 |
0025215 RA |
O'HARA |
|
NOT APPLICABLE
|
|
CONDOMINIUM SUBDIVISION ONLY. NO CHANGE TO ZONING LOT MEETS AND BOUNDS.
|
08/12/2010 |
104825691 |
04 |
A2 |
P APPROVED |
08/18/2010 |
|
DeSimone |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
08/03/2010 |
104825691 |
03 |
A2 |
P APPROVED |
08/04/2010 |
0036874 PE |
Haber |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
05/21/2010 |
110238911 |
03 |
A2 |
P APPROVED |
05/28/2010 |
|
HABER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 012
|
04/28/2010 |
104086230 |
07 |
NB |
P APPROVED |
05/05/2010 |
0036874 PE |
HABER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
11/25/2009 |
120211234 |
01 |
A3 |
X SIGNED OFF |
04/30/2010 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALLATION OF GEMINI PLUS MONORAIL MATERIAL 600LB CAPACITY HOIST. HOIST
|
|
Work on Floor(s): OSP
|
11/10/2009 |
110305802 |
02 |
A2 |
P APPROVED |
11/13/2009 |
|
HABER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 012
|
09/15/2009 |
104086230 |
06 |
NB |
P APPROVED |
02/22/2010 |
0025215 RA |
O'HARA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
09/11/2009 |
110238911 |
02 |
A2 |
P APPROVED |
09/18/2009 |
|
HABER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 012
|
07/17/2009 |
110350995 |
02 |
A3 |
P APPROVED |
07/17/2009 |
|
PITERA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
06/23/2009 |
120079752 |
01 |
A3 |
P APPROVED |
08/14/2009 |
0025215 RA |
O'HARA |
|
NOT APPLICABLE
|
|
FIRE PROTECTION PLAN
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
05/14/2009 |
120038994 |
01 |
A2 |
X SIGNED OFF |
07/27/2010 |
0036874 PE |
HABER |
|
NOT APPLICABLE
|
|
INSTALLATION OF BOILER. NO CHANGE IN USE, EGRESS OR OCCUPANCY. FILED IN
|
|
Work on Floor(s): SUB
|
05/05/2009 |
110350986 |
02 |
A3 |
P APPROVED |
05/05/2009 |
|
PITERA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
04/17/2009 |
104086230 |
05 |
NB |
P APPROVED |
08/28/2009 |
0036874 PE |
HABER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
02/24/2009 |
110468574 |
01 |
A3 |
X SIGNED OFF |
04/22/2011 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALL NEW SHED ON STREET AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE
|
|
Work on Floor(s): OSP
|
10/08/2008 |
110350995 |
01 |
A3 |
X SIGNED OFF |
02/17/2010 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALL 50 FOOT LONG HEAVY DUTY SIDEWALK SHED AS PER PLANS SUBMITTED HERE
|
|
Work on Floor(s): OSP
|
10/08/2008 |
110350986 |
01 |
A3 |
X SIGNED OFF |
02/17/2010 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALL 50 FOOT LONG SCAFFOLD AS PER PLANS SUBMITTED HEREWITH. NO CHANGE
|
|
Work on Floor(s): OSP
|
07/31/2008 |
110238911 |
01 |
A2 |
X SIGNED OFF |
06/20/2011 |
0036874 PE |
HABER |
|
NOT APPLICABLE
|
|
INSTALLATION OF SPRINKLER SYSTEM. NO CHANGE IN OCCUPANCY, USE OR EGRESS.
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 012
|
07/31/2008 |
110305802 |
01 |
A2 |
X SIGNED OFF |
06/20/2011 |
0036874 PE |
HABER |
|
NOT APPLICABLE
|
|
INSTALLATION OF STANDPIPE SYSTEM. NO CHANGE IN OCCUPANCY, USE OR EGRESS.
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 012
|
07/12/2008 |
110290961 |
01 |
A3 |
X SIGNED OFF |
09/14/2010 |
0085449 PE |
CIOCOI |
|
NOT APPLICABLE
|
|
INSTALLATION OF AN AVRO SC270 PERSONNEL/MATERIAL HOIST DURING CONSTRUCTION
|
|
Work on Floor(s): OSP
|
11/14/2007 |
110019854 |
01 |
A2 |
X SIGNED OFF |
06/21/2011 |
0036874 PE |
HABER |
|
NOT APPLICABLE
|
|
INSTALL FIRE ALARM DEVICES AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE
|
|
Work on Floor(s): CEL,SUB,ROF 001 thru 012
|
11/14/2007 |
110019845 |
01 |
A2 |
J P/E DISAPPROVED |
11/19/2007 |
0036874 PE |
HABER |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 12/08/2008 INSTALL SPRINKLER SYSTEM AS SHOWN ON DRAWINGS FIL
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
11/14/2007 |
110019836 |
01 |
A2 |
J P/E DISAPPROVED |
11/16/2007 |
0036874 PE |
HABER |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 12/10/2008 INSTALL STANDPIPE SYSTEM AS SHOWN ON DRAWINGS FIL
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
07/26/2007 |
104847757 |
01 |
A2 |
X SIGNED OFF |
02/02/2009 |
0062685 PE |
Jaffarpo |
|
NOT APPLICABLE
|
|
Shoring for construction of foundation. Filed in conjunction with NB #1040
|
|
Work on Floor(s): OSP
|
07/03/2007 |
104825691 |
02 |
A2 |
X SIGNED OFF |
06/27/2011 |
0036874 PE |
Haber |
|
NOT APPLICABLE
|
|
Underground plumbing work associated with foundation and excavation work.
|
07/03/2007 |
104825691 |
01 |
A2 |
X SIGNED OFF |
06/27/2011 |
0074933 PE |
DeSimone |
|
NOT APPLICABLE
|
|
Foundation and excavation. No change in occupancy, use or egress. Filed
|
|
Work on Floor(s): CEL
|
06/21/2007 |
104459701 |
05 |
A1 |
P APPROVED |
07/03/2007 |
0011247 RA |
Hammer |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 08/27/2007
|
|
Work on Floor(s): ROF 002 thru 005
|
06/13/2007 |
104793822 |
01 |
A3 |
X SIGNED OFF |
06/17/2010 |
818 |
LYKOS |
|
NOT APPLICABLE
|
|
BUILDERS PAVEMENT PLAN-LENGTH 122'IN CO-JUCTION WITH NB#104086230
|
|
Work on Floor(s): 001
|
05/08/2007 |
104757960 |
01 |
A3 |
X SIGNED OFF |
08/18/2010 |
0079601 PE |
McERLEAN |
|
NOT APPLICABLE
|
|
Erect stair tower approx. 80 ft high at 1055 Park Avenue. - Work shall com
|
|
Work on Floor(s): 001
|
04/13/2007 |
104735627 |
01 |
DM |
X SIGNED OFF |
06/03/2008 |
OT |
Santiago |
|
NOT APPLICABLE
|
04/05/2007 |
104727547 |
01 |
A3 |
X SIGNED OFF |
08/03/2010 |
0020419 RA |
Hulme |
|
NOT APPLICABLE
|
|
INSTALL PIPE SCAFFOLD 20LF X 40'H ON PARK AVENUE, 100LF X 40'H ON EAST 87T
|
|
Work on Floor(s): 001
|
06/09/2006 |
104459701 |
04 |
A1 |
P APPROVED |
06/09/2006 |
0080090 PE |
Carnaval |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 08/27/2007 Plumbing modifications associated with the change
|
|
Work on Floor(s): ROF 002 thru 005
|
06/09/2006 |
104459701 |
03 |
A1 |
R PERMIT-ENTIRE |
06/21/2006 |
0080090 PE |
Carnaval |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 08/27/2007
|
|
Work on Floor(s): ROF 002 thru 005
|
06/09/2006 |
104459701 |
02 |
A1 |
R PERMIT-ENTIRE |
06/21/2006 |
0074933 PE |
DeSimone |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 08/27/2007 Structural modifications associated with the chan
|
|
Work on Floor(s): ROF 002 thru 005
|
06/09/2006 |
104459701 |
01 |
A1 |
Q PERMIT-PARTIAL |
06/21/2006 |
0011247 RA |
Hammer |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 08/27/2007 Change from 5 storey building to 1 storey buildin
|
|
Work on Floor(s): ROF 002 thru 005
|