| 08/10/2017 |
123107967 |
01 |
A2 |
X SIGNED OFF |
10/11/2017 |
0037876 RA |
FANG |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION OF APARTMENT UNITS, INCLUDING MINOR CHANGE OF PARTITIO
|
| 07/21/2015 |
122471388 |
01 |
A2 |
X SIGNED OFF |
10/16/2017 |
0059427 PE |
COLLINS |
|
NOT APPLICABLE
|
|
CAP & REMOVE ALL EXISTING BOILERS,INSTALL 2 NEW GAS BOILERS,2HOT WATER TAN
|
|
Work on Floor(s): CEL,OSP
|
| 08/29/2014 |
122116370 |
01 |
A2 |
X SIGNED OFF |
12/18/2014 |
0066722 PE |
HUANG |
|
NOT APPLICABLE
|
|
MINOR RENOVATION OF APT# 1D AT 1ST FLOOR OF THE EXISTING BUILDING AS PER
|
|
Work on Floor(s): 001
|
| 11/27/2012 |
121426910 |
01 |
A2 |
X SIGNED OFF |
08/20/2013 |
0066722 PE |
HUANG |
|
NOT APPLICABLE
|
|
REPAINT AND REPLACE SOME WINDOWS FOR THE EXISTING PUBLIC HALLWAY FROM BASE
|
|
Work on Floor(s): BAS,ROF 001 thru 006
|
| 07/16/2012 |
121152956 |
01 |
A2 |
X SIGNED OFF |
11/19/2012 |
0066722 PE |
HUANG |
|
NOT APPLICABLE
|
|
MINOR RENOVATION OF APT#1A & 1C AT 1ST FLOOR, APT#2B,2C & 2D AT 2ND FLOOR
|
|
Work on Floor(s): 001,002
|
| 10/17/2011 |
120862398 |
01 |
A3 |
R PERMIT-ENTIRE |
10/18/2011 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS, OR
|
|
Work on Floor(s): 001
|
| 10/12/2011 |
120856662 |
01 |
A3 |
X SIGNED OFF |
01/23/2013 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, E
|
|
Work on Floor(s): 001
|
| 08/24/2011 |
120805423 |
01 |
A2 |
R PERMIT-ENTIRE |
10/07/2011 |
0020340 RA |
FENNIMAN |
|
NOT APPLICABLE
|
|
FACADE RESTORATION AS PER PLAN. NO CHANGE TO OCCUPANCY, USE, EGRESS OR BUL
|
|
Work on Floor(s): EXT
|
| 12/17/1990 |
100080305 |
02 |
A2 |
P APPROVED |
12/21/1990 |
0015295 RA |
CHIN |
|
NOT APPLICABLE
|
|
SUBSEQUENT FILING FOR PLUMBING IN CONNECTION WITH BOILER .
|
|
Work on Floor(s): CLR
|
| 07/26/1990 |
100080305 |
01 |
A2 |
Q PERMIT-PARTIAL |
01/08/1991 |
0015295 RA |
CHIN |
|
NOT APPLICABLE
|
|
INSTALLATION OF 2 NEW BOILERS IN THE CELLAR. THERE WILL BE NO CHANGE
|
|
Work on Floor(s): CEL
|