| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 02/11/2025 |
103650158 |
07 |
A2 |
P APPROVED |
02/11/2025 |
0024454 RA |
EDDEN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP,CEL,ROF 001 thru 005
|
| 07/11/2022 |
103650158 |
06 |
A2 |
P APPROVED |
07/11/2022 |
0038071 RA |
JAMES |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP,CEL,ROF 001 thru 005
|
| 05/25/2022 |
103650158 |
05 |
A2 |
P APPROVED |
05/25/2022 |
0038066 RA |
JARED |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP,CEL,ROF 001 thru 005
|
| 10/29/2020 |
103650158 |
04 |
A2 |
P APPROVED |
10/29/2020 |
|
GOLDMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): OSP,CEL,ROF 001 thru 005
|
| 12/13/2018 |
103651059 |
01 |
A3 |
X SIGNED OFF |
12/22/2025 |
0080572 PE |
RAMKEESO |
|
NOT APPLICABLE
|
|
PIPE SCAFFOLD APPLICATION FILED ON BEHALF OF CONTRACTOR
|
|
Work on Floor(s): OSP
|
| 12/13/2018 |
103651031 |
01 |
A3 |
X SIGNED OFF |
12/22/2025 |
0080572 PE |
RAMKEESO |
|
NOT APPLICABLE
|
|
SIDEWALK SHED APPLICATION FILED ON BEHALF OF CONTRACTOR (APPROX. 1100 LF O
|
|
Work on Floor(s): OSP
|
| 12/13/2018 |
103651040 |
01 |
A3 |
X SIGNED OFF |
01/12/2026 |
0080572 PE |
RAMKEESO |
|
NOT APPLICABLE
|
|
TEMPORARY FENCE APPLICATION FILED ON BEHALF OF CONTRACTOR
|
|
Work on Floor(s): OSP
|
| 05/10/2018 |
103650158 |
03 |
A2 |
R PERMIT-ENTIRE |
02/27/2019 |
0069356 PE |
GOLDMAN |
|
NOT APPLICABLE
|
|
REMOVE AND REPLACE EXISTING DRAINS. RELOCATING EXISTING GAS PIPING
|
|
Work on Floor(s): OSP,CEL,ROF 001 thru 005
|
| 05/10/2018 |
103650158 |
02 |
A2 |
R PERMIT-ENTIRE |
02/27/2019 |
0079764 PE |
JOG |
|
NOT APPLICABLE
|
|
NEW ROOFS, AND NEW PARAPET CONSTRUCTION. REPAIRS TO PLAY YARD, FRONT ENTR
|
|
Work on Floor(s): OSP 001 thru 005
|
| 05/10/2018 |
103650158 |
01 |
A2 |
R PERMIT-ENTIRE |
01/20/2026 |
0024454 RA |
EDDEN |
|
NOT APPLICABLE
|
|
FLOOD ELIMINATION, NEW ROOFS, AND NEW PARAPET CONSTRUCTION. REPAIRS TO PLA
|
|
Work on Floor(s): OSP,CEL,ROF 001 thru 005
|
| 03/29/2017 |
122400384 |
01 |
A2 |
R PERMIT-ENTIRE |
03/29/2017 |
0061465 PE |
YUNG |
|
NOT APPLICABLE
|
|
INSTALL (10) TEN 36,000 BTU SPLIT HVAC SYSTEMS. OBTAIN EQUIPMENT USE PERMI
|
|
Work on Floor(s): OSP,002,ROF
|
| 09/26/2014 |
103644326 |
02 |
A2 |
P APPROVED |
09/26/2014 |
|
DESROCHE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALL NEW SPLIT AIR AC UNIT IN ROOM 365 C
|
|
Work on Floor(s): 003,ROF
|
| 07/05/2013 |
103644326 |
01 |
A2 |
X SIGNED OFF |
11/16/2016 |
0065346 PE |
DESROCHE |
|
NOT APPLICABLE
|
|
INSTALL NEW SPLIT AIR AC UNIT IN ROOM 365 CONDENSOR ON ROOF.
|
|
Work on Floor(s): 003,ROF
|
| 06/11/2012 |
101703523 |
08 |
A1 |
P APPROVED |
06/11/2012 |
|
DIGERONI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 PS 189M TWO STORIES ADDITION TO THE EXISTIN
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 06/11/2012 |
101703523 |
07 |
A1 |
P APPROVED |
06/11/2012 |
|
DIGERONI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 1
|
| 05/30/2012 |
103887769 |
07 |
A2 |
P APPROVED |
05/30/2012 |
|
DIGERONI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 01/06/2012 |
103890434 |
03 |
A2 |
P APPROVED |
01/06/2012 |
|
SHENOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,1ST,2ND,3RD
|
| 12/01/2011 |
103640473 |
02 |
A2 |
P APPROVED |
12/01/2011 |
|
EID |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 07/20/2011 |
103887769 |
06 |
A2 |
P APPROVED |
07/20/2011 |
|
SHENOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 07/14/2011 |
103887956 |
02 |
A2 |
P APPROVED |
08/09/2011 |
|
SHENOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,THR,005,ROF
|
| 05/20/2011 |
103640473 |
01 |
A2 |
X SIGNED OFF |
03/17/2014 |
0073979 PE |
EID |
|
NOT APPLICABLE
|
|
REMOVE & REPLACE EXISTING INTERIOR LIGHTING THROUG THE BUILDING.
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 03/09/2011 |
103887769 |
05 |
A2 |
P APPROVED |
03/09/2011 |
0001167 RA |
DIGERONI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 03/03/2011 |
103890979 |
01 |
A3 |
X SIGNED OFF |
01/16/2014 |
0001167 RA |
DIGERONI |
|
NOT APPLICABLE
|
|
FILING OF FIRE PROTECTION PLAN.
|
|
Work on Floor(s): CEL,0RF 001 thru 005
|
| 02/23/2011 |
103887769 |
04 |
A2 |
P APPROVED |
02/23/2011 |
|
SHENOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 12/27/2010 |
103890434 |
02 |
A2 |
P APPROVED |
12/27/2010 |
|
SHENOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,1ST,2ND,3RD
|
| 11/22/2010 |
103887386 |
05 |
A2 |
P APPROVED |
11/22/2010 |
|
SHENOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 003,004,005
|
| 11/18/2010 |
103887386 |
04 |
A2 |
P APPROVED |
11/18/2010 |
|
SHENOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 003,004,005
|
| 11/02/2010 |
102145803 |
03 |
PA |
P APPROVED |
11/02/2010 |
|
MALTZ |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 1
|
| 10/22/2010 |
103890434 |
01 |
A2 |
X SIGNED OFF |
12/19/2013 |
0055232 PE |
SHENOY |
|
NOT APPLICABLE
|
|
PROVIDE NEW EMERGENCY GENERATOR, FUEL STORAGE TANK, FUEL PUMP AND ALL ASSO
|
|
Work on Floor(s): CEL,1ST,2ND,3RD
|
| 10/21/2010 |
102262640 |
05 |
PA |
P APPROVED |
10/21/2010 |
|
MALTZ |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002
|
| 10/07/2010 |
103887386 |
03 |
A2 |
P APPROVED |
10/07/2010 |
|
SHENOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 003,004,005
|
| 08/24/2010 |
101924223 |
02 |
PA |
P APPROVED |
08/24/2010 |
|
EILAM |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 1
|
| 08/11/2010 |
102262668 |
04 |
PA |
P APPROVED |
08/11/2010 |
0024701 RA |
EILAM |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): FIR,ST
|
| 07/20/2010 |
103889874 |
01 |
PA |
U COMPLETED |
05/06/2011 |
0024701 RA |
EILAM |
|
NOT APPLICABLE
|
|
Work on Floor(s): 001
|
| 07/15/2010 |
101703523 |
06 |
A1 |
P APPROVED |
06/11/2012 |
0001167 RA |
DIGERONI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 1
|
| 10/02/2009 |
103888580 |
01 |
A3 |
X SIGNED OFF |
04/18/2012 |
0070592 PE |
STILLER |
|
NOT APPLICABLE
|
|
PS189M: DRAWINGS FILED FOR CONTRACTOR FOR THE INSTALLATION OF TEMPORARY
|
|
Work on Floor(s): OSP
|
| 09/10/2009 |
103888474 |
01 |
A3 |
X SIGNED OFF |
10/21/2011 |
0069932 PE |
CUNNINGH |
|
NOT APPLICABLE
|
|
FENCE PERMIT, FILED IN CONJUNCTION WITH ONGOING REPAIRS UNDER DOB # 103887
|
|
Work on Floor(s): OSP
|
| 04/24/2009 |
103887956 |
01 |
A2 |
X SIGNED OFF |
06/26/2013 |
0055232 PE |
SHENOY |
|
NOT APPLICABLE
|
|
ADDITTION OF FIRE ALARM DEVICES CONSISTING OF PULL STATIONS, HORN STROBES,
|
|
Work on Floor(s): CEL,001,THR,005,ROF
|
| 04/14/2009 |
103887769 |
01 |
A2 |
X SIGNED OFF |
09/13/2013 |
0001167 RA |
DIGERONI |
|
NOT APPLICABLE
|
|
PS189 ERECT NEW STORAGE RMS, OFFICE & EXIT PASSAGEWAY @ 1ST FL, INSTALL NE
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 04/14/2009 |
103887769 |
03 |
A2 |
X SIGNED OFF |
09/13/2013 |
0552321 PE |
SHENOY |
|
NOT APPLICABLE
|
|
PS189 PROVIDE NEW ROOF TOP GAS FIRED H&V UNIT ON DUNNAGE FOR CLASSROOMS ON
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|