| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 01/22/2026 |
122854116 |
02 |
PA |
G PAA FEE DUE |
01/22/2026 |
0017067 RA |
LOEWENSO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001,002
|
| 08/16/2018 |
121192958 |
06 |
A1 |
P APPROVED |
08/21/2018 |
|
ZASKORSK |
|
GRANTED 06/08/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 10/10/2017 |
120084265 |
07 |
A2 |
P APPROVED |
10/25/2017 |
|
BRENNAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002,003
|
| 06/30/2017 |
120084265 |
06 |
A2 |
P APPROVED |
07/31/2017 |
0082724 PE |
BRENNAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002,003
|
| 06/29/2017 |
122026538 |
02 |
A2 |
P APPROVED |
07/13/2017 |
0058648 PE |
CHRISTOF |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 06/16/2017 |
100174776 |
07 |
A2 |
P APPROVED |
06/30/2017 |
|
BRENNAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 06/05/2017 |
122639430 |
04 |
A2 |
P APPROVED |
06/09/2017 |
|
BRENNAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 05/23/2017 |
121192958 |
05 |
A1 |
P APPROVED |
06/07/2017 |
|
ZASKORSK |
|
GRANTED 06/08/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 05/16/2017 |
100174776 |
06 |
A2 |
P APPROVED |
06/09/2017 |
0082724 PE |
BRENNAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 04/05/2017 |
140507299 |
02 |
A3 |
P APPROVED |
05/01/2018 |
|
AHMED |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 007 001 thru 004 008 thru 011
|
| 02/21/2017 |
122843487 |
02 |
A2 |
P APPROVED |
03/09/2017 |
|
MARZILIA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002,003,004
|
| 02/21/2017 |
122744058 |
02 |
A2 |
P APPROVED |
03/09/2017 |
|
MARZILIA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 MODIFICATIONS AND ADDITIONS TO AN EXISTING
|
|
Work on Floor(s): CEL,1, 5, TO, 11
|
| 01/27/2017 |
123005425 |
01 |
A3 |
P APPROVED |
03/27/2017 |
0014342 RA |
ZASKORSK |
|
NOT APPLICABLE
|
|
FIRE PROTECTION PLAN
|
|
Work on Floor(s): CEL 001 thru 011
|
| 01/06/2017 |
122808505 |
03 |
A3 |
P APPROVED |
01/18/2017 |
|
PERDEK |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 11/28/2016 |
122639430 |
03 |
A2 |
P APPROVED |
11/30/2016 |
|
BRENNAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 11/22/2016 |
121192958 |
04 |
A1 |
P APPROVED |
11/30/2016 |
|
ZASKORSK |
|
GRANTED 06/08/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 11/05/2016 |
122808514 |
02 |
A3 |
P APPROVED |
11/09/2016 |
|
PERDEK |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 10/26/2016 |
122882176 |
02 |
A3 |
P APPROVED |
10/28/2016 |
|
PERDEK |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 10/26/2016 |
122790630 |
02 |
A3 |
P APPROVED |
10/28/2016 |
|
PERDEK |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 09/19/2016 |
122808505 |
02 |
A3 |
P APPROVED |
09/20/2016 |
|
PERDEK |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 09/06/2016 |
122882176 |
01 |
A3 |
X SIGNED OFF |
10/19/2017 |
0086757 PE |
PERDEK |
|
NOT APPLICABLE
|
|
INSTALLATION OF PLYWOOD FENCE AS PER DRAWINGS. PLYWOOD FENCE SHALL COMPLY
|
|
Work on Floor(s): OSP
|
| 08/29/2016 |
122808505 |
01 |
A3 |
X SIGNED OFF |
10/19/2017 |
0086757 PE |
PERDEK |
|
NOT APPLICABLE
|
|
INSTALLATION OF A DUAL 6000 LBS CAPACITY PERSONNEL/MATERIAL HOIST DURING
|
|
Work on Floor(s): OSP
|
| 08/26/2016 |
122808514 |
01 |
A3 |
X SIGNED OFF |
11/20/2017 |
0086757 PE |
PERDEK |
|
NOT APPLICABLE
|
|
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPT
|
|
Work on Floor(s): OSP
|
| 08/25/2016 |
122804705 |
01 |
A3 |
X SIGNED OFF |
10/19/2017 |
0086757 PE |
PERDEK |
|
NOT APPLICABLE
|
|
STORAGE UP TO 150 PSF ON TOP OF HEAVY DUTY SIDEWALK SHED. SHED DESIGNED FO
|
|
Work on Floor(s): OSP
|
| 08/08/2016 |
122854116 |
01 |
PA |
U COMPLETED |
10/06/2017 |
0014342 RA |
ZASKORSK |
|
NOT APPLICABLE
|
|
Work on Floor(s): 001,002
|
| 07/29/2016 |
122843487 |
01 |
A2 |
X SIGNED OFF |
11/01/2017 |
0078891 PE |
MARZILIA |
|
NOT APPLICABLE
|
|
MODIFICATIONS & ADDITIONS TO AN EXISTING APPROVED FIRE ALARM SYSTEM AS PER
|
|
Work on Floor(s): 002,003,004
|
| 07/11/2016 |
122790630 |
01 |
A3 |
X SIGNED OFF |
10/19/2017 |
0086757 PE |
PERDEK |
|
NOT APPLICABLE
|
|
INSTALLATION OF 142 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED DURING BUILDIN
|
|
Work on Floor(s): OSP
|
| 06/15/2016 |
140507299 |
01 |
A3 |
X SIGNED OFF |
05/01/2018 |
0093179 PE |
AHMED |
|
NOT APPLICABLE
|
|
TENANT PROTECTION PLAN IN CONJUNCTION WITH THE ALTERATION DOB JOB #1211929
|
|
Work on Floor(s): 007 001 thru 004 008 thru 011
|
| 04/21/2016 |
122762242 |
01 |
A3 |
X SIGNED OFF |
04/17/2017 |
0085870 PE |
WESTRICK |
|
NOT APPLICABLE
|
|
INSTALLATION OF A TEMPORARY WORK PLATFORM @ LOBBY AS PER PLANS DURING GENE
|
|
Work on Floor(s): OSP
|
| 03/23/2016 |
122744058 |
01 |
A2 |
X SIGNED OFF |
02/22/2018 |
0078891 PE |
MARZILIA |
|
NOT APPLICABLE
|
|
MODIFICATIONS AND ADDITIONS TO AN EXISTING APPROVED FIRE ALARM SYSTEM AS P
|
|
Work on Floor(s): CEL,1, 5, TO, 11
|
| 01/20/2016 |
122639430 |
02 |
A2 |
X SIGNED OFF |
04/30/2018 |
0082724 PE |
BRENNAN |
|
NOT APPLICABLE
|
|
RENOVATION TO EXISTING NON-PROFIT PATIENT RESIDENCE THROUGHOUT CEL-ROF.
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 01/20/2016 |
122639430 |
01 |
A2 |
X SIGNED OFF |
04/30/2018 |
0014342 RA |
ZASKORSK |
|
NOT APPLICABLE
|
|
RENOVATION TO EXISTING NON-PROFIT PATIENT RESIDENCE THROUGHOUT CEL-ROF.
|
|
Work on Floor(s): BAS,ROF 001 thru 011
|
| 09/13/2015 |
121192958 |
03 |
A1 |
X SIGNED OFF |
09/11/2018 |
0067955 PE |
O'HANLON |
|
GRANTED 06/08/2016
|
|
STRUCTURAL WORK ON 002-004, 007-011TH FLOORS AND ROF IN CONJUNCTION WITH
|
|
Work on Floor(s): ROF 002 thru 004 007 thru 011
|
| 09/13/2015 |
121192958 |
02 |
A1 |
J P/E DISAPPROVED |
11/30/2015 |
0082724 PE |
BRENNAN |
|
GRANTED 06/08/2016
|
|
DOC WITHDRAWN 04/25/2016 MECHANICAL AND PLUBMING WORK ON FLOORS 001-011 AN
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 07/31/2015 |
121845593 |
05 |
A2 |
P APPROVED |
08/05/2015 |
|
CHRISTOF |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 013
|
| 07/10/2015 |
121192958 |
01 |
A1 |
X SIGNED OFF |
09/11/2018 |
0014342 RA |
ZASKORSK |
|
GRANTED 06/08/2016
|
|
ENLARGEMENT AND RENOVATION OF AN EXISTING RESIDENTIAL AND COMMUNITY FACILI
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 03/24/2015 |
121845593 |
04 |
A2 |
P APPROVED |
03/26/2015 |
|
CHRISTOF |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 013
|
| 12/04/2014 |
121845593 |
03 |
A2 |
P APPROVED |
12/05/2014 |
|
CHRISTOF |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 013
|
| 07/02/2014 |
122026538 |
01 |
A2 |
X SIGNED OFF |
02/20/2018 |
0058648 PE |
CHRISTOF |
|
NOT APPLICABLE
|
|
FUEL OIL TANK INSTALLATION. 275 GAL TANK FOR EMERGENCY GENERATOR. THERE WI
|
|
Work on Floor(s): CEL
|
| 05/19/2014 |
122013178 |
01 |
A2 |
X SIGNED OFF |
09/10/2014 |
0022288 RA |
PARANGI |
|
NOT APPLICABLE
|
|
FILING HEREWITH TO REMOVE EXISTING TRAY CEILING AND REPLACE WITH NEW FLAT
|
|
Work on Floor(s): LOB
|