| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 01/16/2020 |
123902116 |
01 |
A2 |
J P/E DISAPPROVED |
01/21/2020 |
0026466 RA |
ROTHSTEI |
|
NOT APPLICABLE
|
|
REMODEL APT 1 ON THE FIRST FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
|
|
Work on Floor(s): 001
|
| 03/29/2019 |
140716287 |
02 |
A2 |
P APPROVED |
09/23/2019 |
0100581 PE |
LAW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002
|
| 08/21/2018 |
123234525 |
01 |
A2 |
X SIGNED OFF |
10/17/2018 |
0087243 PE |
WONG |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION OF APT 5 ON 3RD FL. WITH PARTITION AND PLUMBING WORK.
|
|
Work on Floor(s): 003
|
| 04/19/2018 |
123104942 |
02 |
A2 |
P APPROVED |
04/25/2018 |
|
LANGER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP,CEL 001 thru 005
|
| 01/23/2018 |
122940416 |
04 |
A2 |
P APPROVED |
01/24/2018 |
|
ZHU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 004
|
| 01/23/2018 |
122802556 |
03 |
A2 |
P APPROVED |
01/24/2018 |
|
ZHU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 01/23/2018 |
123094230 |
03 |
A2 |
P APPROVED |
01/24/2018 |
|
ZHU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002
|
| 12/01/2017 |
123094230 |
02 |
A2 |
P APPROVED |
12/04/2017 |
|
ZHU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002
|
| 12/01/2017 |
122802556 |
02 |
A2 |
P APPROVED |
12/04/2017 |
|
ZHU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 12/01/2017 |
122940416 |
03 |
A2 |
P APPROVED |
12/04/2017 |
|
ZHU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 004
|
| 11/14/2017 |
140716287 |
01 |
A2 |
X SIGNED OFF |
09/24/2019 |
0100581 PE |
LAW |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION ON EXISTING APARTMENT 4 ON 2ND FL. AS PLAN. PAINTING,
|
|
Work on Floor(s): 002
|
| 08/04/2017 |
123104942 |
01 |
A2 |
R PERMIT-ENTIRE |
08/04/2017 |
0044575 PE |
LANGER |
|
NOT APPLICABLE
|
|
REMOVE EXISTING 10 GAS METERS FROM CELLAR & INSTALL TWO NEW METERS AT OSP.
|
|
Work on Floor(s): OSP,CEL 001 thru 005
|
| 05/05/2017 |
123094230 |
01 |
A2 |
X SIGNED OFF |
08/02/2018 |
0089565 PE |
ZHU |
|
NOT APPLICABLE
|
|
JOB FILED FOR EXISTING APT #3 @2ND FLOOR INTERIOR RENOVATION: RELOCATE & I
|
|
Work on Floor(s): 002
|
| 12/12/2016 |
122940416 |
02 |
A2 |
P APPROVED |
12/13/2016 |
|
ZHU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 004
|
| 12/12/2016 |
122802556 |
01 |
A2 |
X SIGNED OFF |
05/23/2018 |
0089565 PE |
ZHU |
|
NOT APPLICABLE
|
|
JOB FILED FOR EXISTING APT #2 @1ST FLOOR INTERIOR RENOVATION: RELOCATE & I
|
|
Work on Floor(s): 001
|
| 11/16/2016 |
122940416 |
01 |
A2 |
X SIGNED OFF |
05/23/2018 |
0089565 PE |
ZHU |
|
NOT APPLICABLE
|
|
JOB FILED FOR EXISTING APT #7 @4TH FLOOR INTERIOR RENOVATION: RELOCATE & I
|
|
Work on Floor(s): 004
|
| 09/27/2016 |
140555218 |
01 |
A2 |
P APPROVED |
09/29/2016 |
0087737 PE |
SO |
|
NOT APPLICABLE
|
|
PLUMBING PLAN IN CONJUNCTION TO JOB# 140475527. NO CHANGE IN USE, OCCUPANC
|
|
Work on Floor(s): 005
|
| 06/10/2016 |
140507404 |
01 |
A3 |
X SIGNED OFF |
11/29/2016 |
0080350 PE |
SOLTANIZ |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED FOR NEW BUILDING AS PER
|
|
Work on Floor(s): OSP
|
| 06/08/2016 |
122668577 |
01 |
A2 |
R PERMIT-ENTIRE |
08/10/2016 |
0093345 PE |
WEINSTEI |
|
NOT APPLICABLE
|
|
PROPOSED LIMITED EXTGERIOR REPAIRS AS INDICATED ON PLANS. NO CHANGE IN USE
|
|
Work on Floor(s): 001 thru 005
|
| 04/29/2016 |
122772721 |
01 |
A2 |
R PERMIT-ENTIRE |
04/29/2016 |
0081186 PE |
BILLAH |
|
NOT APPLICABLE
|
|
OIL GAS CONVERSION IN CELLAR INSTALL NEW HEATING SYSTEM INCLUDING 1 BOILER
|
|
Work on Floor(s): CEL
|
| 03/27/2016 |
140475527 |
01 |
A2 |
X SIGNED OFF |
06/29/2017 |
0087737 PE |
SO |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION ON EXISTING APARTMENTS 9 AND 10 AS PER PLAN. PARTITION
|
|
Work on Floor(s): 005
|