| 07/28/2021 |
141004268 |
01 |
A2 |
X SIGNED OFF |
12/02/2021 |
0089068 PE |
MAHANGU |
|
NOT APPLICABLE
|
|
INSTALL SOLAR PV SYSTEM ON THE EXISTING ROOFTOP. NO CHANGES TO USE, EGRESS
|
|
Work on Floor(s): CEL,ROF
|
| 02/25/2020 |
123100651 |
05 |
A1 |
P APPROVED |
02/27/2020 |
|
BERMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
| 04/24/2019 |
123100651 |
04 |
A1 |
P APPROVED |
07/03/2019 |
0070045 PE |
LOFTI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
| 12/11/2017 |
123100651 |
03 |
A1 |
P APPROVED |
07/24/2018 |
|
BERMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
| 06/21/2017 |
123100651 |
02 |
A1 |
X SIGNED OFF |
03/10/2020 |
0070045 PE |
LOFTI |
|
NOT APPLICABLE
|
|
SUBSEQUENT DOCUMENT FOR MECHANICAL, PLUMBING AND SPRINKLER WORK FOR ALTERA
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
| 06/21/2017 |
123100651 |
01 |
A1 |
X SIGNED OFF |
03/10/2020 |
0036223 RA |
BERMAN |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION OF THE CELLAR, 1ST, 2ND, 3RD FLOORS. WORK TO INCLUDE
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
| 06/06/2017 |
121227001 |
01 |
A2 |
X SIGNED OFF |
10/13/2017 |
0036223 RA |
BERMAN |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION OF THE CELLAR, 1ST, 2ND, AND 3RD FLOORS. WORK INCLUDES
|
|
Work on Floor(s): BAS,ROF 001 thru 003
|
| 05/04/2017 |
123092740 |
02 |
A2 |
J P/E DISAPPROVED |
05/30/2017 |
0070045 PE |
LOFTI |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 07/31/2017 SUBSEQUENT APPLICATION FOR MECHANICAL, PLUMBING,
|
|
Work on Floor(s): BAS,ROF 001 thru 003
|
| 05/04/2017 |
123092740 |
01 |
A2 |
J P/E DISAPPROVED |
05/30/2017 |
0036223 RA |
BERMAN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 07/31/2017 ARCHITECTURAL RENOVATIONS TO BUILDING. RENOVATION
|
|
Work on Floor(s): BAS,ROF 001 thru 003
|
| 11/06/2008 |
104282759 |
09 |
A2 |
P APPROVED |
11/07/2008 |
|
DeLorenz |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001 thru 003
|
| 09/19/2008 |
104282759 |
08 |
A2 |
P APPROVED |
09/19/2008 |
|
DeLorenz |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001 thru 003
|
| 07/25/2008 |
104282759 |
07 |
A2 |
P APPROVED |
07/25/2008 |
|
DeLorenz |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001 thru 003
|
| 07/07/2008 |
104282759 |
06 |
A2 |
P APPROVED |
07/22/2008 |
|
DeLorenz |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001 thru 003
|
| 12/05/2007 |
104282759 |
05 |
A2 |
P APPROVED |
12/06/2007 |
0051702 PE |
DeLorenz |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001 thru 003
|
| 10/29/2007 |
104282759 |
04 |
A2 |
P APPROVED |
11/08/2007 |
0051702 PE |
DeLorenz |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001 thru 003
|
| 09/20/2007 |
104282759 |
03 |
A2 |
P APPROVED |
09/26/2007 |
0051702 PE |
DeLorenz |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001 thru 003
|
| 01/29/2007 |
104662385 |
01 |
A2 |
X SIGNED OFF |
12/02/2016 |
0051702 PE |
DeLORENZ |
|
NOT APPLICABLE
|
|
EXTEND EXISTING SPRINKLER SYSTEM TO ADDITIONAL ROOMS. ADDING PIPING AND 22
|
|
Work on Floor(s): CEL 001 thru 003
|
| 11/25/2005 |
104282759 |
02 |
A2 |
X SIGNED OFF |
05/24/2016 |
0051702 PE |
DeLorenz |
|
NOT APPLICABLE
|
|
Provide design for the apts, in the building to include: gas piping, plum
|
|
Work on Floor(s): 001 thru 003
|
| 11/25/2005 |
104282759 |
01 |
A2 |
X SIGNED OFF |
05/24/2016 |
0007343 RA |
Calwil |
|
NOT APPLICABLE
|
|
Reduce the existing 6 apts to a 4 apts building. Create a duplex apt at 1
|
|
Work on Floor(s): 001 thru 003
|