| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 05/10/2007 |
104610798 |
03 |
A2 |
P APPROVED |
05/11/2007 |
0014928 RA |
Dupuy |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 ALTERATIONT TYPE II IS BEING FILED HEREW IT
|
|
Work on Floor(s): CEL
|
| 02/20/2007 |
104610798 |
02 |
A2 |
P APPROVED |
02/20/2007 |
0014928 RA |
Dupuy |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 11/22/2006 |
104610798 |
01 |
A2 |
X SIGNED OFF |
07/05/2007 |
0014928 RA |
Dupuy |
|
NOT APPLICABLE
|
|
ALTERATIONT TYPE II IS BEING FILED HEREW ITH TO INSTALL 6 PLUMBING
|
|
Work on Floor(s): CEL
|
| 07/27/2006 |
104498768 |
01 |
SC |
U COMPLETED |
07/28/2006 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 05/11/2006 |
104063371 |
02 |
A2 |
P APPROVED |
05/12/2006 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): BAS,PEN 001 thru 004
|
| 05/09/2006 |
103943235 |
05 |
A1 |
P APPROVED |
05/12/2006 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 03/21/2006 |
103943235 |
04 |
A1 |
P APPROVED |
03/23/2006 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 11/02/2005 |
104256662 |
01 |
A2 |
X SIGNED OFF |
08/15/2006 |
0013747 RA |
Negron/D |
|
NOT APPLICABLE
|
|
Proposed Boiler application inconjunction with Alt 1 Application. No chang
|
|
Work on Floor(s): CEL 001 thru 004
|
| 10/06/2005 |
103943235 |
03 |
A1 |
P APPROVED |
10/11/2005 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 05/31/2005 |
103960046 |
02 |
A2 |
P APPROVED |
09/06/2005 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,001,002,003,004 001 thru 004
|
| 05/31/2005 |
103943235 |
02 |
A1 |
P APPROVED |
10/04/2005 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 04/15/2005 |
104063371 |
01 |
A2 |
X SIGNED OFF |
08/15/2006 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
Application being filed in conjunction with Alteration Type 1 Application
|
|
Work on Floor(s): BAS,PEN 001 thru 004
|
| 02/11/2005 |
104039103 |
01 |
A3 |
R PERMIT-ENTIRE |
02/14/2005 |
OT |
ZAHARIA |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED 35' DURING NEW BUILDING
|
|
Work on Floor(s): 001
|
| 02/11/2005 |
104039096 |
01 |
A3 |
R PERMIT-ENTIRE |
02/14/2005 |
OT |
ZAHARIA |
|
NOT APPLICABLE
|
|
INSTALLATION OF A SCAFFOLD 35 X 40'-50' HIGH DURING FACADE REPAIR. . NO
|
|
Work on Floor(s): 001
|
| 11/03/2004 |
103960046 |
01 |
A2 |
X SIGNED OFF |
08/15/2006 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
Proposed Horizontal and Vertical enlargement is in conjunction with the
|
|
Work on Floor(s): CEL,BAS,001,002,003,004 001 thru 004
|
| 10/08/2004 |
103943235 |
01 |
A1 |
X SIGNED OFF |
08/23/2006 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
Interior gut rehab. for two existing buildings also merging two lots into
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 09/16/2004 |
103924700 |
01 |
A1 |
P APPROVED |
09/17/2004 |
0013747 RA |
Danois |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/31/2005 Interior gut rehab. Obtain new Certificate of Oc
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 01/06/2004 |
103623697 |
01 |
DM |
R PERMIT-ENTIRE |
01/06/2004 |
|
CLARKE |
|
NOT APPLICABLE
|
|
Work on Floor(s): 4
|
| 01/06/2004 |
103623688 |
01 |
DM |
B A/P UNPAID |
01/06/2004 |
0016357 RA |
COGEN |
|
NOT APPLICABLE
|
|
Work on Floor(s): ENT
|