FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
04/01/2015 |
121133308 |
08 |
A1 |
P APPROVED |
04/13/2015 |
|
BAIRD |
|
GRANTED 02/20/2013
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
02/09/2015 |
121133308 |
07 |
A1 |
P APPROVED |
03/05/2015 |
|
BAIRD |
|
GRANTED 02/20/2013
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
09/09/2014 |
121133308 |
06 |
A1 |
P APPROVED |
09/15/2014 |
0054305 PE |
AMBROSIN |
|
GRANTED 02/20/2013
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
08/28/2014 |
121133308 |
05 |
A1 |
P APPROVED |
08/29/2014 |
0054305 PE |
AMBROSIN |
|
GRANTED 02/20/2013
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
08/27/2014 |
121133308 |
04 |
A1 |
P APPROVED |
08/29/2014 |
|
BAIRD |
|
GRANTED 02/20/2013
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
05/14/2013 |
121451035 |
04 |
A2 |
P APPROVED |
06/06/2013 |
|
BAIRD |
|
GRANTED 02/07/2013
|
|
POST APPROVAL AMENDMENT FOR 01 ENLARGE CELLAR OF BUILDING HORIZONTALLY . N
|
|
Work on Floor(s): CEL
|
01/25/2013 |
121133308 |
03 |
A1 |
X SIGNED OFF |
05/01/2015 |
0072030 PE |
FALCONER |
|
GRANTED 02/20/2013
|
|
FOUNDATION AND STRUCTURAL WORK FILED SUBSEQUENT TO ALT I #121133308 FOR TH
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
01/25/2013 |
121133308 |
02 |
A1 |
X SIGNED OFF |
05/01/2015 |
0054305 PE |
AMBROSIN |
|
GRANTED 02/20/2013
|
|
MECHANICAL AND PLUMBING MODIFICATIONS SUBSEQUENT TO ALT I# 121133308 FOR T
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
01/11/2013 |
121451035 |
03 |
A2 |
X SIGNED OFF |
02/10/2015 |
0089733 PE |
AMEY |
|
GRANTED 02/07/2013
|
|
APPLICATION FILED FOR SUPPORT OF EXCAVATION. COSTS COVERED UNDER DOC 02.
|
|
Work on Floor(s): CEL
|
12/05/2012 |
121451035 |
02 |
A2 |
X SIGNED OFF |
02/10/2015 |
0072030 PE |
FALCONER |
|
GRANTED 02/07/2013
|
|
STRUCTURAL WORK ASSOCIATED WITH HORIZONTAL ENLARGEMENT OF CELLAR.
|
|
Work on Floor(s): CEL
|
12/05/2012 |
121451035 |
01 |
A2 |
X SIGNED OFF |
02/10/2015 |
0029016 RA |
BAIRD |
|
GRANTED 02/07/2013
|
|
ENLARGE CELLAR OF BUILDING HORIZONTALLY . NO CHANGE TO ZONING FLOOR AREA.
|
|
Work on Floor(s): CEL
|
11/23/2012 |
121133291 |
03 |
A2 |
P APPROVED |
12/20/2012 |
|
BAIRD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 003
|
11/21/2012 |
121443599 |
01 |
A3 |
X SIGNED OFF |
03/25/2015 |
0016966 RA |
GALLO |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS, OR
|
|
Work on Floor(s): GRD
|
11/15/2012 |
140038885 |
01 |
A3 |
X SIGNED OFF |
03/25/2015 |
0016966 RA |
GALLO |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, E
|
|
Work on Floor(s): 002,003
|
11/09/2012 |
140037868 |
01 |
A3 |
H P/E IN PROCESS |
11/09/2012 |
0016966 RA |
GALLO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/15/2012 INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER P
|
|
Work on Floor(s): 002,003
|
11/09/2012 |
140037831 |
01 |
A3 |
H P/E IN PROCESS |
11/09/2012 |
0016966 RA |
GALLO |
|
NOT APPLICABLE
|
|
ADMIN CLOSED 01/08/2013 INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHA
|
|
Work on Floor(s): 002,003
|
09/24/2012 |
121133291 |
02 |
A2 |
P APPROVED |
09/26/2012 |
|
BAIRD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 APPLICATION FILED FOR MINOR PARTITION REMOV
|
|
Work on Floor(s): 001 thru 003
|
06/29/2012 |
121133291 |
01 |
A2 |
X SIGNED OFF |
09/25/2014 |
0029016 RA |
BAIRD |
|
NOT APPLICABLE
|
|
APPLICATION FILED FOR MINOR PARTITION REMOVAL ON THE THIRD FLOOR. ALSO INS
|
|
Work on Floor(s): 001 thru 003
|
06/29/2012 |
121133308 |
01 |
A1 |
X SIGNED OFF |
05/01/2015 |
0029016 RA |
BAIRD |
|
GRANTED 02/20/2013
|
|
APPLICATION FILED TO CHANGE USE OF BUILDING INCLUDING REAR BUILDING TO SIN
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
04/20/2012 |
121053581 |
01 |
A3 |
X SIGNED OFF |
08/02/2012 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED A TOTAL OF APPROXIMATELY 35 L.F.
|
|
Work on Floor(s): OSP
|
05/29/2009 |
120050470 |
01 |
A3 |
X SIGNED OFF |
02/23/2010 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED 26' LONG X 13' WIDE X 14' HIGH
|
|
Work on Floor(s): 001
|
04/20/2009 |
120018952 |
01 |
A2 |
X SIGNED OFF |
04/14/2011 |
0016554 RA |
ZENREICH |
|
NOT APPLICABLE
|
|
INSTALL A NEW AC SYSTEM AND DUNNAGE ON ROOF, NEW DUCT WORK ON THIRD FLOOR.
|
|
Work on Floor(s): 003,ROF
|
03/12/2009 |
110476486 |
01 |
A1 |
X SIGNED OFF |
06/17/2011 |
0016554 RA |
ZENREICH |
|
NOT APPLICABLE
|
|
FILING HERE A NO WORK ALTERATION. THIS APPLICATION IS TO FILE TO RENEW BSA
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
07/22/1997 |
101579720 |
01 |
A3 |
X SIGNED OFF |
05/10/2010 |
0654301 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF SHED 25' DURING FACADE REPAIR.NO CHANGE IN USE
|
|
Work on Floor(s): GRD
|