| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 01/21/2026 |
123392168 |
11 |
A1 |
G PAA FEE DUE |
01/21/2026 |
|
MAKOOI |
|
GRANTED 05/14/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 06/11/2021 |
123392168 |
10 |
A1 |
P APPROVED |
10/05/2021 |
0079188 PE |
SCHELL |
|
GRANTED 05/14/2018
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): BAS,ROF 001 thru 005
|
| 01/27/2021 |
123392168 |
09 |
A1 |
P APPROVED |
04/27/2021 |
|
MAKOOI |
|
GRANTED 05/14/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 02/10/2020 |
123392168 |
08 |
A1 |
P APPROVED |
02/12/2020 |
0088692 PE |
AUYEUNG |
|
GRANTED 05/14/2018
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 10/03/2019 |
123392168 |
07 |
A1 |
P APPROVED |
10/08/2019 |
0079188 PE |
SCHELL |
|
GRANTED 05/14/2018
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): BAS,ROF 001 thru 005
|
| 03/25/2019 |
123392168 |
06 |
A1 |
P APPROVED |
04/19/2019 |
|
MAKOOI |
|
GRANTED 05/14/2018
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 04/17/2018 |
123502557 |
01 |
A2 |
R PERMIT-ENTIRE |
10/23/2019 |
0079188 PE |
SCHELL |
|
NOT APPLICABLE
|
|
INSTALLATION OF MANUAL/AUTOMATIC SMOKE/HEAT DETECTION SPRINKLER ALARM SYST
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 04/04/2018 |
123392168 |
05 |
A1 |
R PERMIT-ENTIRE |
07/06/2018 |
0088692 PE |
AUYEUNG |
|
GRANTED 05/14/2018
|
|
SUPPORT OF EXCAVATION IN CONJUNCTION WITH ALT-1 VERTICAL ENLARGEMENT AND
|
|
Work on Floor(s): CEL 001 thru 005
|
| 04/04/2018 |
123392168 |
04 |
A1 |
R PERMIT-ENTIRE |
07/06/2018 |
0079188 PE |
SCHELL |
|
GRANTED 05/14/2018
|
|
DOC WITHDRAWN 05/30/2023 INSTALLATION OF BOILER IN CONJUNCTION WITH THE RE
|
|
Work on Floor(s): BAS
|
| 04/04/2018 |
123392168 |
03 |
A1 |
R PERMIT-ENTIRE |
07/06/2018 |
0088692 PE |
AUYEUNG |
|
GRANTED 05/14/2018
|
|
STRUCTURAL WORK IN CONJUNCTION WITH ALT-1 VERTICAL ENLARGEMENT AND CONVERS
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 04/04/2018 |
123392168 |
02 |
A1 |
R PERMIT-ENTIRE |
08/19/2019 |
0079188 PE |
SCHELL |
|
GRANTED 05/14/2018
|
|
PLUMBING, MECHANICAL AND SPRINKLER APPLICATION IN CONJUNCTION WITH THE
|
|
Work on Floor(s): BAS,ROF 001 thru 005
|
| 04/04/2018 |
123392168 |
01 |
A1 |
R PERMIT-ENTIRE |
12/30/2025 |
0034686 RA |
MAKOOI |
|
GRANTED 05/14/2018
|
|
HEREBY FILING VERTICAL ENLARGEMENT AND CONVERSION OF RESIDENTIAL BUILDING
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 04/29/2015 |
122380299 |
01 |
A2 |
P APPROVED |
04/30/2015 |
0018385 RA |
PELES |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/01/2016 COMBINATION OF 4 APARTMENTS INTO 2 , APARTMENTS
|
|
Work on Floor(s): 004
|
| 03/30/2006 |
104392319 |
01 |
A2 |
X SIGNED OFF |
05/26/2006 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
REPLACE BOILER AND OIL BURNER. (NYC BOILER NO. MD5733-01) FILED IN
|
|
Work on Floor(s): CEL
|