| 10/03/2017 |
123159072 |
01 |
A2 |
X SIGNED OFF |
02/14/2020 |
0052081 PE |
ZINGHER |
|
NOT APPLICABLE
|
|
APPLICATION FILE TO REPAIR CHIMNEY AT ROOF. NO CHANGE IN USE, OCCUPANCY OR
|
|
Work on Floor(s): RF, 004
|
| 06/15/2017 |
121233414 |
01 |
A3 |
X SIGNED OFF |
07/10/2018 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGR
|
|
Work on Floor(s): OSP
|
| 06/14/2017 |
121242404 |
01 |
A3 |
X SIGNED OFF |
07/10/2018 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE
|
|
Work on Floor(s): OSP
|
| 07/08/2016 |
104450407 |
08 |
A1 |
P APPROVED |
07/11/2016 |
|
SEHIC |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN,ROF 001 thru 005
|
| 05/24/2016 |
104450407 |
07 |
A1 |
P APPROVED |
06/29/2016 |
0073350 PE |
LEVIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,PEN,ROF 001 thru 004
|
| 07/19/2013 |
121378428 |
02 |
A2 |
P APPROVED |
07/31/2013 |
|
LEVIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 06/19/2013 |
120832956 |
03 |
A2 |
P APPROVED |
08/21/2013 |
|
LIOTTA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002
|
| 01/11/2013 |
104450407 |
06 |
A1 |
P APPROVED |
01/14/2013 |
|
SEHIC |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 CONVERT EXISTING MIXED USE COMMERCIAL (2) F
|
|
Work on Floor(s): CEL,PEN,ROF 001 thru 005
|
| 12/27/2012 |
120832956 |
02 |
A2 |
P APPROVED |
01/08/2013 |
|
LEVIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 FILING APPLICATION FOR INSTALLATION OF SPRI
|
|
Work on Floor(s): CEL,001
|
| 12/07/2012 |
121400215 |
01 |
A2 |
X SIGNED OFF |
09/17/2015 |
0052081 PE |
ZINGHER |
|
NOT APPLICABLE
|
|
THIS APPLICATION IS BEING FILED FOR THE INSTALLATION OF NEW FIRE ESCAPE.
|
|
Work on Floor(s): 002,003,004
|
| 09/20/2012 |
121378428 |
01 |
A2 |
X SIGNED OFF |
08/15/2016 |
0073350 PE |
LEVIN |
|
NOT APPLICABLE
|
|
THIS APPLICATION IS BEING FILED FOR PLUMBING WORK ON THE CEL, 001-005 AS P
|
|
Work on Floor(s): CEL 001 thru 005
|
| 09/21/2011 |
120832956 |
01 |
A2 |
X SIGNED OFF |
03/01/2016 |
0048918 PE |
LIOTTA |
|
NOT APPLICABLE
|
|
FILING APPLICATION FOR INSTALLATION OF SPRINKLER HEADS AT CELLAR LEVEL, AS
|
|
Work on Floor(s): CEL,001,002
|
| 08/11/2009 |
104450407 |
05 |
A1 |
P APPROVED |
08/14/2009 |
0029622 RA |
SEHIC |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN,ROF 001 thru 004
|
| 03/03/2009 |
110462632 |
01 |
A2 |
X SIGNED OFF |
08/24/2009 |
0052081 PE |
ZINGHER |
|
NOT APPLICABLE
|
|
TEMPORARY PLATFORMS FOR ROOF REPAIRS. NO CHANGE IN USE, EGRESS, OR OCCUPA
|
|
Work on Floor(s): ROF
|
| 09/16/2008 |
110248633 |
01 |
A3 |
X SIGNED OFF |
08/24/2009 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD 90' LONG X 42'-53' HIGH (50'-57' HIGH FROM G
|
|
Work on Floor(s): 001
|
| 07/25/2008 |
104450407 |
04 |
A1 |
P APPROVED |
07/25/2008 |
0020478 |
LEDER-LU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN,ROF 001 thru 004
|
| 05/08/2008 |
110163028 |
01 |
A3 |
X SIGNED OFF |
10/22/2009 |
OT |
HALLICK |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD 90' LONG X 36' HIGH FROM GRADE DURING EXTERI
|
|
Work on Floor(s): 1
|
| 05/08/2008 |
110163000 |
01 |
A3 |
X SIGNED OFF |
10/22/2009 |
OT |
HALLICK |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED 70' LONG DURING EXTERIOR MASONRY
|
|
Work on Floor(s): 1
|
| 02/08/2007 |
104450407 |
03 |
A1 |
P APPROVED |
02/14/2007 |
0073350 PE |
LEVIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,PEN,ROF 001 thru 004
|
| 07/06/2006 |
104482677 |
01 |
A3 |
X SIGNED OFF |
12/08/2009 |
OT |
MATTHEWS |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF 70 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED FOR
|
|
Work on Floor(s): OSP
|
| 06/08/2006 |
104450407 |
02 |
A1 |
X SIGNED OFF |
10/27/2016 |
0073350 PE |
LEVIN |
|
NOT APPLICABLE
|
|
SUBSEQUENT FILING FOR PLUMBING AND MECHANICAL WORK.
|
|
Work on Floor(s): CEL,PEN,ROF 001 thru 004
|
| 06/07/2006 |
104450407 |
01 |
A1 |
X SIGNED OFF |
10/27/2016 |
0029622 RA |
SEHIC |
|
NOT APPLICABLE
|
|
CONVERT EXISTING MIXED USE COMMERCIAL (2) FAMILY RESIDENTIAL BUILDING INTO
|
|
Work on Floor(s): CEL,PEN,ROF 001 thru 005
|
| 10/15/2003 |
103585531 |
01 |
A1 |
J P/E DISAPPROVED |
11/14/2003 |
0024039 RA |
TRUEMMER |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 08/13/2009 ENLARGE EXISTING BUILDING OBTAIN NEW CER TIFICAT
|
|
Work on Floor(s): 003,004,005
|
| 10/29/2001 |
103021882 |
01 |
A2 |
X SIGNED OFF |
03/08/2016 |
0027492 RA |
SLEIMAN |
|
NOT APPLICABLE
|
|
RESTORATION OF BROWNSTONE EXTERIOR STAIR AS PER PLANS. NO CHANGE IN USE,
|
|
Work on Floor(s): FAC,OSP
|
| 07/14/1998 |
101853727 |
01 |
A2 |
X SIGNED OFF |
12/31/2015 |
0023289 RA |
Davis |
|
NOT APPLICABLE
|
|
Chimney Repair. No change in use, egress or occupancy.
|
|
Work on Floor(s): 006
|
| 06/24/1998 |
101893872 |
01 |
A3 |
X SIGNED OFF |
07/02/2009 |
|
LAMENDOL |
|
NOT APPLICABLE
|
|
INSTALLATION OF SHED 100'DURING REPAIR SHED TO COMPLY WITH LL33/91
|
|
Work on Floor(s): GRD
|