| FILE DATE |
JOB # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
| 08/03/2018 |
140790464 |
PR |
I LAA SIGNED OFF |
01/23/2019 |
MP 001790 |
SANGIRAY |
|
REPLACE APPROX 10FT OF 2" NHCI PIPE FOR WASTE AND VENT LINES AND APPROX 10
|
|
Work on Floor(s): 012
|
| 02/16/2018 |
140741062 |
PR |
I LAA SIGNED OFF |
05/30/2018 |
MP 002267 |
KARDASAK |
|
IN APT 10B ON THE 10TH FLOOR REPLACE ON EXISTING ROUGHING (1) TOILET, (1)
|
|
Work on Floor(s): 010
|
| 01/26/2018 |
140734784 |
PR |
I LAA SIGNED OFF |
04/12/2018 |
MP 002129 |
LIOTTA |
|
IN APARTMENT 3B ON THE 3RD FLOOR, IN THE BATHROOM WILL REPLACE TUB AND SHO
|
|
Work on Floor(s): 003
|
| 12/17/2015 |
140441948 |
PR |
I LAA SIGNED OFF |
05/16/2016 |
MP 001537 |
KORBL JR |
|
AMENDMENT TO SCOPE OF WORK SHOWN ON LAA#140441948. SCOPE IS NOW: 1- WATER
|
|
Work on Floor(s): 012
|
| 09/25/2015 |
140407753 |
PR |
I LAA SIGNED OFF |
03/11/2016 |
MP 000872 |
DIETZ |
|
IN APT.10H ON THE 10TH FLOOR GUEST BATHROOM REPLACE 1 SINK,1 TOILET ON EXI
|
|
Work on Floor(s): 010
|
| 09/04/2015 |
121886502 |
PR |
I LAA SIGNED OFF |
11/23/2015 |
OBI 002735 |
EISENBER |
|
INSTALLATION OF A TEMPORARY MOBILER STEAM TRAILER OUTSIDE THE BUILDING TO
|
|
Work on Floor(s): OSP
|
| 10/27/2014 |
140273040 |
PR |
I LAA SIGNED OFF |
02/12/2015 |
MP 001177 |
O'GRADY |
|
WE WILL ON THE SAME ROUGH INSTALL NEW KITCHEN SINK AND DISHWASHER , WITH N
|
|
Work on Floor(s): 9TH
|
| 10/14/2014 |
140267707 |
PR |
E LAA FILED |
10/14/2014 |
MP 001177 |
O'GRADY |
|
WE WILL AT THE EXISTING LOCATION INSTALL NEW HOT,COLD CONTROL VALVES FOR T
|
|
Work on Floor(s): 6TH
|
| 09/22/2014 |
140257095 |
PR |
I LAA SIGNED OFF |
05/01/2015 |
MP 001342 |
DISABATO |
|
IN APARTMENT 1G ON THE FIRST FLOOR REPLACE LAV AND TOILET ON EXISTING W/S
|
|
Work on Floor(s): 001
|
| 07/01/2014 |
140220124 |
PR |
I LAA SIGNED OFF |
01/12/2016 |
MP 001316 |
VALERA |
|
REPLACEMENT OF EXISTING PLUMBING FIXTURES ON EXISTING BATHROOMS ON EXISTIN
|
| 02/21/2014 |
140165238 |
PR |
I LAA SIGNED OFF |
04/07/2014 |
MP 001790 |
SANGIRAY |
|
REPLACE (1) SINK & (1) STOVE IN KITCHEN AND (1) LAVATORY IN BATHROOM ALL O
|
|
Work on Floor(s): 006
|
| 07/11/2013 |
121646308 |
PR |
I LAA SIGNED OFF |
09/27/2013 |
MP 001268 |
ALTADONN |
|
SUPPLY AND INSTALL NEW 4" RPZ WATTS 957; MEA #65-03-E, DEP APPROVAL #11031
|
|
Work on Floor(s): CEL
|
| 06/03/2013 |
140084361 |
PR |
I LAA SIGNED OFF |
08/22/2013 |
OBI 001509 |
BENDJOUY |
|
CHANGE GRADE OF FUEL FROM #6 OIL TO #4 OIL. WE WILL REMOVE THE PRE-HEATER
|
|
Work on Floor(s): BAS
|
| 01/27/2012 |
140007409 |
PR |
E LAA FILED |
01/27/2012 |
MP 001268 |
ALTADONN |
|
SUPPLY AND INSTALL NEW 4" RPZ WATTS 957; MEA# 65-03-E, DEP APPROVAL # 1103
|
|
Work on Floor(s): CEL
|
| 07/21/2010 |
110515568 |
PR |
I LAA SIGNED OFF |
12/21/2010 |
MP 001101 |
KOUMPARO |
|
REMOVE EXISTING 1-WC, 1-LAVATORY, 1-BATHTUB AND DISPOSE OF THEM PROPERLY.
|
|
Work on Floor(s): 009
|
| 01/21/2010 |
110497409 |
PR |
I LAA SIGNED OFF |
07/06/2010 |
MP 001210 |
DIAZ |
|
REPLACE FIXTURES ON EX'G ROUGHING, REPLACING 1 BATHTUB, WITH SHOWER BODY,
|
|
Work on Floor(s): 012
|
| 06/02/2008 |
103885299 |
PR |
I LAA SIGNED OFF |
11/15/2010 |
MP 001210 |
DIAZ |
|
REPLACE FIXTURES ON EXIST.ROUGHING.REPLACE 1 BATH TUB W/SHOWER BODY 1 TOIL
|
|
Work on Floor(s): 012
|
| 04/24/2008 |
103882666 |
PR |
E LAA FILED |
04/24/2008 |
MP 001490 |
LOMBARDO |
|
DIRECT REPLACE ON EXIST. ROUGHING:1 KITCHEN SINK,BATH SINK, TANK BOWL, BAT
|
|
Work on Floor(s): 008
|
| 08/24/2007 |
102416431 |
PR |
E LAA FILED |
08/24/2007 |
MP 000825 |
TERDOSLA |
|
TO PLACE LAVATORY & WATER CLOSET ON EXISTING ROUGHING IN APT# 2H, 2ND FLR.
|
|
Work on Floor(s): 002
|
| 06/15/2006 |
102388578 |
PR |
E LAA FILED |
06/15/2006 |
MP 002020 |
YOHE |
|
REPLACE ON EXISTING ROUGHING 1 SINK, 1 DISHWASHER, 1 STOVE , 1 TOILET, 1 L
|
|
Work on Floor(s): 001
|
| 01/29/2001 |
102125763 |
PR |
I LAA SIGNED OFF |
03/02/2001 |
MP 001035 |
TUNE |
|
EXTEND THE GAS LINE 25 FT TO THE NEW COOK TOP/OVEN LOCATION.
|