| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 10/25/2021 |
123842002 |
03 |
A2 |
P APPROVED |
11/10/2021 |
|
ACCARDO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 NEW REMOVE/REPLACE MASONRY AND WINDOW LINTE
|
|
Work on Floor(s): FAC
|
| 12/16/2020 |
123045506 |
04 |
A2 |
P APPROVED |
12/21/2020 |
|
WILDER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 010,PEN
|
| 06/14/2020 |
123045506 |
03 |
A2 |
P APPROVED |
07/27/2020 |
|
WILDER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INTERIOR RENOVATION AND COMBINATION OF APAR
|
|
Work on Floor(s): 010,PEN
|
| 05/06/2020 |
123842002 |
02 |
A2 |
P APPROVED |
05/08/2020 |
0074584 PE |
ACCARDO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): FAC
|
| 02/18/2020 |
123842002 |
01 |
A2 |
X SIGNED OFF |
08/01/2022 |
0074584 PE |
ACCARDO |
|
NOT APPLICABLE
|
|
NEW REMOVE/REPLACE MASONRY AND WINDOW LINTELS,RE-POINT SPECIFIED MORTAR,JO
|
|
Work on Floor(s): FAC
|
| 08/13/2019 |
123692904 |
01 |
A2 |
X SIGNED OFF |
05/27/2020 |
0020199 RA |
BARUJEL |
|
NOT APPLICABLE
|
|
INTERIOR ALTERATIONS TO APT 7C (7TH FLOOR). REMOVAL / RELOCATION OF PARTIT
|
|
Work on Floor(s): 007
|
| 07/30/2019 |
140629513 |
07 |
A2 |
P APPROVED |
08/09/2019 |
|
CROSS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP
|
| 06/20/2019 |
123045506 |
01 |
A2 |
X SIGNED OFF |
04/19/2021 |
0037812 RA |
WILDER |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION AND COMBINATION OF APARTMENT 10F, 10G, 10H AND PHB IN
|
|
Work on Floor(s): 010,PEN
|
| 06/20/2019 |
123045506 |
02 |
A2 |
X SIGNED OFF |
04/19/2021 |
0091145 PE |
WALCOTT |
|
NOT APPLICABLE
|
|
INSTALLATION OF INTERIOR CONVENIENCE STAIR IN CONJUNCTION WITH APARTMENT
|
|
Work on Floor(s): 010,PEN
|
| 06/18/2019 |
140629513 |
06 |
A2 |
P APPROVED |
07/05/2019 |
|
CROSS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP
|
| 05/09/2019 |
140629513 |
05 |
A2 |
P APPROVED |
06/14/2019 |
0031026 RA |
CROSS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP
|
| 02/28/2019 |
140629513 |
04 |
A2 |
P APPROVED |
04/02/2019 |
0031026 RA |
CROSS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP
|
| 12/27/2018 |
123519353 |
01 |
A2 |
R PERMIT-ENTIRE |
03/15/2019 |
0039141 RA |
CHUA |
|
NOT APPLICABLE
|
|
INTERIOR ALTERATION TO APARTMENT 6G INCLUDING RELOCATION OF NON-BEARING
|
|
Work on Floor(s): 006
|
| 06/29/2018 |
140629513 |
03 |
A2 |
P APPROVED |
07/03/2018 |
|
CROSS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP
|
| 05/02/2018 |
140629513 |
02 |
A2 |
P APPROVED |
05/08/2018 |
|
CROSS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP
|
| 04/26/2017 |
140629513 |
01 |
A2 |
X SIGNED OFF |
08/26/2019 |
0031026 RA |
CROSS |
|
NOT APPLICABLE
|
|
PROVIDE NEW PAVEMENT, NEW SEATING PLATFORM, PLANTERS AND NEW GAS GRILL AT
|
|
Work on Floor(s): CEL,OSP
|
| 04/14/2017 |
140630342 |
01 |
A2 |
D A/P ENTIRE |
04/14/2017 |
0031026 RA |
CROSS |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/26/2017 PROVIDE NEW PAVEMENT, NEW SEATING PLATFORM, PLANT
|
|
Work on Floor(s): BAS
|
| 01/23/2017 |
140597628 |
01 |
A2 |
D A/P ENTIRE |
01/23/2017 |
0033766 RA |
HANER |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 01/23/2017 INTERIOR RENOVATION OF APARTMENT 6C AS PER PLANS
|
| 01/10/2017 |
122915596 |
01 |
A2 |
X SIGNED OFF |
10/03/2017 |
0023066 RA |
LIBASCI |
|
GRANTED 04/05/2017
|
|
RESPECTFULLY REQUEST TO ENLARGE CLOSET @ PENTHOUSE B.
|
|
Work on Floor(s): PHB
|
| 09/30/2015 |
122442972 |
02 |
A2 |
P APPROVED |
10/09/2015 |
|
KAUSHANS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 008
|
| 07/24/2015 |
122435365 |
01 |
A2 |
X SIGNED OFF |
04/07/2016 |
0027419 RA |
ABRAMOWI |
|
NOT APPLICABLE
|
|
MINOR RENOVATION OF APARTMENT #6H; CREATION OF NEW AC SLEEVE AND INSTALLAT
|
|
Work on Floor(s): 006
|
| 07/22/2015 |
122442972 |
01 |
A2 |
X SIGNED OFF |
03/21/2016 |
0023923 RA |
KAUSHANS |
|
NOT APPLICABLE
|
|
COMBINE APTS 8FGH. AS PER TPPN 3/97 MINOR CONSTRUCTION WORK AND PLUMBING
|
|
Work on Floor(s): 008
|
| 03/06/2015 |
122329131 |
01 |
A2 |
X SIGNED OFF |
09/14/2015 |
0031910 RA |
GRAVES |
|
NOT APPLICABLE
|
|
MINOR INTERIOR ALTERATION WORK IN APARTMENT 3GH. NO CHANGE TO OCCUPANCY,
|
|
Work on Floor(s): 003
|
| 05/29/2014 |
121945324 |
02 |
A2 |
P APPROVED |
07/29/2014 |
|
LEONG-AK |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): PH
|
| 04/03/2014 |
121945324 |
01 |
A2 |
X SIGNED OFF |
01/14/2015 |
0016682 RA |
LEONG-AK |
|
NOT APPLICABLE
|
|
RENOVATION OF PENTHOUSE B, ARCHITECTURAL AND PLUMBING WORK AS PER PLANS. N
|
|
Work on Floor(s): PH
|
| 08/12/2013 |
121746977 |
01 |
A2 |
X SIGNED OFF |
04/13/2015 |
0047135 PE |
GERMAIN |
|
NOT APPLICABLE
|
|
REPLACE (1) NEW BURNER ONTO EXISTING LP BOILER. CHANGE GRADE OF FUEL OIL F
|
|
Work on Floor(s): CEL
|
| 06/20/2013 |
121689510 |
01 |
A2 |
X SIGNED OFF |
02/03/2014 |
0033722 RA |
SEQUEIRA |
|
NOT APPLICABLE
|
|
RENOVATION TO APARTMENT. NO CHANGE IN USE OCCUPANCY OR EGRESS
|
|
Work on Floor(s): 009
|
| 02/06/2013 |
121428534 |
02 |
A2 |
P APPROVED |
02/13/2013 |
|
DEUTSCH |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002
|
| 12/03/2012 |
121428534 |
01 |
A2 |
X SIGNED OFF |
06/26/2013 |
0027303 RA |
DEUTSCH |
|
NOT APPLICABLE
|
|
HERE WITH FILING DRAWINGS SHOWING THE COMBINATION OF APARTMENTS 2B/2C. WOR
|
|
Work on Floor(s): 002
|
| 08/16/2012 |
120744524 |
03 |
A2 |
P APPROVED |
09/25/2012 |
|
HUMPHREY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 009
|
| 03/15/2012 |
121010146 |
01 |
A2 |
X SIGNED OFF |
07/18/2012 |
0745841 PE |
ACCARDO |
|
NOT APPLICABLE
|
|
REPAIR FENCING AND TOP OF THE WALL AT THE SOUTH WEST CORNER OF THE REAR YA
|
|
Work on Floor(s): OSP
|
| 11/21/2011 |
120744524 |
02 |
A2 |
P APPROVED |
01/17/2012 |
|
HUMPHREY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 009
|
| 08/10/2011 |
120744524 |
01 |
A2 |
X SIGNED OFF |
06/20/2016 |
0015384 RA |
HUMPHREY |
|
NOT APPLICABLE
|
|
MINOR ALTERATION OF APARTMENT; DEMOLITION OF NON-LOADBEARING PARTITIONS;
|
|
Work on Floor(s): 009
|
| 02/01/2011 |
120348169 |
02 |
A2 |
P APPROVED |
04/19/2011 |
|
DE LUNA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 009
|
| 01/26/2011 |
120587846 |
01 |
A2 |
X SIGNED OFF |
10/23/2013 |
0022927 RA |
CHABON |
|
NOT APPLICABLE
|
|
ALT-2 RENOVATION OF AN EXISTING RESIDENTIAL CO-OP APARTMENT. GENERAL
|
|
Work on Floor(s): 008
|
| 11/05/2010 |
120527475 |
01 |
A2 |
P APPROVED |
11/22/2010 |
0031606 RA |
CHINA |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/21/2011 FILING HEREWITH PLANS INDICATION INTERIOR RENOVAT
|
|
Work on Floor(s): 004
|
| 09/09/2010 |
120416647 |
01 |
A2 |
P APPROVED |
09/16/2010 |
0011397 RA |
DUNNING |
|
NOT APPLICABLE
|
|
REARRANGE EXISTING BATHROOM, INSTALL HUNG CEILING
|
|
Work on Floor(s): 010
|
| 06/29/2010 |
120397533 |
01 |
A2 |
X SIGNED OFF |
07/18/2012 |
0745841 PE |
ACCARDO |
|
NOT APPLICABLE
|
|
REMOVAL AND REPLACEMENT OF DAMAGED MASONRY, REPAIR AT NORTH PARAPET, WINDO
|
|
Work on Floor(s): ROF
|
| 05/07/2010 |
120348169 |
01 |
A2 |
X SIGNED OFF |
05/10/2011 |
0023851 RA |
DE LUNA |
|
NOT APPLICABLE
|
|
MINOR REMOVAL OF INTERIOR NON-BEARING PARTITION, NEW INTERIOR PARTITION.
|
|
Work on Floor(s): 009
|
| 05/03/2010 |
120107516 |
02 |
A3 |
P APPROVED |
05/24/2010 |
|
HULME |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF HEAVY DUTY SIDEWALK SHED A
|
|
Work on Floor(s): OSP
|