| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 02/28/2013 |
120092684 |
19 |
A1 |
P APPROVED |
03/05/2013 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 01/30/2013 |
120092684 |
18 |
A1 |
P APPROVED |
02/01/2013 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 12/27/2012 |
120092684 |
17 |
A1 |
P APPROVED |
01/08/2013 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 10/19/2012 |
120092684 |
16 |
A1 |
P APPROVED |
11/15/2012 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 08/09/2011 |
120783937 |
02 |
A2 |
P APPROVED |
08/15/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 08/02/2011 |
120092684 |
15 |
A1 |
P APPROVED |
08/10/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL 001 thru 005
|
| 08/02/2011 |
120783937 |
01 |
A2 |
X SIGNED OFF |
09/14/2011 |
0022194 RA |
HELD |
|
NOT APPLICABLE
|
|
INSTALL SPRINKLER HEADS AT LOT-LINE WINDOWS. NO CHANGE TO USE, OCCUPANCY
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 07/16/2011 |
120092684 |
14 |
A1 |
P APPROVED |
07/18/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL 001 thru 005
|
| 07/15/2011 |
120092684 |
13 |
A1 |
P APPROVED |
07/18/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 07/01/2011 |
120092684 |
12 |
A1 |
P APPROVED |
07/05/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL 001 thru 005
|
| 06/10/2011 |
120092684 |
11 |
A1 |
P APPROVED |
06/17/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 06/06/2011 |
120092684 |
10 |
A1 |
P APPROVED |
06/07/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 05/14/2011 |
120092684 |
09 |
A1 |
P APPROVED |
05/18/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL 001 thru 005
|
| 04/20/2011 |
120092684 |
08 |
A1 |
P APPROVED |
05/06/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 03/25/2011 |
120092684 |
07 |
A1 |
P APPROVED |
03/30/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 03/24/2011 |
120092684 |
06 |
A1 |
P APPROVED |
03/28/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL 001 thru 005
|
| 02/02/2011 |
120092684 |
05 |
A1 |
P APPROVED |
02/09/2011 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL 001 thru 005
|
| 01/19/2011 |
120580567 |
01 |
A2 |
X SIGNED OFF |
10/28/2011 |
0062815 PE |
PATEL |
|
NOT APPLICABLE
|
|
FILING HEREWITH FOR INSTALLATION OF SMOKE /HEAT DETECTION & SPRINKLER FAS
|
|
Work on Floor(s): CEL,ROO 001 thru 005
|
| 01/19/2011 |
120577072 |
01 |
A2 |
X SIGNED OFF |
09/14/2011 |
0062815 PE |
PATEL |
|
NOT APPLICABLE
|
|
FILING HEREWITH FOR MECHANICAL MODIFICATIONS AS PER PLANS. NO CHANGE TO US
|
|
Work on Floor(s): CEL,ROO 001 thru 005
|
| 08/30/2010 |
120454855 |
01 |
A3 |
X SIGNED OFF |
03/20/2012 |
0080123 PE |
SYED-NAQ |
|
NOT APPLICABLE
|
|
INSTALLATION OF 30 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED FOR BUILDING
|
|
Work on Floor(s): OSP
|
| 08/25/2010 |
120451260 |
01 |
A3 |
X SIGNED OFF |
06/30/2011 |
0077059 PE |
LUCCHETT |
|
NOT APPLICABLE
|
|
PROVIDE CANTILEVER PLATFORM, PIPE SCAFFOLD, AND SAFETY NETTING AS PER PLAN
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 06/02/2010 |
120368583 |
01 |
A3 |
X SIGNED OFF |
08/19/2011 |
0064004 PE |
WALSH |
|
NOT APPLICABLE
|
|
ERECT A TOTAL OF 83 LINEAR FEET BY 42 FEET APPROXIMATE HEIGHT OF TUBULAR S
|
|
Work on Floor(s): OSP
|
| 05/26/2010 |
120364033 |
01 |
A3 |
X SIGNED OFF |
08/17/2011 |
0064004 PE |
WALSH |
|
NOT APPLICABLE
|
|
ERECT A TOTAL OF 88 LINEAR FEET BY 10 FEET APPROXIMATE HIGH HEAVY DUTY SID
|
|
Work on Floor(s): OSP
|
| 02/10/2010 |
120092693 |
02 |
A2 |
P APPROVED |
04/14/2010 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 02/05/2010 |
120092684 |
04 |
A1 |
P APPROVED |
07/12/2010 |
|
HELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 12/21/2009 |
120092684 |
03 |
A1 |
X SIGNED OFF |
03/28/2013 |
0022194 RA |
HELD |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL 001 thru 005
|
| 11/17/2009 |
120092684 |
02 |
A1 |
X SIGNED OFF |
03/28/2013 |
0022194 RA |
HELD |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 08/20/2009 |
120136058 |
01 |
A3 |
X SIGNED OFF |
09/03/2010 |
0080123 PE |
SYED-NAQ |
|
NOT APPLICABLE
|
|
INSTALLATION OF 30 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED FOR BUILDING
|
|
Work on Floor(s): OSP
|
| 06/29/2009 |
120092693 |
01 |
A2 |
X SIGNED OFF |
03/17/2011 |
0022194 RA |
HELD |
|
NOT APPLICABLE
|
|
FILING HEREWITH FOR INTERIOR DEMOLITION AND EXCAVATION AS PER PLANS.
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 06/29/2009 |
120092684 |
01 |
A1 |
X SIGNED OFF |
03/28/2013 |
0022194 RA |
HELD |
|
NOT APPLICABLE
|
|
FILING HEREWITH FOR ALTERATION TYPE 1 TO CHANGE 4 STORY RESIDENTIAL/COMMER
|
|
Work on Floor(s): CEL 001 thru 005
|
| 03/31/1992 |
100385236 |
01 |
A3 |
X SIGNED OFF |
04/18/2012 |
0025706 PE |
KAMHOLTZ |
|
NOT APPLICABLE
|
|
ERECT A SIDEWALK SHED 20 S.F. NO CHANGE IN USE/EGRESS/OCCUPANCY.
|
|
Work on Floor(s): GRD
|