Premises: 1 TUDOR CITY PLACE MANHATTAN BIN: 1038647    Block: 1333    Lot: 23

To start overview at new date, select Month:   Day:   Year:  

         

FILE DATE JOB # DOC # JOB TYPE JOB STATUS STATUS DATE LIC # APPLICANT IN AUDIT ZONING APPROVAL
01/03/2025 123184794 03 A2 P APPROVED 03/11/2025 0017736 RA SAGE NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 022,023

09/26/2024 123108216 04 A2 P APPROVED 04/07/2025 BERTOLIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 001 thru 026

06/06/2024 102779389 02 A1 P APPROVED 07/18/2024 Moralish NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01 The renovation and extension of an existing
 Work on Floor(s): 022 thru 025

05/23/2024 122802413 03 A2 P APPROVED 06/12/2024 GUO NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 018

03/10/2023 103508848 02 A2 P APPROVED 02/05/2024 0021393 RA BERTOLIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 3, 4

10/07/2022 104076740 06 A1 P APPROVED 10/25/2022 BERTOLIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC3,SC2,001

10/29/2021 140703013 04 A3 P APPROVED 11/04/2021 BAKHTARW NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

06/02/2021 140703013 03 A3 P APPROVED 07/09/2021 0101129 PE BAKHTARW NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

05/04/2021 123108216 03 A2 P APPROVED 06/21/2021 BERTOLIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01 EXTERIOR RESTORATION AS PER PLANS. COMBININ
 Work on Floor(s): 001 thru 026

04/06/2021 140703175 04 A3 P APPROVED 04/27/2021 0086757 PE PERDEK NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

01/15/2021 104076768 02 A2 P APPROVED 11/15/2021 BERTOLIN NOT APPLICABLE
 DOC WITHDRAWN 10/06/2025
 Work on Floor(s): SC3

12/02/2020 104076740 05 A1 P APPROVED 01/11/2021 0021393 RA BERTOLIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC3,SC2,001

08/10/2020 104322760 02 A2 P APPROVED 01/22/2021 BERTOLIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SUB,002

07/17/2020 123857656 02 A2 P APPROVED 07/20/2020 0033384 RA COLBERG NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01 APPLICATION FILED FOR APARTMENT COMBINATION
 Work on Floor(s): 004

07/13/2020 104076740 04 A1 P APPROVED 07/27/2020 BERTOLIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC3,SC2,001

02/13/2020 123857656 01 A2 X SIGNED OFF 07/27/2020 0033384 RA COLBERG NOT APPLICABLE
 APPLICATION FILED FOR APARTMENT COMBINATION OF UNITS 405 AND 406 PER TPPN
 Work on Floor(s): 004

12/30/2019 140703175 03 A3 P APPROVED 01/02/2020 DOOLING NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

12/19/2019 140703013 02 A3 P APPROVED 12/26/2019 0019131 RA DOOLING NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

10/07/2019 140703175 02 A3 P APPROVED 10/09/2019 BAILEY NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

08/14/2019 123852054 01 A2 X SIGNED OFF 01/22/2020 0022383 RA TAYLOR NOT APPLICABLE
 APPLICATION FILED FOR THE INSTALLATION OF NEW THRU WALL A/C UNITS AND OPEN
 Work on Floor(s): 011

04/25/2019 123519371 03 A2 P APPROVED 04/29/2019 TAYLOR NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 003,010,016,017,021 005 thru 008 012 thru 014

04/12/2019 123519371 02 A2 P APPROVED 04/12/2019 TAYLOR NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01 APPLICATION FILED FOR 25 EXTERIO WALL OPENI
 Work on Floor(s): 003,010,016,017,021 005 thru 008 012 thru 014

04/09/2019 123591782 02 A3 D A/P ENTIRE 05/14/2019 TAYLOR NOT APPLICABLE
 DOC WITHDRAWN 02/13/2022 PROFESSIONALLY CERTIFIED FACADE REPAIR SITE SAFET
 Work on Floor(s): 003,010,016,017,021 005 thru 008 012 thru 014

04/03/2019 123591782 01 A3 P APPROVED 04/04/2019 0022383 RA TAYLOR NOT APPLICABLE
 JOB WITHDRAWN 02/13/2022 PROFESSIONALLY CERTIFIED FACADE REPAIR SITE SAFET
 Work on Floor(s): 003,010,016,017,021 005 thru 008 012 thru 014

03/29/2019 123861375 01 A2 P APPROVED 05/03/2019 0021393 RA BERTOLIN NOT APPLICABLE
 JOB WITHDRAWN 10/17/2024 RAILING INSTALLATION, CAST STONE REPLACEMENT AND
 Work on Floor(s): FAC

03/13/2019 123519371 01 A2 X SIGNED OFF 10/28/2019 0022383 RA TAYLOR NOT APPLICABLE
 APPLICATION FILED FOR 25 EXTERIO WALL OPENING/SLEEVES & INSTALLATION OF 25
 Work on Floor(s): 003,010,016,017,021 005 thru 008 012 thru 014

02/13/2019 123108216 02 A2 P APPROVED 03/08/2019 BERTOLIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 001 thru 026

01/18/2018 122948775 02 A2 P APPROVED 04/03/2018 TAYLOR NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 001 thru 005 007 thru 023

11/02/2017 140713048 01 A2 D A/P ENTIRE 11/02/2017 0022383 RA TAYLOR NOT APPLICABLE
 ADMIN CLOSED 01/01/2018 APPLICATION FILED FOR THE INSTALLATION OF FIFTEEN
 Work on Floor(s): 001 thru 015

10/27/2017 123184794 02 A2 P APPROVED 10/30/2017 SAGE NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 022,023

10/19/2017 123291302 01 A2 X SIGNED OFF 06/25/2018 0022383 RA TAYLOR NOT APPLICABLE
 COMBINE APARTMENTS 1819 AND 1820 ON THE 18TH FLOOR. CAP/REMOVE EXISTING
 Work on Floor(s): 018

10/04/2017 140703175 01 A3 X SIGNED OFF 07/11/2024 0086757 PE PERDEK NOT APPLICABLE
 PROPOSED INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGR
 Work on Floor(s): OSP

10/04/2017 140703013 01 A3 P APPROVED 10/04/2017 0101129 PE BAKHTARW NOT APPLICABLE
 FACADE SSP FILED IN CONJUNCTION WITH APPLICATION #123108216 AS PER PLANS.
 Work on Floor(s): OSP

09/28/2017 123184785 01 A3 X SIGNED OFF 06/19/2018 0017736 RA SAGE NOT APPLICABLE
 RESPECTFULLY SUBMIT PROFESSIONALLY CERTIFIED FACADE SITE SAFETY PLAN FOR
 Work on Floor(s): 022,023

09/28/2017 123184794 01 A2 R PERMIT-ENTIRE 03/13/2025 0017736 RA SAGE NOT APPLICABLE
 EXTERIOR FACADE WORK AND MISCELLANEOUS INTERIOR STRUCTURAL WORK. ENERGY EX
 Work on Floor(s): 022,023

09/19/2017 122676194 01 A2 H P/E IN PROCESS 09/20/2017 0026548 RA TORRES NOT APPLICABLE
 JOB WITHDRAWN 11/22/2021 HEREWITH FILING TO CONSTRUCT A CONSERVATORY ON OU
 Work on Floor(s): 005

08/28/2017 123135160 02 A2 R PERMIT-ENTIRE 01/16/2018 0032276 RA TANKERSL NOT APPLICABLE
 PH1 AND PH2 APARTMENT COMBINATION AS PER PLANS FIELD HEREWITH. NO CHANGE I
 Work on Floor(s): 022,023,ROF

08/28/2017 123135160 01 A2 R PERMIT-ENTIRE 05/17/2022 0036757 PE BOGART NOT APPLICABLE
 NEW MECHANICAL SYSTEM IN DUPLEX PH-1 APARTMENT. AC UNITS ON EXISTING DUNNA
 Work on Floor(s): 022,023,ROF

08/16/2017 123116859 01 A2 X SIGNED OFF 11/21/2017 0015714 RA MAYERFEL NOT APPLICABLE
 COMBINATION OF APARTMENTS 1803 AND 1804 ON THE 18TH FLOOR. MINOR PARTITION
 Work on Floor(s): 018

08/10/2017 123108216 01 A2 X SIGNED OFF 03/05/2026 0021393 RA BERTOLIN NOT APPLICABLE
 EXTERIOR RESTORATION AS PER PLANS. COMBINING RAILING INSTALLATION AND CAST
 Work on Floor(s): 001 thru 026