| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 11/08/2021 |
121097295 |
04 |
A1 |
P APPROVED |
12/01/2021 |
|
GOULD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001
|
| 09/21/2021 |
121097295 |
03 |
A1 |
P APPROVED |
10/06/2021 |
0023320 RA |
GOULD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001
|
| 04/01/2019 |
121097295 |
02 |
A1 |
P APPROVED |
04/16/2019 |
|
DUARTE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001
|
| 07/05/2017 |
140664038 |
01 |
A3 |
X SIGNED OFF |
09/15/2017 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGR
|
|
Work on Floor(s): OSP
|
| 07/05/2017 |
140664029 |
01 |
A3 |
X SIGNED OFF |
09/15/2017 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE
|
|
Work on Floor(s): OSP
|
| 03/29/2017 |
120911576 |
03 |
A2 |
J P/E DISAPPROVED |
04/11/2017 |
|
SIDERIS |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 08/25/2017
|
|
Work on Floor(s): CEL
|
| 03/09/2017 |
120911576 |
02 |
A2 |
P APPROVED |
03/21/2017 |
|
SIDERIS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 05/17/2016 |
122777389 |
01 |
A2 |
X SIGNED OFF |
11/01/2017 |
0038117 RA |
VURAL |
|
NOT APPLICABLE
|
|
MINOR REPAIR OF INTERIOR PARTITION, INSTALLATION OF PLUMBING FIXTURES: 2
|
|
Work on Floor(s): 001
|
| 05/01/2015 |
122364235 |
01 |
A2 |
X SIGNED OFF |
11/13/2015 |
0087678 PE |
BAZINI |
|
NOT APPLICABLE
|
|
RE-FILING OF APPLICATION OF #100244102 FOR REPLACEMENT OF GAS BOILER. NO C
|
|
Work on Floor(s): CEL
|
| 05/23/2014 |
122018798 |
01 |
A2 |
X SIGNED OFF |
09/19/2014 |
0023320 RA |
GOULD |
|
NOT APPLICABLE
|
|
APARTMENT RENOVATIONS TO APARTMENT 6 CONSISTING OF MINOR DEMOLITION, GENER
|
|
Work on Floor(s): 002
|
| 04/07/2014 |
140181639 |
01 |
A3 |
X SIGNED OFF |
02/24/2015 |
0066791 PE |
PARIHAR |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PIPE SCAFFOLD FOR REMEDIAL REPAIRS AS PER PLANS.
|
|
Work on Floor(s): OSP
|
| 04/02/2014 |
140181256 |
01 |
A3 |
X SIGNED OFF |
02/27/2015 |
0066791 PE |
PARIHAR |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED FILED FOR REMEDIAL REPAI
|
|
Work on Floor(s): OSP
|
| 03/31/2014 |
121962091 |
01 |
A3 |
X SIGNED OFF |
07/16/2015 |
0072914 PE |
AHMED |
|
NOT APPLICABLE
|
|
MISCALLANEOUS ACADE REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
|
|
Work on Floor(s): CEL,ROF 001 thru 006
|
| 01/21/2014 |
140152251 |
01 |
A2 |
J P/E DISAPPROVED |
02/03/2014 |
0089565 PE |
ZHU |
|
NOT APPLICABLE
|
|
MINOR INTERIOR RENOVATION AT EXISTING CELLAR STORE SPACE WITH PLUMBING AND
|
|
Work on Floor(s): CEL
|
| 05/28/2013 |
121629461 |
01 |
A2 |
X SIGNED OFF |
01/13/2016 |
0014938 RA |
FREDMAN |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION OF APARTMENT 16 TO INCLUDE LIMITED DEMOLITION, CARPENT
|
| 05/31/2012 |
121097295 |
01 |
A1 |
R PERMIT-ENTIRE |
03/28/2013 |
0023320 RA |
GOULD |
|
NOT APPLICABLE
|
|
TO EXTEND TERM OF VARIANCE FOR COMMERCIAL USE AT THE BOARD OF STANDARDS AN
|
|
Work on Floor(s): CEL,001
|
| 03/13/2012 |
120926800 |
02 |
A2 |
P APPROVED |
04/24/2012 |
|
GOULD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 003,006
|
| 12/16/2011 |
120926800 |
01 |
A2 |
X SIGNED OFF |
06/04/2012 |
0023320 RA |
GOULD |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION OF EXISTING APARTMENTS, WORK TO INCLUDE PARTITIONS, DO
|
|
Work on Floor(s): 003,006
|
| 11/30/2011 |
120911576 |
01 |
A2 |
X SIGNED OFF |
09/20/2017 |
0065574 PE |
SIDERIS |
|
NOT APPLICABLE
|
|
HEREWITH FILING FILING FOR VOLUNTARY SPRINKLER SYSTEM FOR COMMERCIAL SPACE
|
|
Work on Floor(s): CEL
|
| 02/24/2010 |
120275335 |
01 |
A2 |
X SIGNED OFF |
10/18/2010 |
0023320 RA |
GOULD |
|
NOT APPLICABLE
|
|
MODIFICATION OF INTERIOR PARTITIONS, FLOORS, DOORS, REFLECTED CEILINGS, PL
|
|
Work on Floor(s): 001,006
|
| 01/27/2009 |
110431220 |
01 |
A1 |
J P/E DISAPPROVED |
01/30/2009 |
0033875 PE |
DUARTE |
|
NOT APPLICABLE
|
|
TO OBTAIN EXTENSION OF TERM BSA VARIANCE GRANTED 5/17/94 FOR TERM OF TEN Y
|
|
Work on Floor(s): CEL,001
|
| 01/11/2008 |
110046762 |
01 |
A2 |
X SIGNED OFF |
04/10/2009 |
0047726 PE |
AINSO |
|
NOT APPLICABLE
|
|
REPLACE PART OF A BEAM. NO CHANGE IN USEEGRESS OR OCCUPANCY.
|
|
Work on Floor(s): 004
|
| 11/08/2006 |
104598696 |
01 |
A3 |
X SIGNED OFF |
02/10/2009 |
0020419 RA |
Hulme |
|
NOT APPLICABLE
|
|
INSTALL HEAVY DUTY SIDEWALK SHED A TOTAL OF 40 FT LONG AT 238 EAST 58 STRE
|
|
Work on Floor(s): 001
|
| 03/25/1998 |
101769178 |
01 |
A3 |
R PERMIT-ENTIRE |
03/26/1998 |
0599271 PE |
MELAMUD |
|
NOT APPLICABLE
|
|
INSTALLATION OF SIDEWALK SHED 36' ON EXT ERIOR OF BLDG. NO CHANGE IN USE
|
|
Work on Floor(s): GRD
|
| 09/20/1993 |
100688212 |
01 |
SG |
X SIGNED OFF |
11/16/1993 |
0006733 RA |
DAUB |
|
NOT APPLICABLE
|
|
TO ERECT NON-ILLUMINATED SIGN STATING BOUTIQUE IN ACCODANCE W/BSA CAL
|
|
Work on Floor(s): BSM
|
| 09/17/1993 |
100688203 |
01 |
SG |
X SIGNED OFF |
11/16/1993 |
0006733 RA |
DAUB |
|
NOT APPLICABLE
|
|
TO ERECT NON-ILLUMINATED SIGN STATING: "DRY CLEANING - SHIRT- BULK- LAU
|
|
Work on Floor(s): BAS
|
| 09/17/1993 |
100688196 |
01 |
SG |
X SIGNED OFF |
11/16/1993 |
0006733 RA |
DAUB |
|
NOT APPLICABLE
|
|
TO ERECT NON-ILLUMINATED SIGN STATING "RYN" IN ACCORDANCE W/BSA CAL# 5
|
|
Work on Floor(s): BAS
|
| 04/22/1991 |
100244102 |
01 |
A2 |
R PERMIT-ENTIRE |
05/01/1991 |
60500-1 PE |
WITTMANN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 12/28/2015 REPLACE GAS BOILER WEIL MCLAIN LGB-10 GAS BOILER
|
|
Work on Floor(s): CEL
|