| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 02/19/2021 |
121204785 |
09 |
A2 |
P APPROVED |
03/03/2021 |
|
SCHELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 034,035,ROF,CEL,SC1,SC2 011 thru 014 051 thru 052
|
| 01/25/2021 |
121204785 |
08 |
A2 |
P APPROVED |
02/17/2021 |
|
SCHELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 034,035,ROF,CEL,SC1,SC2 011 thru 014 051 thru 052
|
| 12/23/2020 |
123894367 |
02 |
A2 |
P APPROVED |
12/31/2020 |
|
FOX |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,SC1,SC2,SC3 001 thru 052
|
| 09/14/2020 |
121204785 |
07 |
A2 |
P APPROVED |
01/21/2021 |
|
SCHELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 034,035,ROF,CEL,SC1,SC2 011 thru 014 051 thru 052
|
| 08/21/2020 |
121204785 |
06 |
A2 |
P APPROVED |
09/11/2020 |
|
SCHELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 034,035,ROF,CEL,SC1,SC2 011 thru 014 051 thru 052
|
| 06/22/2020 |
123511182 |
04 |
A2 |
P APPROVED |
06/24/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 029
|
| 06/01/2020 |
121204785 |
05 |
A2 |
P APPROVED |
07/01/2020 |
|
SCHELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 034,035,ROF,CEL,SC1,SC2 011 thru 014 051 thru 052
|
| 04/24/2020 |
123414634 |
04 |
A2 |
P APPROVED |
05/07/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 049 thru 050
|
| 04/06/2020 |
123371519 |
04 |
A2 |
P APPROVED |
04/15/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 030 thru 032
|
| 04/06/2020 |
123510904 |
04 |
A2 |
P APPROVED |
04/14/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 04/06/2020 |
123369719 |
04 |
A2 |
P APPROVED |
04/15/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 005 thru 008
|
| 04/06/2020 |
123369504 |
04 |
A2 |
P APPROVED |
04/23/2020 |
|
MULIWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 017 thru 020
|
| 04/01/2020 |
123491836 |
05 |
A2 |
P APPROVED |
05/07/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 033 thru 036
|
| 04/01/2020 |
123493282 |
04 |
A2 |
P APPROVED |
05/06/2020 |
|
FOX |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 037 thru 040
|
| 03/25/2020 |
123415946 |
04 |
A2 |
P APPROVED |
04/01/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 025 thru 028
|
| 03/25/2020 |
123414625 |
06 |
A2 |
P APPROVED |
04/01/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 009 thru 011
|
| 03/25/2020 |
123510860 |
04 |
A2 |
P APPROVED |
04/01/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002 thru 004
|
| 03/24/2020 |
123416026 |
04 |
A2 |
P APPROVED |
05/07/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 015 thru 016
|
| 03/24/2020 |
123493503 |
04 |
A2 |
P APPROVED |
04/01/2020 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 045 thru 048
|
| 03/23/2020 |
123493497 |
04 |
A2 |
P APPROVED |
05/06/2020 |
|
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 021 thru 024
|
| 02/25/2020 |
121204785 |
04 |
A2 |
P APPROVED |
03/24/2020 |
|
SCHELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 034,035,ROF,CEL,SC1,SC2 011 thru 014 051 thru 052
|
| 01/22/2020 |
140850265 |
03 |
A2 |
P APPROVED |
03/03/2020 |
|
SCHELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,ROF 001 thru 013
|
| 12/11/2019 |
123491836 |
04 |
A2 |
P APPROVED |
12/13/2019 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 033 thru 036
|
| 12/03/2019 |
123493282 |
03 |
A2 |
P APPROVED |
12/04/2019 |
|
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 037 thru 040
|
| 12/02/2019 |
123414634 |
03 |
A2 |
P APPROVED |
12/04/2019 |
|
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 049 thru 050
|
| 12/02/2019 |
123493503 |
03 |
A2 |
P APPROVED |
12/04/2019 |
|
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 045 thru 048
|
| 12/02/2019 |
123511182 |
03 |
A2 |
P APPROVED |
12/04/2019 |
|
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 029
|
| 12/02/2019 |
123510860 |
03 |
A2 |
P APPROVED |
12/04/2019 |
|
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 002 thru 004
|
| 11/13/2019 |
121994752 |
03 |
A2 |
P APPROVED |
08/17/2020 |
|
RUCCIO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC3
|
| 11/12/2019 |
123415973 |
03 |
A2 |
P APPROVED |
11/14/2019 |
|
MULIWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 042 thru 044
|
| 11/12/2019 |
123414625 |
05 |
A2 |
P APPROVED |
11/14/2019 |
|
MMULIAWA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 009 thru 011
|
| 11/12/2019 |
123415946 |
03 |
A2 |
P APPROVED |
11/13/2019 |
|
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 025 thru 028
|
| 11/12/2019 |
123493497 |
03 |
A2 |
P APPROVED |
11/13/2019 |
|
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 021 thru 024
|
| 10/01/2019 |
140850265 |
02 |
A2 |
P APPROVED |
10/02/2019 |
|
SCHELD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SC1,CEL,ROF 001 thru 013
|
| 09/11/2019 |
123153470 |
04 |
A2 |
M P/E PAA $ RESOLV |
09/19/2019 |
|
SPECTOR |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002
|
| 09/11/2019 |
123153470 |
03 |
A2 |
L P/E PAA $ PENDIN |
09/19/2019 |
|
DESIMONE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 002
|
| 08/07/2019 |
123416026 |
03 |
A2 |
P APPROVED |
11/07/2019 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 015 thru 016
|
| 08/06/2019 |
123371519 |
03 |
A2 |
P APPROVED |
11/06/2019 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 030 thru 032
|
| 08/06/2019 |
123369504 |
03 |
A2 |
P APPROVED |
11/06/2019 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 017 thru 020
|
| 08/06/2019 |
123369719 |
03 |
A2 |
P APPROVED |
11/06/2019 |
0066144 PE |
MULIAWAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 005 thru 008
|