| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 10/11/2016 |
122895858 |
01 |
A2 |
X SIGNED OFF |
02/13/2017 |
0061152 PE |
GEIGER |
|
NOT APPLICABLE
|
|
EXTERIOR FACADE REPAIR ON ALL SIDES. REPAIR DEFECTIVE MASONRY, MORTAR JOIN
|
|
Work on Floor(s): FAC
|
| 08/17/2016 |
140536481 |
01 |
A3 |
X SIGNED OFF |
10/30/2017 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE
|
|
Work on Floor(s): OSP
|
| 03/27/2013 |
103740542 |
04 |
A1 |
P APPROVED |
04/02/2013 |
|
MCKEAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL 001 thru 017
|
| 02/06/2013 |
103740542 |
03 |
A1 |
P APPROVED |
02/08/2013 |
|
McKean |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL 001 thru 017
|
| 02/06/2013 |
103960938 |
15 |
A1 |
P APPROVED |
02/07/2013 |
|
McKean |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL 001 thru 017
|
| 01/14/2013 |
104298047 |
02 |
PA |
P APPROVED |
01/14/2013 |
|
MCKEAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 1ST,2ND
|
| 01/10/2013 |
104283035 |
03 |
PA |
P APPROVED |
01/11/2013 |
|
MCKEAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 12/24/2012 |
104283035 |
02 |
PA |
P APPROVED |
01/03/2013 |
|
MCKEAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 05/17/2012 |
103740542 |
02 |
A1 |
P APPROVED |
06/11/2012 |
|
McKean |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL 001 thru 017
|
| 04/06/2012 |
103960938 |
14 |
A1 |
P APPROVED |
06/12/2012 |
|
McKean |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 CONVERSION AND RENOVATION OF A BANK TO A CO
|
|
Work on Floor(s): SUB,CEL 001 thru 017
|
| 03/13/2012 |
103960938 |
13 |
A1 |
P APPROVED |
06/12/2012 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 10/03/2011 |
120830725 |
01 |
A2 |
X SIGNED OFF |
12/05/2012 |
0076082 PE |
METZLER |
|
NOT APPLICABLE
|
|
INSTALLATION OF A NEW EMERGENCY GENERATOR SYSTEM. MECHANICAL WORK,
|
|
Work on Floor(s): PH
|
| 09/19/2011 |
120817401 |
01 |
A2 |
X SIGNED OFF |
01/17/2012 |
0061152 PE |
GEIGER |
|
NOT APPLICABLE
|
|
EXTERIOR FACADE REPAIR ON ALL SIDES. REPAIR DEFECTIVE MASONRY, MORTAR JOIN
|
|
Work on Floor(s): 1-, ROF
|
| 08/24/2011 |
120802523 |
01 |
A3 |
X SIGNED OFF |
01/23/2012 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS, OR
|
|
Work on Floor(s): 001
|
| 07/26/2011 |
120740528 |
01 |
A3 |
X SIGNED OFF |
08/24/2012 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, E
|
|
Work on Floor(s): 001
|
| 07/22/2011 |
120762763 |
01 |
A3 |
P APPROVED |
08/08/2012 |
0019559 RA |
HEYDEN |
|
NOT APPLICABLE
|
|
FILING A FIRE PROTECTION PLAN NO WORK DONE UNDER THIS APPLICATION. NO CHA
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 09/24/2010 |
103960938 |
12 |
A1 |
J P/E DISAPPROVED |
03/12/2012 |
|
McKean |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 04/05/2012 CONVERSION AND RENOVATION OF BANK COMMERCIAL GALL
|
|
Work on Floor(s): SUB,CEL 001 thru 017
|
| 04/24/2007 |
103960938 |
11 |
A1 |
P APPROVED |
05/29/2007 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 01/02/2007 |
103960938 |
10 |
A1 |
P APPROVED |
01/30/2007 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 12/07/2006 |
103960938 |
09 |
A1 |
P APPROVED |
12/20/2006 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 11/13/2006 |
103960938 |
08 |
A1 |
P APPROVED |
12/06/2006 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 11/28/2005 |
103960938 |
07 |
A1 |
P APPROVED |
03/05/2007 |
0027247 RA |
McKean |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 11/25/2005 |
104298047 |
01 |
PA |
U COMPLETED |
01/14/2013 |
0027247 RA |
MCKEAN |
|
NOT APPLICABLE
|
|
TAIPEI ECONOMIC AND CULTURAL OFFICE
|
|
Work on Floor(s): 1ST,2ND
|
| 11/10/2005 |
104283035 |
01 |
PA |
U COMPLETED |
01/09/2013 |
0027247 RA |
MCKEAN |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL
|
| 08/26/2005 |
103974950 |
03 |
A2 |
D A/P ENTIRE |
09/23/2005 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 10/19/2012
|
| 08/15/2005 |
103960938 |
06 |
A1 |
P APPROVED |
08/31/2005 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 06/24/2005 |
104144196 |
01 |
A2 |
X SIGNED OFF |
08/04/2005 |
0036497 PE |
ROSLYN |
|
NOT APPLICABLE
|
|
REPLACE EXISTING HIGH PRESSURE STEAM SYS TEM WITH NEW PIPING AND VALVES
|
|
Work on Floor(s): STR
|
| 04/12/2005 |
103960938 |
05 |
A1 |
P APPROVED |
08/04/2005 |
0027247 RA |
McKean |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 02/18/2005 |
103960938 |
04 |
A1 |
P APPROVED |
03/04/2005 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 11/19/2004 |
103974987 |
01 |
A2 |
X SIGNED OFF |
12/07/2007 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
Filed for installation of new Fire Alarm system. No change of use, occupan
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 11/19/2004 |
103974950 |
02 |
A2 |
R PERMIT-ENTIRE |
01/07/2005 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 10/19/2012 MECHANICAL WORK IN CONJUNCTION WITH INTERIOR REMO
|
| 11/19/2004 |
103974950 |
01 |
A2 |
R PERMIT-ENTIRE |
01/07/2005 |
0028561 RA |
Blumenfe |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 10/19/2012 Interior renovation of existing office space on f
|
|
Work on Floor(s): 005 thru 016
|
| 11/04/2004 |
103960938 |
03 |
A1 |
X SIGNED OFF |
04/12/2013 |
0037971 PE |
Messina |
|
NOT APPLICABLE
|
|
Structural work in conjunction with conversion and renovation of a bank sp
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 11/04/2004 |
103960938 |
02 |
A1 |
X SIGNED OFF |
04/12/2013 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
Mechanical, plumbing, sprinkler and standpipe work in conjunction with
|
|
Work on Floor(s): SUB,CEL,PEN 001 thru 017
|
| 11/04/2004 |
103960938 |
01 |
A1 |
X SIGNED OFF |
04/12/2013 |
0027247 RA |
McKean |
|
NOT APPLICABLE
|
|
CONVERSION AND RENOVATION OF A BANK TO A COMMERCIAL GALLERY. ARCHITECTURAL
|
|
Work on Floor(s): SUB,CEL 001 thru 017
|
| 05/28/2004 |
103796956 |
01 |
A3 |
X SIGNED OFF |
04/17/2008 |
|
O'FARREL |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK BRID GE 80'DURING FACADE REPAIR NO
|
|
Work on Floor(s): GRD
|
| 05/10/2004 |
103774060 |
01 |
A3 |
X SIGNED OFF |
07/05/2007 |
0654301 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF A SCAFFOLD, 40' X 185' H IGH DURING FACADE REPAIR. NO CH
|
|
Work on Floor(s): GRD
|
| 04/20/2004 |
103750914 |
03 |
A2 |
X SIGNED OFF |
07/02/2010 |
0027247 RA |
McKean |
|
NOT APPLICABLE
|
|
Structural work in conjunction with the interior renovation of existing of
|
| 04/20/2004 |
103750914 |
02 |
A2 |
R PERMIT-ENTIRE |
10/27/2004 |
0076082 PE |
Metzler |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 07/01/2010 Plumbing, mechanical work in conjunction with th
|
| 04/20/2004 |
103750914 |
01 |
A2 |
X SIGNED OFF |
07/02/2010 |
0027247 RA |
McKean |
|
NOT APPLICABLE
|
|
Interior renovation of existing office space on floors 1 thru 17 .
|
|
Work on Floor(s): CEL 001 thru 017
|