| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 08/06/2024 |
122214308 |
12 |
A1 |
P APPROVED |
08/13/2024 |
0037566 RA |
MAXWELL |
|
GRANTED 02/27/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,ROF 001 thru 004
|
| 03/11/2024 |
122214308 |
11 |
A1 |
P APPROVED |
03/25/2024 |
|
MAXWELL |
|
GRANTED 02/27/2015
|
|
POST APPROVAL AMENDMENT FOR 01 CHANGE FROM EIGHT(8)FAMILY TO SINGLE FAMILY
|
|
Work on Floor(s): CEL,BAS,ROF 001 thru 004
|
| 09/24/2020 |
122214308 |
10 |
A1 |
P APPROVED |
10/23/2020 |
0079477 PE |
MCSHANE |
|
GRANTED 02/27/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 005
|
| 06/25/2020 |
122214308 |
09 |
A1 |
P APPROVED |
07/22/2020 |
0079477 PE |
MCSHANE |
|
GRANTED 02/27/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 005
|
| 03/19/2020 |
122214308 |
08 |
A1 |
P APPROVED |
04/20/2020 |
|
MAXWELL |
|
GRANTED 02/27/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,ROF 001 thru 004
|
| 12/03/2019 |
122214308 |
07 |
A1 |
P APPROVED |
12/16/2019 |
0079477 PE |
MCSHANE |
|
GRANTED 02/27/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 005
|
| 04/18/2019 |
123708023 |
01 |
A2 |
X SIGNED OFF |
07/28/2021 |
0070045 PE |
LOTFI |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEW SPRINKLER SYSTEM AS PER PLANS. NO CHANGE TO USE EGRESS
|
|
Work on Floor(s): CEL,BAS,ROF 001 thru 004
|
| 02/04/2019 |
123671348 |
01 |
A2 |
J P/E DISAPPROVED |
02/07/2019 |
0079477 PE |
MCSHANE |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 07/29/2021 INSTALLATION OF NEW SPRINKLER SYSTEM AS PER PLANS
|
|
Work on Floor(s): CEL,BAS,ROF 001 thru 004
|
| 01/10/2019 |
122214308 |
06 |
A1 |
P APPROVED |
01/16/2019 |
0079477 PE |
MCSHANE |
|
GRANTED 02/27/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 005
|
| 08/14/2018 |
122214308 |
05 |
A1 |
P APPROVED |
08/17/2018 |
0079477 PE |
MCSHANE |
|
GRANTED 02/27/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 07/13/2018 |
122214308 |
04 |
A1 |
P APPROVED |
08/17/2018 |
|
MAXWELL |
|
GRANTED 02/27/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,ROF 001 thru 004
|
| 08/31/2016 |
140542161 |
01 |
A3 |
X SIGNED OFF |
11/04/2022 |
0035839 RA |
O'CONNOR |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PIPE SCAFFOLD FOR REMEDIAL REPAIRS AS PER PLANS.
|
|
Work on Floor(s): OSP
|
| 08/31/2016 |
140542152 |
01 |
A3 |
X SIGNED OFF |
11/07/2022 |
0035839 RA |
O'CONNOR |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS AS
|
|
Work on Floor(s): OSP
|
| 08/02/2016 |
122848320 |
01 |
A3 |
X SIGNED OFF |
11/28/2023 |
0060234 PE |
CAMBOURA |
|
NOT APPLICABLE
|
|
FENCE TO GO IN CONJUNCTION WITH ALT 1 APPLICATION #122214308.
|
|
Work on Floor(s): GRD
|
| 04/18/2016 |
140484045 |
01 |
A3 |
X SIGNED OFF |
11/04/2022 |
0085110 PE |
ODIGIE |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL
|
|
Work on Floor(s): OSP
|
| 04/18/2016 |
140484036 |
01 |
A3 |
X SIGNED OFF |
11/04/2022 |
0085110 PE |
ODIGIE |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD
|
|
Work on Floor(s): OSP
|
| 04/16/2015 |
122214308 |
03 |
A1 |
X SIGNED OFF |
09/09/2025 |
0079477 PE |
MCSHANE |
|
GRANTED 02/27/2015
|
|
FILING MECHANICAL AND PLUMBING MODIFICATIONS ASSOCIATED WITH SINGLE FAMILY
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 005
|
| 04/16/2015 |
122370941 |
01 |
A2 |
P APPROVED |
02/04/2016 |
0079477 PE |
MCSHANE |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 07/29/2021 FILING TO INSTALL SPRINKLER SYSTEM IN SINGLE FAMI
|
|
Work on Floor(s): CEL,ROF,BAS 001 thru 004
|
| 12/16/2014 |
122214308 |
02 |
A1 |
X SIGNED OFF |
09/09/2025 |
0060234 PE |
CAMBOURA |
|
GRANTED 02/27/2015
|
|
STRUCTURAL WORK IN CONJUNCTION WITH CHANGE OF USE TO 1 FAMILY HOUSE AND SM
|
|
Work on Floor(s): CEL,BAS,ROF 001 thru 004
|
| 12/16/2014 |
122214308 |
01 |
A1 |
X SIGNED OFF |
09/09/2025 |
0037566 RA |
MAXWELL |
|
GRANTED 02/27/2015
|
|
CHANGE FROM EIGHT(8)FAMILY TO SINGLE FAMILY"VERTICAL AND HORIZONTAL ENLARG
|
|
Work on Floor(s): CEL,BAS,ROF 001 thru 004
|
| 08/16/2000 |
102897714 |
01 |
A2 |
X SIGNED OFF |
11/07/2022 |
0076805 PE |
CHRYSLER |
|
NOT APPLICABLE
|
|
REPLACE BOILER & BURNER STRUCTURAL STABILITY WILL NOT BE AFFECTED
|
|
Work on Floor(s): CEL
|