| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 04/10/2024 |
102283413 |
05 |
PA |
P APPROVED |
06/05/2024 |
0031613 RA |
GENTZLER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 006
|
| 06/11/2019 |
123292515 |
02 |
PA |
P APPROVED |
07/08/2019 |
|
GENTZLER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 005
|
| 04/16/2019 |
123292506 |
11 |
A1 |
P APPROVED |
05/08/2019 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001,003,005,ROF,CEL
|
| 04/15/2019 |
123677146 |
01 |
A2 |
X SIGNED OFF |
01/21/2020 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
ADDITIONS/MODIFICATIONS TO AN EXISTING FIRE ALARM SYSTEM
|
|
Work on Floor(s): 001
|
| 03/11/2019 |
123292506 |
10 |
A1 |
P APPROVED |
03/20/2019 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001,003,005,ROF
|
| 12/06/2018 |
140821412 |
01 |
A3 |
X SIGNED OFF |
09/20/2019 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF INTERNAL WORKING PLATFORM AS PER PLANS. NO CHANGE IN USE,
|
|
Work on Floor(s): 001
|
| 12/05/2018 |
123292506 |
09 |
A1 |
P APPROVED |
01/14/2019 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001,003,005,ROF
|
| 10/26/2018 |
123292506 |
08 |
A1 |
P APPROVED |
11/28/2018 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001,003,005,ROF
|
| 10/12/2018 |
123292506 |
07 |
A1 |
P APPROVED |
11/28/2018 |
|
GENTZLER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 APPLICATION FILED FOR GENERAL CONSTRUCTION
|
|
Work on Floor(s): 001,005,ROF
|
| 08/31/2018 |
123400257 |
01 |
A3 |
P APPROVED |
09/06/2018 |
0031613 RA |
GENTZLER |
|
NOT APPLICABLE
|
|
OCCUPANT PROTECTION PLANS, FILED IN CONJUNCTION WITH ONGOING WORK WITHIN T
|
|
Work on Floor(s): CEL,MEZ 001 thru 006
|
| 08/30/2018 |
123292506 |
06 |
A1 |
P APPROVED |
11/20/2018 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001,003,005,ROF
|
| 08/07/2018 |
123292506 |
05 |
A1 |
P APPROVED |
08/31/2018 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001,003,005,ROF
|
| 07/10/2018 |
123292506 |
04 |
A1 |
P APPROVED |
08/29/2018 |
|
GENTZLER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001,005,ROF
|
| 07/06/2018 |
123376934 |
01 |
A3 |
P APPROVED |
09/17/2019 |
0031613 RA |
GENTZLER |
|
NOT APPLICABLE
|
|
FIRE PROTECTIONS PANS IN CONJUNCTION WITH ALT-I#123292506
|
|
Work on Floor(s): 001,003,005,ROF
|
| 05/21/2018 |
123565409 |
01 |
A2 |
X SIGNED OFF |
07/12/2018 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
INSTALLATION OF HVAC SYSTEM.
|
|
Work on Floor(s): ROF
|
| 05/10/2018 |
123183456 |
02 |
A2 |
P APPROVED |
07/13/2018 |
|
NEWBOLD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001,003,005
|
| 02/09/2018 |
123242302 |
03 |
A2 |
P APPROVED |
02/12/2018 |
|
GENTZLER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 003,005,ROF
|
| 11/16/2017 |
123242302 |
02 |
A2 |
X SIGNED OFF |
09/11/2019 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
MECHANICAL & PLUMBING WORK AS SHOWN ON PLANS.
|
|
Work on Floor(s): 003,002
|
| 11/16/2017 |
123242302 |
01 |
A2 |
X SIGNED OFF |
09/11/2019 |
0031613 RA |
GENTZLER |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION TO INCLUDE DEMO OF EXISTING AND CONSTRUCTION OF NEW
|
|
Work on Floor(s): 003,005,ROF
|
| 09/28/2017 |
123183456 |
01 |
A2 |
X SIGNED OFF |
09/11/2019 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
REPLACEMENT OF FIRE ALARM CONTROL PANEL WITH ADDITIONS/MODIFICATION TO AN
|
|
Work on Floor(s): 001,003,005
|
| 09/28/2017 |
123292515 |
01 |
PA |
U COMPLETED |
05/28/2019 |
0031613 RA |
GENTZLER |
|
NOT APPLICABLE
|
|
Work on Floor(s): 005
|
| 09/27/2017 |
123292506 |
03 |
A1 |
X SIGNED OFF |
12/02/2020 |
0081677 PE |
ELLIOTT |
|
NOT APPLICABLE
|
|
STRUCTURAL ALTERATIONS IN CONJUNCTION WITH INITIAL APPLICATION
|
|
Work on Floor(s): 005,006
|
| 09/27/2017 |
123292506 |
02 |
A1 |
X SIGNED OFF |
12/02/2020 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
MODIFY / INSTALL NEW PLUMBING AND HVAC AS SHOWN
|
|
Work on Floor(s): 001,003,005,ROF,CEL
|
| 09/27/2017 |
123292506 |
01 |
A1 |
X SIGNED OFF |
12/02/2020 |
0031613 RA |
GENTZLER |
|
NOT APPLICABLE
|
|
APPLICATION FILED FOR GENERAL CONSTRUCTION ON FLOORS 1ST,3RD, 5TH, ROOF PL
|
|
Work on Floor(s): 001,005,ROF
|
| 11/30/2016 |
122940050 |
01 |
A2 |
X SIGNED OFF |
08/15/2017 |
0042991 PE |
BUTLER |
|
NOT APPLICABLE
|
|
REPAIRS TO FACADE, REPAIR VARIOUS BRICK MASONRY CRACK CONDITIONS AS PER PL
|
|
Work on Floor(s): 001 thru 006
|
| 09/29/2016 |
140556592 |
01 |
A3 |
X SIGNED OFF |
04/24/2017 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGR
|
|
Work on Floor(s): OSP
|
| 09/29/2016 |
140556574 |
01 |
A3 |
X SIGNED OFF |
04/24/2017 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE
|
|
Work on Floor(s): OSP
|
| 11/19/2015 |
122474483 |
03 |
A2 |
P APPROVED |
11/23/2015 |
|
NEWBOLD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,ROF 001 thru 006
|
| 08/24/2015 |
122474483 |
02 |
A2 |
P APPROVED |
08/25/2015 |
|
NEWBOLD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAL,ROF 001 thru 006
|
| 07/23/2015 |
122474483 |
01 |
A2 |
X SIGNED OFF |
04/04/2016 |
0089878 PE |
NEWBOLD |
|
NOT APPLICABLE
|
|
REPLACEMENT OF GAS PIPING AND RELATED PLUMBING WORK AS SHOWN ON PLANS.
|
|
Work on Floor(s): CEL,BAS,ROF 001 thru 006
|
| 06/15/2015 |
102283413 |
04 |
PA |
P APPROVED |
06/24/2015 |
0024659 RA |
WITZIG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 006
|
| 09/16/2013 |
121679184 |
01 |
A2 |
X SIGNED OFF |
05/21/2018 |
0047135 PE |
GERMAIN |
|
NOT APPLICABLE
|
|
REPLACE NEW LP GAS SERVICE, GAS METER, GAS BOOSTER, GAS TRAINS, & ASSOC PI
|
|
Work on Floor(s): CEL
|
| 05/07/2012 |
120316372 |
02 |
A2 |
P APPROVED |
06/06/2012 |
|
CONRAD |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 004
|
| 05/11/2011 |
120690289 |
01 |
A2 |
X SIGNED OFF |
08/29/2012 |
0042991 PE |
BUTLER |
|
NOT APPLICABLE
|
|
HEREWITH FILING FOR REPAIRS OF DETERIORATED BRICK MASONRY CONDITIONS AND S
|
|
Work on Floor(s): FAC
|
| 04/20/2011 |
120668642 |
01 |
A3 |
X SIGNED OFF |
11/05/2011 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
INSTALLATION OF 170 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED FOR BUILDING
|
|
Work on Floor(s): OSP
|
| 06/21/2010 |
120388874 |
01 |
A2 |
X SIGNED OFF |
12/30/2010 |
0042991 PE |
BUTLER |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEW STEEL DUNNAGE FOR EXISTING CHILLER UNITS IN THE EXISTI
|
|
Work on Floor(s): 004
|
| 04/13/2010 |
120316372 |
01 |
A2 |
X SIGNED OFF |
08/09/2012 |
0059371 PE |
CONRAD |
|
NOT APPLICABLE
|
|
REMOVAL OF OLD COMPRESSORS AND INSTALLATION OF A NEW MODULAR CHILLER IN TH
|
|
Work on Floor(s): 004
|
| 04/01/2010 |
120310038 |
01 |
A3 |
X SIGNED OFF |
06/01/2010 |
0080123 PE |
SYED-NAQ |
|
NOT APPLICABLE
|
|
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPT
|
|
Work on Floor(s): OSP
|
| 11/23/2009 |
120207695 |
01 |
A2 |
X SIGNED OFF |
07/08/2010 |
0042991 PE |
BUTLER |
|
NOT APPLICABLE
|
|
HEREWITH FILING FOR LL 11/98 CYCLE 6 REPAIRS. REBUILD BRICK MASONARY AT NW
|
|
Work on Floor(s): 001
|
| 05/02/2007 |
104748711 |
01 |
A2 |
X SIGNED OFF |
05/25/2011 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
REPLACE TWO (2) BOILERS AND TWO (2) OIL BURNERS (NYC BOILER # 80500-01,02)
|
|
Work on Floor(s): CEL
|