FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
12/29/2022 |
123037276 |
09 |
A2 |
P APPROVED |
02/07/2023 |
|
TOSCANO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 013
|
06/28/2022 |
101170466 |
17 |
A1 |
P APPROVED |
12/22/2022 |
|
TOSCANO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,002,003,004,PEN
|
06/15/2022 |
101170466 |
16 |
A1 |
D A/P ENTIRE |
06/22/2022 |
|
TOSCANO |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 06/28/2022
|
|
Work on Floor(s): CEL,PEN 002 thru 006
|
03/19/2022 |
140707322 |
02 |
A3 |
P APPROVED |
11/30/2022 |
0090955 PE |
RAZZAK |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SH.
|
11/03/2021 |
123037276 |
08 |
A2 |
P APPROVED |
12/13/2021 |
0020848 RA |
TOSCANO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 013
|
08/11/2021 |
122388479 |
07 |
A1 |
J P/E DISAPPROVED |
02/27/2024 |
|
TOSCANO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 014
|
12/22/2020 |
123037276 |
07 |
A2 |
P APPROVED |
12/24/2020 |
|
TOSCANO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 013
|
08/25/2020 |
122388479 |
06 |
A1 |
P APPROVED |
09/15/2020 |
0020848 RA |
TOSCANO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 014
|
08/19/2020 |
123037276 |
06 |
A2 |
P APPROVED |
10/27/2020 |
0020848 RA |
TOSCANO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 CONVERT EXISTING STORAGE ROOM TO NEW LAUNDR
|
|
Work on Floor(s): 013
|
05/01/2020 |
123688508 |
02 |
A2 |
P APPROVED |
09/22/2020 |
|
TOSCANO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
06/14/2019 |
122388479 |
05 |
A1 |
P APPROVED |
02/28/2020 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 014
|
06/03/2019 |
123688508 |
01 |
A2 |
R PERMIT-ENTIRE |
09/23/2024 |
0020848 RA |
TOSCANO |
|
NOT APPLICABLE
|
|
PROPOSED ACCESSORY TENNANT LAUNDRY AT CELLAR FLOOR. SCOPE TO INCLUDE MINOR
|
|
Work on Floor(s): CEL
|
|
123783520 |
01 |
A2 |
A PRE-FILED |
05/30/2019 |
0020848 RA |
TOSCANO |
|
NOT APPLICABLE
|
|
PROPOSED ACCESSORY TENNANT LAUNDRY AT CELLAR FLOOR. SCOPE TO INCLUDE MINOR
|
|
Work on Floor(s): CEL
|
04/24/2019 |
140690438 |
02 |
A2 |
P APPROVED |
05/17/2019 |
|
FENNELL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 012
|
04/04/2019 |
123837018 |
01 |
A2 |
X SIGNED OFF |
09/08/2020 |
0067415 PE |
KOENIGSB |
|
NOT APPLICABLE
|
|
EXTERIOR RESTORATION AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS
|
|
Work on Floor(s): ROF 002 thru 012
|
11/29/2018 |
123037276 |
05 |
A2 |
P APPROVED |
02/15/2019 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 013
|
11/15/2018 |
123370020 |
01 |
A2 |
R PERMIT-ENTIRE |
08/28/2019 |
0010059 RA |
GOLDBERG |
|
NOT APPLICABLE
|
|
FILING TO ADDRESS VIOLATIONS 35306724P AND 35306809Y. HALLWAYS CONSTRUCTI
|
|
Work on Floor(s): 002 thru 012
|
08/01/2018 |
123037276 |
04 |
A2 |
P APPROVED |
09/12/2018 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 013
|
05/18/2018 |
123037276 |
03 |
A2 |
P APPROVED |
06/29/2018 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 013
|
05/18/2018 |
122388460 |
07 |
A2 |
P APPROVED |
06/29/2018 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002 thru 005 007 thru 012
|
02/08/2018 |
140738423 |
01 |
A3 |
X SIGNED OFF |
01/12/2021 |
0093179 PE |
AHMED |
|
NOT APPLICABLE
|
|
INSTALLATION OF STORAGE OF MATERIAL ON SIDEWALK SHED AS PER PLANS. WORK SH
|
|
Work on Floor(s): OSP
|
11/27/2017 |
123037276 |
02 |
A2 |
P APPROVED |
12/12/2017 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 RELOCATE THE EXISTING LAUNDRY ROOM ON THE 1
|
|
Work on Floor(s): 013
|
10/29/2017 |
140707322 |
01 |
A3 |
R PERMIT-ENTIRE |
11/08/2017 |
0090955 PE |
RAZZAK |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY SUPPORTED PIPE SCAFFOLD AS SHOWN ON PLANS. WORK
|
|
Work on Floor(s): SH.
|
10/20/2017 |
140709008 |
01 |
A2 |
R PERMIT-ENTIRE |
10/26/2017 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
ACTIVATE GAS PORTION OF EXISTING GAS/OIL BURNER ON NYC BOILER NO. MD13177-
|
|
Work on Floor(s): CEL,OSP
|
09/07/2017 |
140690438 |
01 |
A2 |
X SIGNED OFF |
05/28/2019 |
0090544 PE |
FENNELL |
|
NOT APPLICABLE
|
|
BRICK REPLACEMENT, MASONRY REPOINTING, STONE REPAIR, CORNER REPLACEMENT, S
|
|
Work on Floor(s): 001 thru 012
|
08/22/2017 |
140685042 |
01 |
A2 |
H P/E IN PROCESS |
08/22/2017 |
0090544 PE |
FENNELL |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 09/05/2017 1. BRICK REPLACEMENT 2. MASONRY REPOINTING 3. S
|
|
Work on Floor(s): 001 thru 012
|
08/04/2017 |
140678103 |
01 |
A3 |
R PERMIT-ENTIRE |
08/09/2017 |
0093179 PE |
AHMED |
|
NOT APPLICABLE
|
|
INSTALLATION OF SIDEWALK SHED AS PER PLANS. WORK SHALL COMPLY WITH 2014 BU
|
|
Work on Floor(s): OSP
|
03/17/2017 |
123037276 |
01 |
A2 |
R PERMIT-ENTIRE |
09/23/2024 |
0020848 RA |
TOSCANO |
|
NOT APPLICABLE
|
|
CONVERT EXISTING STORAGE ROOM TO NEW LAUNDRY ROOM ON THE 13TH (PENTHOUSE)
|
|
Work on Floor(s): 013
|
05/28/2016 |
122388460 |
06 |
A2 |
P APPROVED |
07/11/2016 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 11 002 thru 006
|
04/20/2016 |
122388460 |
05 |
A2 |
P APPROVED |
05/23/2016 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002 thru 005 007 thru 012
|
04/20/2016 |
122388479 |
04 |
A1 |
P APPROVED |
10/20/2016 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 014
|
03/11/2016 |
122388460 |
04 |
A2 |
P APPROVED |
03/22/2016 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002 thru 005 007 thru 012
|
02/16/2016 |
122388479 |
03 |
A1 |
P APPROVED |
03/22/2016 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 014
|
12/02/2015 |
122388460 |
03 |
A2 |
P APPROVED |
01/20/2016 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 002 thru 005 007 thru 012
|
11/19/2015 |
122388460 |
02 |
A2 |
R PERMIT-ENTIRE |
09/20/2016 |
0010059 RA |
GOLDBERG |
|
NOT APPLICABLE
|
|
FILING FOR MINOR PARTITION CHNAGES IN APARTMENTS. REPLACING FIXTURES ON EX
|
|
Work on Floor(s): 11 002 thru 006
|
10/28/2015 |
122388479 |
02 |
A1 |
P APPROVED |
01/14/2016 |
|
GOLDBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 014
|
07/28/2015 |
122400945 |
01 |
A2 |
X SIGNED OFF |
11/30/2018 |
0019548 RA |
HAMMOND |
|
NOT APPLICABLE
|
|
REPLACE 2 EXISTING HVAC UNITS AT 1ST FLOOR COURTYARD ON EXISTING STEEL DUN
|
|
Work on Floor(s): OSP,001
|
06/10/2015 |
122388479 |
01 |
A1 |
R PERMIT-ENTIRE |
11/12/2015 |
0020848 RA |
TOSCANO |
|
NOT APPLICABLE
|
|
FILING ALT1 COFO APP TO BE APPROVED AND SIGNED OFF IN CONJUNCTION WITH
|
|
Work on Floor(s): CEL 001 thru 014
|
06/04/2015 |
122388460 |
01 |
A2 |
R PERMIT-ENTIRE |
09/20/2016 |
0010059 RA |
GOLDBERG |
|
NOT APPLICABLE
|
|
FILING FOR MINOR PARTITION CHANGES IN APARTMENTS. REPLACING FIXTURES ON EX
|
|
Work on Floor(s): 002 thru 005 007 thru 012
|
10/09/2014 |
140265898 |
01 |
A2 |
R PERMIT-ENTIRE |
10/21/2014 |
0087678 PE |
BAZINI |
|
NOT APPLICABLE
|
|
ACTIVATE GAS PORTION ON EXISTING GAS/OIL BURNER. NO CHANGE IN USE, OCCUPAN
|
|
Work on Floor(s): CEL
|