| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 12/23/2016 |
122977261 |
01 |
A3 |
R PERMIT-ENTIRE |
12/23/2016 |
0032813 PE |
PARMET |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS SHOWN ON DRAWING. THERE WIL
|
|
Work on Floor(s): OSP
|
| 12/23/2016 |
122977252 |
01 |
A3 |
R PERMIT-ENTIRE |
12/23/2016 |
0032813 PE |
PARMET |
|
NOT APPLICABLE
|
|
INSTALLATION OF A SCAFFOLD STAIR TOWER AS SHOWN ON DRAWING. THERE WILL BE
|
|
Work on Floor(s): OSP
|
| 10/21/2015 |
122561334 |
01 |
A3 |
X SIGNED OFF |
11/20/2015 |
0017578 RA |
FORMICHE |
|
NOT APPLICABLE
|
|
INSTALL INTERIOR THEATRICAL STAGING, LIGHTING, AUDIO, EXTERIOR TENTING FOR
|
|
Work on Floor(s): 001
|
| 02/19/2014 |
121924597 |
01 |
A3 |
X SIGNED OFF |
03/17/2014 |
0071719 PE |
UDDIN |
|
NOT APPLICABLE
|
|
INSTALLATION OF 106 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED FOR BUILDING
|
|
Work on Floor(s): OSP
|
| 02/13/2014 |
140162990 |
01 |
A3 |
H P/E IN PROCESS |
02/13/2014 |
0071719 PE |
UDDIN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 02/13/2014 INSTALLATION OF 106 LINEAR FEET OF HEAVY DUTY SID
|
|
Work on Floor(s): OSP
|
| 02/11/2014 |
121919255 |
01 |
A3 |
X SIGNED OFF |
03/04/2014 |
0017578 RA |
FORMICHE |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY INTERIOR TENTS, FOR PRODUCTION PURPOSES, FOR THE
|
|
Work on Floor(s): 001
|
| 10/25/2013 |
121822885 |
01 |
A2 |
X SIGNED OFF |
11/21/2013 |
0017578 RA |
FORMICHE |
|
NOT APPLICABLE
|
|
INSTALLATION ON TEMPORARY SEATING RISERS, PLATFORMS AND LOADING DOCK FOR T
|
|
Work on Floor(s): 001
|
| 09/10/2013 |
121775454 |
01 |
A2 |
X SIGNED OFF |
09/23/2013 |
0017578 RA |
FORMICHE |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY SEATING PLATFORMS FOR THE MARC JACOBS FASHION SH
|
|
Work on Floor(s): 001
|
| 05/08/2013 |
121612228 |
01 |
A2 |
X SIGNED OFF |
05/29/2013 |
0017578 RA |
FOMICHEL |
|
NOT APPLICABLE
|
|
INSTALLATION OF A TEMPORAY PLATFORM SYSTEM FOR THE EVENT KNOWN AS VERSACE
|
|
Work on Floor(s): 001
|
| 11/05/2012 |
121425662 |
01 |
A3 |
R PERMIT-ENTIRE |
11/07/2012 |
0033652 RA |
STILES |
Y |
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED OF 528 LF AS PER PLANS. SHED IS
|
|
Work on Floor(s): OSP
|
| 10/18/2012 |
121412051 |
01 |
A2 |
X SIGNED OFF |
12/03/2012 |
0017578 RA |
FORMICHE |
|
NOT APPLICABLE
|
|
INSTALLATION OF INTERIOR TEMPORARY SEATING BLEACHERS AND OTHER PRODUCTION
|
|
Work on Floor(s): 001
|
| 01/09/2012 |
120902309 |
01 |
A3 |
R PERMIT-ENTIRE |
01/24/2012 |
OT |
PAPADAKI |
|
NOT APPLICABLE
|
|
INSTALLATION OF A FENCE.NO CHANGE TO USE EGRESS OR OCCUPANCY.
|
|
Work on Floor(s): 001
|
| 08/25/2011 |
120806146 |
01 |
A3 |
R PERMIT-ENTIRE |
10/30/2014 |
0032813 PE |
PARMET |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED. THERE WILL BE NO CHANGE IN USE E
|
|
Work on Floor(s): OSP
|
| 07/19/2011 |
120763600 |
01 |
A2 |
X SIGNED OFF |
08/09/2011 |
0017578 RA |
FORMICHE |
|
NOT APPLICABLE
|
|
INSTALLATION OF A TEMPORARY DECK AND TRUSSING FOR THE M&M?S PRETZEL FIRST
|
|
Work on Floor(s): 001
|
| 02/11/2011 |
120611007 |
01 |
A3 |
R PERMIT-ENTIRE |
02/11/2011 |
0033652 RA |
STILES |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVYDUTY SIDEWALK SHED FILED FOR REMEDIAL REPAIR
|
|
Work on Floor(s): OSP
|
| 10/28/2009 |
120185977 |
01 |
A2 |
X SIGNED OFF |
12/22/2010 |
0017578 RA |
FORMICHE |
|
NOT APPLICABLE
|
|
TEMPORARY INTERIOR BLEACHER SEATING WITH TEMPORARY EXTERIOR ENTRY TENTS AN
|
|
Work on Floor(s): 001
|
| 11/16/2007 |
110025712 |
01 |
A2 |
X SIGNED OFF |
12/22/2010 |
0175781 RA |
Formiche |
|
NOT APPLICABLE
|
|
Erect temporary tents. LPC approval notrequired. No change to egress, u
|
|
Work on Floor(s): 001
|
| 05/04/2006 |
104423385 |
01 |
A3 |
R PERMIT-ENTIRE |
11/07/2007 |
0078402 PE |
Blinn |
|
NOT APPLICABLE
|
|
Erect Temporary Scaffold 202' in length & 68' tall on E. 25th St. side of
|
|
Work on Floor(s): 001
|
| 02/01/2006 |
104343667 |
01 |
A3 |
R PERMIT-ENTIRE |
02/08/2006 |
|
PILKU |
|
NOT APPLICABLE
|
|
INSTALLATION OF 670' SIDEWALK SHED FORTHE PURPOSE OF FACADE INSPECTION
|
|
Work on Floor(s): GRD
|
| 10/27/2005 |
104272840 |
01 |
A3 |
R PERMIT-ENTIRE |
10/31/2005 |
OT |
ZAHARIA |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF 55 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED FOR
|
|
Work on Floor(s): OSP
|
| 10/27/2005 |
104264966 |
01 |
A3 |
R PERMIT-ENTIRE |
10/31/2005 |
OT |
ZAHARIA |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF 16 LINEAR FEET X 50 FEET HIGH HEAVY DUTY PIPE SCA
|
|
Work on Floor(s): OSP
|
| 07/29/2005 |
104182475 |
01 |
A3 |
R PERMIT-ENTIRE |
03/20/2007 |
OT |
Hama |
|
NOT APPLICABLE
|
|
Erect temporary scaffold 200' long by 55' high during repairs on dome of
|
|
Work on Floor(s): 001
|
| 07/27/2005 |
104177944 |
01 |
A3 |
R PERMIT-ENTIRE |
02/07/2008 |
OT |
Hama |
|
NOT APPLICABLE
|
|
Erect 35' ofTemporary Heavy Duty Sidewalk Shed 300 psf at each entrance
|
|
Work on Floor(s): 001
|
| 05/29/2003 |
103468935 |
01 |
A3 |
X SIGNED OFF |
11/18/2005 |
0020419 RA |
HULME |
|
NOT APPLICABLE
|
|
Install scaffold 20ft long by134ft high with five levels of planking rea
|
|
Work on Floor(s): 001
|
| 09/07/2001 |
102998730 |
01 |
A3 |
R PERMIT-ENTIRE |
11/14/2001 |
|
HARDON |
|
NOT APPLICABLE
|
|
INSTALL HEAVY DUTY SIDE WALK SHED 34'LNG AT 68 LEXINGTON AVE DURING REME
|
|
Work on Floor(s): GRD
|
| 08/29/2000 |
102750836 |
01 |
A3 |
X SIGNED OFF |
08/26/2004 |
0020419 RA |
HULME |
|
NOT APPLICABLE
|
|
8INSTALL HEAVY DUTY SIDEWALK SHED : 80' LONG
|
| 02/11/1993 |
100590754 |
01 |
A2 |
R PERMIT-ENTIRE |
03/15/1993 |
0039622 PE |
PEROTTO |
|
NOT APPLICABLE
|
|
REPLACE TWO BOILER AND BURNERS
|
|
Work on Floor(s): CLR
|