| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 04/14/2026 |
123329521 |
16 |
NB |
P APPROVED |
04/16/2026 |
|
POON |
|
AMENDED 10/20/2021
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 035
|
| 01/24/2024 |
123007628 |
02 |
A2 |
P APPROVED |
05/26/2024 |
|
CHIU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 07/24/2023 |
123329521 |
15 |
NB |
P APPROVED |
07/25/2023 |
0075441 PE |
CHIU |
|
AMENDED 10/20/2021
|
|
POST APPROVAL AMENDMENT FOR 06
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 032
|
| 07/05/2023 |
123178989 |
04 |
A2 |
P APPROVED |
07/18/2023 |
|
CHIU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP 001 thru 035
|
| 06/29/2023 |
123178989 |
03 |
A2 |
P APPROVED |
07/03/2023 |
|
CHIU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP 001 thru 035
|
| 06/15/2023 |
123489705 |
07 |
A2 |
P APPROVED |
07/10/2023 |
|
CHIU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 06/09/2023 |
123329521 |
14 |
NB |
P APPROVED |
06/16/2023 |
0075441 PE |
CHIU |
|
AMENDED 10/20/2021
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 035
|
| 04/20/2023 |
123329521 |
13 |
NB |
P APPROVED |
05/01/2023 |
|
POON |
|
AMENDED 10/20/2021
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 035
|
| 03/30/2023 |
123489705 |
06 |
A2 |
P APPROVED |
05/25/2023 |
0075441 PE |
CHIU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 01/31/2023 |
123489705 |
05 |
A2 |
P APPROVED |
02/03/2023 |
|
CHIU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 12/23/2022 |
123178989 |
02 |
A2 |
P APPROVED |
06/01/2023 |
0075441 PE |
CHIU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP 001 thru 035
|
| 11/17/2022 |
123489705 |
04 |
A2 |
P APPROVED |
12/19/2022 |
|
CHIU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 05/17/2022 |
123489705 |
03 |
A2 |
P APPROVED |
05/19/2022 |
|
CHIU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 02/01/2022 |
123252639 |
02 |
A2 |
P APPROVED |
02/13/2023 |
0099830 PE |
TROFIMCH |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION AND SUBMISSION OF A REPEATER A
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 12/13/2021 |
123489705 |
02 |
A2 |
P APPROVED |
01/03/2022 |
|
CHIU |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 10/29/2021 |
123329521 |
12 |
NB |
P APPROVED |
02/18/2022 |
0075441 PE |
CHIU |
|
AMENDED 10/20/2021
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 035
|
| 09/20/2021 |
123329521 |
11 |
NB |
P APPROVED |
10/20/2021 |
|
POON |
|
AMENDED 10/20/2021
|
|
POST APPROVAL AMENDMENT FOR 01 PROPOSE ERECT NEW 35 STORY PLUS CELLAR TRAN
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 035
|
| 09/02/2021 |
140861878 |
02 |
A3 |
P APPROVED |
09/07/2021 |
|
UDDIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): RF
|
| 06/10/2021 |
123329521 |
10 |
NB |
P APPROVED |
06/24/2021 |
0082265 PE |
WONG |
|
AMENDED 10/20/2021
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 032
|
| 05/17/2021 |
140814028 |
04 |
A3 |
P APPROVED |
05/18/2021 |
|
ZDANCEWI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 04/16/2021 |
140814028 |
03 |
A3 |
P APPROVED |
04/19/2021 |
|
ZDANCEWI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 04/02/2021 |
140814028 |
02 |
A3 |
P APPROVED |
04/05/2021 |
|
ZDANCEWI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 02/05/2021 |
123329521 |
09 |
NB |
P APPROVED |
02/23/2021 |
0075441 PE |
CHIU |
|
AMENDED 10/20/2021
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 035
|
| 10/24/2019 |
123329521 |
08 |
NB |
P APPROVED |
11/15/2019 |
0075441 PE |
CHIU |
|
AMENDED 10/20/2021
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 035
|
| 10/16/2019 |
123329521 |
07 |
NB |
P APPROVED |
11/20/2019 |
|
POON |
|
AMENDED 10/20/2021
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 032
|
| 07/24/2019 |
140861878 |
01 |
A3 |
X SIGNED OFF |
04/05/2022 |
0071719 PE |
UDDIN |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION ON ROOF AS PER PLAN SUBMITTE
|
|
Work on Floor(s): RF
|
| 07/08/2019 |
140855493 |
01 |
A2 |
X SIGNED OFF |
06/17/2021 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
INSTALLATION AND USE OF X-CLIMB SYSTEM AS PER PLANS FILED HEREWITH. NO CHA
|
|
Work on Floor(s): ROF 004 thru 032
|
| 06/03/2019 |
140852076 |
01 |
A2 |
X SIGNED OFF |
06/17/2021 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
INSTALLATION AND USE OF MINI CRANE AS PER PLANS FILED HEREWITH. NO CHANGE
|
|
Work on Floor(s): ROF 004 thru 032
|
| 01/08/2019 |
123252639 |
01 |
A2 |
X SIGNED OFF |
02/26/2025 |
0099830 PE |
TROFIMCH |
|
NOT APPLICABLE
|
|
INSTALLATION AND SUBMISSION OF A REPEATER AUXILIARY RADIO COMMUNICATION SY
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 12/03/2018 |
123489705 |
01 |
A2 |
X SIGNED OFF |
08/02/2023 |
0075441 PE |
CHIU |
|
NOT APPLICABLE
|
|
FILING FOR THE EMERGENCY GENERATOR IN CONJUNCTION TO THE NEW BUILDING
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 10/23/2018 |
140814037 |
01 |
A3 |
X SIGNED OFF |
05/25/2022 |
0090372 PE |
ZDANCEWI |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLAN SUBMITTED. WORK SHAL
|
|
Work on Floor(s): RF
|
| 10/23/2018 |
140814028 |
01 |
A3 |
X SIGNED OFF |
05/25/2022 |
0090372 PE |
ZDANCEWI |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY 4-POINTS SUSPENDED SCAFFOLD AS PER PLAN SUBMITTE
|
|
Work on Floor(s): OSP
|
| 09/27/2018 |
140807134 |
01 |
A3 |
X SIGNED OFF |
07/28/2021 |
0071719 PE |
UDDIN |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY DUAL CAR PERSONNEL/MATERIAL HOISTS DURING NB
|
|
Work on Floor(s): OSP
|
| 09/11/2018 |
123007628 |
01 |
A2 |
X SIGNED OFF |
05/05/2026 |
0075441 PE |
CHIU |
|
NOT APPLICABLE
|
|
INSTALLATION OF MANUAL/AUTOMATIC SMOKE/HEAT/CO DETECTION AND SPRINKLER FIR
|
|
Work on Floor(s): CEL,ROF 001 thru 035
|
| 05/08/2018 |
123366419 |
01 |
A2 |
X SIGNED OFF |
06/09/2023 |
0072803 PE |
WONG |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY DRY STANDPIPE SYSTEM WITH AN AIR PRESSURIZED ALA
|
|
Work on Floor(s): CEL,ROF 001 thru 033
|
| 12/20/2017 |
123178989 |
01 |
A2 |
X SIGNED OFF |
05/23/2025 |
0075441 PE |
CHIU |
|
NOT APPLICABLE
|
|
INSTALLATION OF A COMBINED SPRINKLER & STANDPIPE SYSTEM IN CONJUNCTION WIT
|
|
Work on Floor(s): CEL,OSP 001 thru 035
|
| 12/20/2017 |
123329521 |
06 |
NB |
R PERMIT-ENTIRE |
01/02/2019 |
0075441 PE |
CHIU |
|
AMENDED 10/20/2021
|
|
HEREWITH FILING UNDERGROUND PLUMBING WORK IN CONJUNCTION WITH PROPOSED NEW
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 032
|
| 12/19/2017 |
123178783 |
01 |
A3 |
X SIGNED OFF |
03/07/2024 |
0016481 RA |
POON |
|
NOT APPLICABLE
|
|
HEREWITH FILING NEW BUILDERS PAVEMENT PLAN IN CONJUNCTION WITH NB APPLICAT
|
|
Work on Floor(s): OSP
|
| 11/16/2017 |
123329521 |
05 |
NB |
R PERMIT-ENTIRE |
12/27/2018 |
0082265 PE |
WONG |
|
AMENDED 10/20/2021
|
|
HEREWITH FILING FOUNDATION WORK IN CONJUNCTION WITH NEW 32 STORY BUILDING
|
|
Work on Floor(s): CEL,001,OSP
|
| 09/13/2017 |
123329521 |
04 |
NB |
R PERMIT-ENTIRE |
12/27/2018 |
0078732 PE |
THOMANN |
|
AMENDED 10/20/2021
|
|
HEREWITH FILING SUPPORT OF EXCAVATION (SOE) WORK IN CONJUNCTION WITH NEW B
|
|
Work on Floor(s): OSP,CEL
|