| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 01/21/2026 |
123049735 |
02 |
A2 |
J P/E DISAPPROVED |
03/13/2026 |
0089538 PE |
MATSUMOT |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,001
|
| 11/14/2025 |
103623900 |
23 |
A1 |
P APPROVED |
11/18/2025 |
|
MCAPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,ROF 001 thru 011
|
| 10/14/2025 |
103623900 |
22 |
A1 |
P APPROVED |
10/16/2025 |
0019160 RA |
MCAPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,ROF 001 thru 011
|
| 07/15/2025 |
103623900 |
21 |
A1 |
P APPROVED |
07/24/2025 |
|
MCAPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,ROF 001 thru 011
|
| 04/30/2025 |
103623900 |
20 |
A1 |
P APPROVED |
05/01/2025 |
|
MCAPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,ROF 001 thru 011
|
| 03/31/2025 |
103623900 |
19 |
A1 |
P APPROVED |
04/01/2025 |
|
MCAPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,ROF 001 thru 011
|
| 09/30/2024 |
103623900 |
18 |
A1 |
P APPROVED |
10/01/2024 |
|
MCAPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,ROF 001 thru 011
|
| 06/10/2024 |
103472895 |
03 |
A2 |
P APPROVED |
06/28/2024 |
0019160 RA |
MCALPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): BAS 001 thru 010
|
| 05/15/2024 |
103683621 |
02 |
A2 |
P APPROVED |
05/22/2024 |
0071143 PE |
FELDMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 NEW GAS-FIRED BOILERS ON ROOF WITH GAS PIP
|
|
Work on Floor(s): CEL,ROF
|
| 03/21/2024 |
102421808 |
04 |
A2 |
P APPROVED |
04/15/2024 |
0019160 RA |
MCALPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): 001
|
| 03/21/2024 |
102421808 |
03 |
A2 |
P APPROVED |
04/15/2024 |
0019160 RA |
MCALPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 08/01/2023 |
104331448 |
02 |
A2 |
P APPROVED |
08/02/2023 |
0082894 PE |
BEHAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001
|
| 07/31/2023 |
104035134 |
04 |
A2 |
P APPROVED |
08/01/2023 |
0082894 PE |
BEHAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
| 07/19/2023 |
104035134 |
03 |
A2 |
P APPROVED |
07/21/2023 |
0019160 RA |
MCALPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 003
|
| 04/28/2023 |
141019421 |
05 |
A2 |
P APPROVED |
05/02/2023 |
|
MCALPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 04/06/2023 |
103623900 |
17 |
A1 |
P APPROVED |
04/07/2023 |
|
MCAPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,ROF 001 thru 011
|
| 01/05/2023 |
141019421 |
04 |
A2 |
P APPROVED |
01/07/2023 |
|
MCALPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 12/01/2022 |
122331841 |
02 |
PA |
P APPROVED |
01/09/2023 |
0027900 RA |
KNIP |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 004
|
| 10/24/2022 |
103623900 |
16 |
A1 |
P APPROVED |
11/01/2022 |
|
MCAPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,ROF 001 thru 011
|
| 09/12/2022 |
141019421 |
03 |
A2 |
P APPROVED |
09/16/2022 |
|
MCALPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 08/01/2022 |
103623900 |
15 |
A1 |
P APPROVED |
08/02/2022 |
|
MCAPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,ROF 001 thru 011
|
| 07/21/2022 |
141019421 |
02 |
A2 |
P APPROVED |
07/21/2022 |
|
MCALPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 06/06/2022 |
141019421 |
01 |
A2 |
X SIGNED OFF |
01/24/2024 |
0019160 RA |
MCALPINE |
|
NOT APPLICABLE
|
|
HEREWITH FILING OCCUPANT PROTECTION PLAN IN CONJUNCTION WITH ALT 1 #103623
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 03/23/2022 |
140986431 |
02 |
A2 |
P APPROVED |
04/21/2022 |
|
MCALPINE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INTERIOR DEMOLITION OF NON LOAD BEARING PAR
|
|
Work on Floor(s): 008,009,010
|
| 03/07/2022 |
123901778 |
02 |
A2 |
P APPROVED |
06/24/2022 |
|
BEHAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): FAC
|
| 02/17/2022 |
104024048 |
05 |
A1 |
D A/P ENTIRE |
02/18/2022 |
|
HARPER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,MEZ
|
| 02/08/2022 |
104103202 |
05 |
PA |
P APPROVED |
02/09/2022 |
|
HARPER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,MEZ
|
| 12/03/2021 |
104024048 |
04 |
A1 |
P APPROVED |
12/29/2021 |
|
HARPER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,MEZ
|
| 12/02/2021 |
104103202 |
04 |
PA |
P APPROVED |
01/06/2022 |
0034858 RA |
HARPER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,MEZ
|
| 11/03/2021 |
104024048 |
03 |
A1 |
P APPROVED |
12/01/2021 |
0034858 RA |
HARPER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,MEZ
|
| 09/30/2021 |
103623900 |
14 |
A1 |
P APPROVED |
10/13/2021 |
|
Vandeber |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 008,009,010,011 002 thru 007
|
| 09/16/2021 |
103623900 |
13 |
A1 |
P APPROVED |
09/28/2021 |
0010137 RA |
Vandeber |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 008,009,010,011 002 thru 007
|
| 12/03/2020 |
140986431 |
01 |
A2 |
X SIGNED OFF |
03/15/2023 |
0019160 RA |
MCALPINE |
|
NOT APPLICABLE
|
|
INTERIOR DEMOLITION OF NON LOAD BEARING PARTITIONS AND WINDOW REPLACEMENT
|
|
Work on Floor(s): 008,009,010
|
| 09/15/2020 |
123865031 |
02 |
A2 |
P APPROVED |
09/25/2020 |
|
LEE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 06/09/2020 |
140908178 |
01 |
A2 |
R PERMIT-ENTIRE |
07/14/2020 |
0083433 PE |
CHANG |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 09/15/2023 HEREWITH FILE FOR INTERIOR ALTERATION OF EXIST. E
|
|
Work on Floor(s): 001
|
| 12/23/2019 |
123865031 |
01 |
A2 |
X SIGNED OFF |
11/16/2020 |
0030647 RA |
LEE |
|
NOT APPLICABLE
|
|
HEREWITH FILE FOR INTERIOR DEMO. OF EXIST. EASTING & DRINKING ESTABLISHMEN
|
|
Work on Floor(s): 001
|
| 06/25/2019 |
123820570 |
01 |
A2 |
X SIGNED OFF |
09/02/2025 |
0025584 RA |
BOSELLI |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION OF EXISTING RESTAURANT AS PER PLAN. INSTALL (2) URINAL
|
|
Work on Floor(s): 001
|
| 05/10/2019 |
123901778 |
01 |
A2 |
X SIGNED OFF |
11/28/2022 |
0082894 PE |
BEHAN |
|
NOT APPLICABLE
|
|
APPLICATION FILED FOR FACADE RESTORATION. FACE BRICK REPAIR AND REPLACEMEN
|
|
Work on Floor(s): FAC
|
| 02/12/2019 |
103623900 |
12 |
A1 |
P APPROVED |
02/14/2019 |
|
Vandeber |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 008,009,010,011 002 thru 007
|
| 11/07/2018 |
123418220 |
01 |
A2 |
R PERMIT-ENTIRE |
11/07/2018 |
0016698 RA |
HAYES |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/22/2023 INTERIOR RENOVATION AS PER PLANS FILED HEREWITH.
|
|
Work on Floor(s): 002
|