| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 12/11/2017 |
121891694 |
06 |
A1 |
P APPROVED |
12/14/2017 |
|
ALICEA |
|
GRANTED 11/17/2014
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP,ROF 001 thru 004
|
| 08/30/2017 |
121891694 |
05 |
A1 |
P APPROVED |
09/12/2017 |
|
ALICEA |
|
GRANTED 11/17/2014
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP,ROF 001 thru 004
|
| 08/10/2017 |
122384151 |
03 |
A2 |
P APPROVED |
08/18/2017 |
|
GERAZOUN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 09/26/2016 |
122384151 |
02 |
A2 |
P APPROVED |
09/29/2016 |
|
GERAZOUN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 04/25/2016 |
121891694 |
04 |
A1 |
P APPROVED |
05/19/2016 |
|
ALICEA |
|
GRANTED 11/17/2014
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP,ROF 001 thru 004
|
| 09/23/2015 |
140406594 |
01 |
A3 |
X SIGNED OFF |
04/10/2017 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PLYWOOD ENCLOSURE AS PER PLANS. NO CHANGE IN USE,
|
|
Work on Floor(s): OSP
|
| 06/04/2015 |
122424135 |
01 |
A2 |
X SIGNED OFF |
06/13/2017 |
0074781 PE |
RENFROE |
|
NOT APPLICABLE
|
|
HEREWITH FILING SOE AND SEQUENCE DEMOLITION DRAWINGS IN CONJUNCTION WITH A
|
|
Work on Floor(s): CEL 001 thru 004
|
| 04/30/2015 |
122384151 |
01 |
A2 |
X SIGNED OFF |
11/28/2017 |
0072050 PE |
GERAZOUN |
|
NOT APPLICABLE
|
|
HEREWITH FILING MH, PL, AND SP IN CONJUNCTION WITH ALT 1 APPLICATION 12189
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 04/22/2015 |
121891694 |
03 |
A1 |
P APPROVED |
08/03/2015 |
|
ALICEA |
|
GRANTED 11/17/2014
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,OSP,ROF 001 thru 004
|
| 04/16/2015 |
140335117 |
01 |
A3 |
X SIGNED OFF |
04/17/2017 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGR
|
|
Work on Floor(s): OSP
|
| 12/31/2014 |
122241706 |
01 |
A3 |
X SIGNED OFF |
03/01/2017 |
0018085 RA |
ALICEA |
|
NOT APPLICABLE
|
|
HEREWITH FILING TO INSTALL A TEMPORARY CONSTRUCTION FENCE
|
|
Work on Floor(s): OSP
|
| 09/25/2014 |
121891694 |
02 |
A1 |
X SIGNED OFF |
12/21/2017 |
0064408 PE |
PAGNOTTA |
|
GRANTED 11/17/2014
|
|
SUBSEQUENT STRUCTURAL FILING
|
|
Work on Floor(s): CEL,OSP,ROF 001 thru 004
|
| 03/13/2014 |
121947386 |
01 |
A2 |
X SIGNED OFF |
11/30/2016 |
0035463 RA |
LESSLIE |
|
NOT APPLICABLE
|
|
ERECTING TEMPORARY MOCK UP AS PER LANDMARKS REQUIREMENTS
|
|
Work on Floor(s): ROF
|
| 01/09/2014 |
121891694 |
01 |
A1 |
X SIGNED OFF |
12/21/2017 |
0018085 RA |
ALICEA |
|
GRANTED 11/17/2014
|
|
INTERIOR AND EXTERIOR RENOVATION TO CONVERT A MULTIPLE DWELLING INTO A SIN
|
|
Work on Floor(s): CEL,OSP,ROF 001 thru 004
|
| 12/01/2011 |
120911790 |
01 |
A2 |
X SIGNED OFF |
10/21/2013 |
0069933 PE |
MURRAY |
|
NOT APPLICABLE
|
|
FACADE STABILIZATION
|
|
Work on Floor(s): FAC
|