| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 12/16/2020 |
121329115 |
11 |
A1 |
P APPROVED |
12/21/2020 |
|
TURETT |
|
AMENDED 12/04/2014
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 10/09/2020 |
121329115 |
10 |
A1 |
P APPROVED |
10/22/2020 |
|
TURETT |
|
AMENDED 12/04/2014
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 07/10/2020 |
121329115 |
09 |
A1 |
P APPROVED |
08/25/2020 |
|
TURETT |
|
AMENDED 12/04/2014
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 05/08/2018 |
121329115 |
08 |
A1 |
P APPROVED |
05/23/2018 |
0086805 PE |
TOBIAS |
|
AMENDED 12/04/2014
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 03/05/2018 |
121329115 |
07 |
A1 |
P APPROVED |
03/09/2018 |
0086805 PE |
TOBIAS |
|
AMENDED 12/04/2014
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 09/25/2017 |
122527649 |
02 |
A3 |
P APPROVED |
10/03/2017 |
|
AHMED |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 11/12/2020
|
|
Work on Floor(s): OSP
|
| 05/09/2017 |
121329115 |
06 |
A1 |
P APPROVED |
06/05/2017 |
0086805 PE |
TOBIAS |
|
AMENDED 12/04/2014
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 11/09/2016 |
122931792 |
01 |
A2 |
X SIGNED OFF |
03/01/2019 |
0086805 PE |
TOBIAS |
|
NOT APPLICABLE
|
|
FILING ALT-2 FOR INSTALLATION OF NEW SPRINKLER SYSTEM.
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 12/23/2015 |
122527649 |
01 |
A3 |
R PERMIT-ENTIRE |
02/28/2017 |
0093179 PE |
AHMED |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/12/2020 INSTALLATION OF SIDEWALK SHED AS PER PLANS FOR RE
|
|
Work on Floor(s): OSP
|
| 08/31/2015 |
122457028 |
01 |
A3 |
X SIGNED OFF |
05/03/2019 |
0089587 PE |
PHAGOO |
|
NOT APPLICABLE
|
|
INSTALLATION OF 35 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED DURING BUILDING
|
|
Work on Floor(s): OSP
|
| 11/18/2014 |
121329115 |
05 |
A1 |
P APPROVED |
12/06/2014 |
0016090 RA |
TURETT |
|
AMENDED 12/04/2014
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 06/25/2014 |
121329115 |
04 |
A1 |
P APPROVED |
07/17/2014 |
0032918 RA |
HERZOG |
|
AMENDED 12/04/2014
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 09/23/2013 |
121332423 |
01 |
A2 |
P APPROVED |
04/21/2014 |
0086805 PE |
TOBIAS |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 08/16/2018 FILING ALT-2 FOR INSTALLATION OF NEW SPRINKLER SY
|
|
Work on Floor(s): CEL,OSP
|
| 09/23/2013 |
121332414 |
01 |
A2 |
X SIGNED OFF |
08/09/2018 |
0074781 PE |
RENFROE |
|
NOT APPLICABLE
|
|
FILING ALT-2 FOR SUPPORTIVE EXCAVATION AND UNDERPINNING AS PER SOE PLANS F
|
|
Work on Floor(s): CEL,OSP
|
| 09/17/2013 |
121329115 |
03 |
A1 |
X SIGNED OFF |
12/22/2020 |
0074781 PE |
RENFROE |
|
AMENDED 12/04/2014
|
|
STRUCTURAL WORK PROPOSED AS PER PLANS FILED HEREWITH.
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 08/09/2013 |
121329115 |
02 |
A1 |
X SIGNED OFF |
12/22/2020 |
0086805 PE |
TOBIAS |
|
AMENDED 12/04/2014
|
|
MECHANICAL AND PLUMBING WORK PROPOSED AS PER PLANS FILED HEREWITH.
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 05/22/2013 |
121329115 |
01 |
A1 |
X SIGNED OFF |
12/22/2020 |
0016090 RA |
TURETT |
|
AMENDED 12/04/2014
|
|
CONVERSION OF THREE FAMILY HOME TO A SINGLE FAMILY HOME. NEW BULKHEAD AND
|
|
Work on Floor(s): CEL,BAS,ROF,OSP 001 thru 003
|
| 05/13/2013 |
121617116 |
01 |
A2 |
X SIGNED OFF |
07/30/2018 |
0025627 RA |
STAPLETO |
|
NOT APPLICABLE
|
|
CONSTRUCTION OF A TEMPORARY MOCK-UP STRUCTURE AT ROOF SIMILATING A NEW PRO
|
|
Work on Floor(s): BAS 001 thru 003
|
| 03/12/2013 |
121543785 |
01 |
A2 |
R PERMIT-ENTIRE |
04/29/2013 |
0025627 RA |
STAPLETO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 02/20/2019 RESIDENTIAL RENOVATION OF AN EXISTING 4 FAMILY WA
|
|
Work on Floor(s): BAS 001 thru 003
|