| 01/15/2026 |
102857847 |
02 |
A3 |
D A/P ENTIRE |
01/15/2026 |
0013798 RA |
PEACHY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 01/08/2026 |
102470425 |
02 |
A2 |
D A/P ENTIRE |
01/08/2026 |
0013798 RA |
PEACHY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 002 thru 004
|
| 12/18/2025 |
102774464 |
02 |
A2 |
F ASSIGNED TO P/E |
12/29/2025 |
0013798 RA |
PEACHY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001,CEL,ROF
|
| 07/10/2017 |
140644060 |
01 |
A2 |
R PERMIT-ENTIRE |
07/28/2017 |
0070592 PE |
STILLER |
|
NOT APPLICABLE
|
|
APT4 - FILING ON BEHALF OF CONTRACTOR FOR MINOR ALTERATION OF APT4. NO CHA
|
|
Work on Floor(s): 004
|
| 09/26/2000 |
102774464 |
01 |
A2 |
R PERMIT-ENTIRE |
12/07/2000 |
0054064 PE |
Choy |
|
NOT APPLICABLE
|
|
Install A/C units for and existing store on first floor and cellar.Install
|
|
Work on Floor(s): 001,CEL,ROF
|
| 03/30/2000 |
102857847 |
01 |
A3 |
R PERMIT-ENTIRE |
04/13/2000 |
0054064 PE |
Choy |
|
NOT APPLICABLE
|
|
Replace existing wood joists with new steel beams on first floor.
|
|
Work on Floor(s): 001
|
| 03/29/2000 |
102855698 |
01 |
A3 |
R PERMIT-ENTIRE |
04/05/2000 |
|
ZAHARIA |
|
NOT APPLICABLE
|
|
INSTALLATION OF 25' HEAVY DUTY SIDEWALK BRIDGE DURING FACADE REPAIR.
|
|
Work on Floor(s): GRD
|
| 09/02/1999 |
102470425 |
01 |
A2 |
R PERMIT-ENTIRE |
05/18/2000 |
0054064 PE |
Choy |
|
NOT APPLICABLE
|
|
RECONSTRUCTION OF EXISTING PARAPET WALL AT FRONT OF BUILDING.
|
|
Work on Floor(s): ROF 002 thru 004
|
| 02/26/1993 |
100585528 |
01 |
A2 |
X SIGNED OFF |
06/29/1993 |
0054064 PE |
CHOY |
|
NOT APPLICABLE
|
|
INSTALL PARTITIONS & PLUMBING FIXTURE ON 2ND FLR. REPLACE BOILER ON 2N
|
|
Work on Floor(s): 2
|