FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
02/01/2018 |
123132234 |
02 |
A2 |
P APPROVED |
02/02/2018 |
|
BILLAH |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 5TH
|
01/02/2018 |
123132234 |
01 |
A2 |
X SIGNED OFF |
11/06/2020 |
0081186 PE |
BILLAH |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION TO RENOVATE APT 11 AT 5TH FLOOR. WORK WILL INCLUDE NE
|
|
Work on Floor(s): 5TH
|
11/21/2016 |
122952581 |
01 |
A3 |
R PERMIT-ENTIRE |
11/22/2016 |
0031839 RA |
CHOI |
|
NOT APPLICABLE
|
|
BUSINESS ACCESSORY AWNING. NO CHANGE TO USE, EGRESS OR OCCUPANCY
|
|
Work on Floor(s): 001
|
11/16/2016 |
122946580 |
01 |
A3 |
H P/E IN PROCESS |
01/31/2017 |
0031839 RA |
CHOI |
|
NOT APPLICABLE
|
|
BUSINESS ACCESSORY AWNING. NO CHANGE TO USE, EGRESS OR OCCUPANCY
|
|
Work on Floor(s): 001
|
11/16/2016 |
122946599 |
01 |
A3 |
R PERMIT-ENTIRE |
11/17/2016 |
0031839 RA |
CHOI |
|
NOT APPLICABLE
|
|
BUSINESS ACCESSORY AWNING. NO CHANGE TO USE, EGRESS OR OCCUPANCY
|
|
Work on Floor(s): 001
|
11/15/2016 |
140575704 |
01 |
A3 |
H P/E IN PROCESS |
11/15/2016 |
0031839 RA |
CHOI |
|
NOT APPLICABLE
|
|
ADMIN CLOSED 01/14/2017 BUSINESS ACCESSORY AWNING. NO CHANGE TO USE, EGRES
|
|
Work on Floor(s): 001
|
11/13/2015 |
140429551 |
01 |
A2 |
X SIGNED OFF |
02/22/2016 |
0083149 PE |
ALAUDDIN |
|
NOT APPLICABLE
|
|
ALTERATION OF EXISTING FIRE ESCAPE ON RIVINGTON STREET TO RELOCATE DROP DO
|
|
Work on Floor(s): OSP
|
06/19/2015 |
122446157 |
01 |
A2 |
X SIGNED OFF |
08/19/2015 |
0083149 PE |
ALAUDDIN |
|
NOT APPLICABLE
|
|
FILED HEREWITH FOR INSTALLATION OF COOLING TOWER ON ROOF AND AUXILIARIES.
|
|
Work on Floor(s): ROF
|
04/04/2014 |
121969539 |
01 |
A2 |
X SIGNED OFF |
03/07/2017 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION TO RENOVATE APT 12 TO INCLUDE NEW PARTITION, REPLACE
|
|
Work on Floor(s): 5TH
|
02/06/2014 |
121916294 |
01 |
A2 |
R PERMIT-ENTIRE |
02/12/2014 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION TO INCLUDE NEW PARTITION, REPLACE EXISTING PLUMBING
|
|
Work on Floor(s): 4TH
|
03/20/2013 |
121018004 |
02 |
A2 |
P APPROVED |
04/04/2013 |
|
MALLEA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
11/30/2012 |
120982473 |
02 |
A2 |
P APPROVED |
11/21/2013 |
|
MAK |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 5TH
|
07/27/2012 |
121169396 |
01 |
A2 |
X SIGNED OFF |
07/21/2015 |
0083941 PE |
POPESCU |
|
NOT APPLICABLE
|
|
FILED HEREWITH FOR INSTALLATION OF STEEL DUNNAGE ON ROOF. THERE SHALL BE N
|
|
Work on Floor(s): ROF
|
07/27/2012 |
121169715 |
01 |
A2 |
X SIGNED OFF |
02/20/2013 |
0019548 RA |
HAMMOND |
|
NOT APPLICABLE
|
|
FILING TO INSTALL FIRE SUPPRESSION SYSTEM. ALL ELECTRICAL EQUIPMENT. NO CH
|
|
Work on Floor(s): 001
|
07/19/2012 |
121158433 |
01 |
A2 |
R PERMIT-ENTIRE |
07/19/2012 |
0083433 PE |
CHANG |
|
NOT APPLICABLE
|
|
REPLACEMENT OF EXHAUST DUCT. NO CHANGE IN USE, OCCUPANCY AND MEANS OF EGRE
|
|
Work on Floor(s): 001
|
07/18/2012 |
121156532 |
01 |
A2 |
P APPROVED |
07/19/2012 |
0083941 PE |
POPESCU |
|
NOT APPLICABLE
|
|
FILED HEREWITH FOR INSTALLATION OF COOLING TOWER ON ROOF AND AUXILIARIES.
|
|
Work on Floor(s): ROF
|
07/10/2012 |
121134744 |
01 |
A2 |
R PERMIT-ENTIRE |
02/12/2014 |
0087678 PE |
BAZINI |
|
NOT APPLICABLE
|
|
REPLACE OIL BURNER WITH GAS/OIL BURNER ON EXISTING LOW PRESSURE BOILER. NO
|
|
Work on Floor(s): CEL
|
06/20/2012 |
121121589 |
01 |
A2 |
D A/P ENTIRE |
06/20/2012 |
0083941 PE |
POPESCU |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 07/10/2012 APPLICATION FILED HEREWITH FOR INSTALLATION OF CO
|
|
Work on Floor(s): CEL,ROF
|
05/23/2012 |
121089035 |
01 |
A2 |
X SIGNED OFF |
03/08/2013 |
0021308 RA |
CHRISTMA |
|
NOT APPLICABLE
|
|
INSTALLATION OF FIRE SUPPRESSION SYSTEM AS PER PLANS FILED HEREWITH. THER
|
|
Work on Floor(s): 001
|
05/08/2012 |
121059200 |
01 |
A2 |
X SIGNED OFF |
10/08/2013 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION TO INCLUDE NEW PARTITION, REPLACE EXISTING PLUMBING
|
|
Work on Floor(s): 3RD
|
05/03/2012 |
121059193 |
01 |
A2 |
R PERMIT-ENTIRE |
05/11/2012 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION TO INCLUDE NEW PARTITION, REPLACE EXISTING PLUMBING
|
|
Work on Floor(s): 2ND
|
04/25/2012 |
121056846 |
01 |
A2 |
R PERMIT-ENTIRE |
05/21/2012 |
0020506 RA |
MALLEA |
|
NOT APPLICABLE
|
|
CONSTRUCTION FENCE FILED IN CONJUNCTION WITH APP. # 121018004
|
|
Work on Floor(s): 001
|
03/22/2012 |
121018004 |
01 |
A2 |
R PERMIT-ENTIRE |
05/09/2012 |
0020506 RA |
MALLEA |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION TO INCLUDE NEW INTERIOR PARTITIONS, PLUMBING & STRUC
|
|
Work on Floor(s): 001
|
02/16/2012 |
120982473 |
01 |
A2 |
R PERMIT-ENTIRE |
02/21/2012 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION TO INCLUDE NEW PARTITION, REPLACE EXISTING PLUMBING
|
|
Work on Floor(s): 5TH
|
01/13/2012 |
120713781 |
02 |
A2 |
P APPROVED |
01/18/2012 |
|
MAK |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 3RD
|
11/18/2011 |
120903086 |
01 |
A2 |
X SIGNED OFF |
02/08/2012 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION TO INCLUDE NEW PARTITION, REPLACE EXISTING PLUMBING
|
|
Work on Floor(s): 3RD
|
10/24/2011 |
120868392 |
01 |
A2 |
X SIGNED OFF |
02/08/2012 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION TO INCLUDE NEW PARTITION, REPLACE EXISTING PLUMBING
|
|
Work on Floor(s): 6TH
|
10/03/2011 |
120842687 |
01 |
A2 |
X SIGNED OFF |
08/08/2012 |
0052367 PE |
VILAS |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION OF EXISTING COMMERCIAL SPACE ON CELLAR AND FIRST FLOOR
|
|
Work on Floor(s): CEL,001
|
06/10/2011 |
120713781 |
01 |
A2 |
R PERMIT-ENTIRE |
10/14/2011 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION TO INCLUDE NEW PARTITION, REPLACE EXISTING PLUMBING
|
|
Work on Floor(s): 3RD
|
02/25/2011 |
120598978 |
02 |
A2 |
P APPROVED |
07/26/2011 |
|
MAK |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 SEE SECTION #24.
|
|
Work on Floor(s): 003,005
|
02/04/2011 |
120598978 |
01 |
A2 |
X SIGNED OFF |
02/08/2012 |
0078495 PE |
MAK |
|
NOT APPLICABLE
|
|
SEE SECTION #24.
|
|
Work on Floor(s): 003,005
|
10/27/2010 |
120512677 |
01 |
A3 |
R PERMIT-ENTIRE |
10/29/2010 |
0066791 PE |
PARIHAR |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED FILED FOR REMEDIAL REPAI
|
|
Work on Floor(s): OSP
|
12/02/1994 |
100944356 |
01 |
A2 |
R PERMIT-ENTIRE |
12/15/1994 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
REPLACE BOILER AND OIL BURNER. NO CHANGE IN EGRESS, OCCUPANCY OR USE UND
|
|
Work on Floor(s): CEL
|