FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
08/07/2024 |
121185369 |
21 |
NB |
P APPROVED |
08/21/2024 |
|
MAKOI |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1,PT2 001 thru 024
|
07/11/2024 |
121185369 |
20 |
NB |
P APPROVED |
07/24/2024 |
0087988 RA |
DOW |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
05/07/2024 |
121185369 |
19 |
NB |
P APPROVED |
05/31/2024 |
0087988 RA |
DOW |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
04/26/2024 |
121185369 |
18 |
NB |
P APPROVED |
05/28/2024 |
|
MAKOI |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1,PT2 001 thru 024
|
04/18/2024 |
122020179 |
05 |
A3 |
P APPROVED |
04/22/2024 |
|
MAKOOI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 015
|
01/18/2024 |
122889810 |
08 |
A2 |
P APPROVED |
01/19/2024 |
|
WALL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
12/21/2023 |
121185369 |
17 |
NB |
P APPROVED |
02/06/2024 |
|
MAKOI |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1,PT2 001 thru 024
|
12/05/2023 |
122897623 |
06 |
A2 |
P APPROVED |
12/08/2023 |
|
DOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
11/06/2023 |
122020179 |
04 |
A3 |
P APPROVED |
11/08/2023 |
|
MAKOOI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 015
|
10/31/2023 |
122889810 |
07 |
A2 |
P APPROVED |
11/01/2023 |
|
WALL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
10/13/2023 |
121185369 |
16 |
NB |
P APPROVED |
10/19/2023 |
0072050 PE |
GERAZOUN |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): CEL,PT1,PT2,ROF 001 thru 024
|
08/28/2023 |
121185369 |
15 |
NB |
P APPROVED |
10/13/2023 |
0087988 RA |
DOW |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
06/27/2023 |
122020179 |
03 |
A3 |
P APPROVED |
07/26/2023 |
0034686 RA |
MAKOOI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 015
|
06/21/2023 |
122889810 |
06 |
A2 |
P APPROVED |
06/22/2023 |
|
WALL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
05/15/2023 |
122889810 |
05 |
A2 |
P APPROVED |
05/18/2023 |
0078542 PE |
WALL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
05/01/2023 |
122897623 |
05 |
A2 |
P APPROVED |
05/02/2023 |
|
DOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
04/21/2023 |
121185369 |
14 |
NB |
P APPROVED |
12/06/2023 |
|
MAKOI |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,PT1,PT2 001 thru 024
|
03/03/2023 |
122889810 |
04 |
A2 |
P APPROVED |
03/06/2023 |
|
JUNDI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
02/06/2023 |
122897623 |
04 |
A2 |
P APPROVED |
03/16/2023 |
|
DOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
01/23/2023 |
121185369 |
13 |
NB |
P APPROVED |
02/23/2023 |
0072050 PE |
GERAZOUN |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 05 SPRINKLER,MECHANICAL,STANDPIPE FILED IN CON
|
|
Work on Floor(s): CEL,PT1,PT2,ROF 001 thru 024
|
01/12/2023 |
122889810 |
03 |
A2 |
P APPROVED |
01/21/2023 |
|
JUNDI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
01/12/2023 |
121185369 |
12 |
NB |
P APPROVED |
02/23/2023 |
0087988 RA |
DOW |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
01/04/2023 |
121185369 |
11 |
NB |
P APPROVED |
02/23/2023 |
|
MAKOI |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 01 CONSTRUCT NEW 24 STORY BUILDING MIXED USE B
|
|
Work on Floor(s): CEL,ROF,PT1,PT2 001 thru 024
|
11/09/2022 |
122020179 |
02 |
A3 |
P APPROVED |
11/21/2022 |
|
MAKOOI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 015
|
10/07/2022 |
121185369 |
10 |
NB |
P APPROVED |
10/18/2022 |
|
MAKOI |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
09/30/2022 |
122897623 |
03 |
A2 |
P APPROVED |
10/06/2022 |
|
DOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
06/13/2022 |
121185369 |
09 |
NB |
P APPROVED |
09/14/2022 |
0034686 RA |
MAKOI |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 01 PROPOSED FOURTEEN STORY MIXED USE DEVELOPME
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
01/05/2018 |
122897623 |
02 |
A2 |
P APPROVED |
06/03/2022 |
0087988 PE |
DOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
01/05/2018 |
122889810 |
02 |
A2 |
P APPROVED |
12/13/2022 |
0083095 PE |
JUNDI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
12/27/2017 |
121185369 |
08 |
NB |
P APPROVED |
01/10/2018 |
0073902 PE |
KWON |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
09/22/2016 |
122889810 |
01 |
A2 |
R PERMIT-ENTIRE |
08/01/2023 |
0078542 PE |
WALL |
|
NOT APPLICABLE
|
|
PROVIDE SOE PLANS AND DETAILS IN CONJUNCTION WITH NEW BUILDING APPLICATION
|
|
Work on Floor(s): CEL
|
09/22/2016 |
122897623 |
01 |
A2 |
R PERMIT-ENTIRE |
08/01/2023 |
0087988 PE |
DOW |
|
NOT APPLICABLE
|
|
PROVIDE FOUNDATION AND EARTHWORK PLANS AND DETAILS IN CONJUNCTION WITH NEW
|
|
Work on Floor(s): CEL
|
09/01/2015 |
121185369 |
07 |
NB |
P APPROVED |
09/02/2015 |
0065106 PE |
SHARON |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
08/18/2015 |
121185369 |
06 |
NB |
P APPROVED |
09/02/2015 |
|
FISCHER |
|
AMENDED 05/31/2024
|
|
POST APPROVAL AMENDMENT FOR 01 PROPOSED FOURTEEN STORY MIXED USE DEVELOPME
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
01/15/2015 |
121185369 |
05 |
NB |
R PERMIT-ENTIRE |
12/09/2015 |
0072050 PE |
GERAZOUN |
|
AMENDED 05/31/2024
|
|
SPRINKLER,MECHANICAL,STANDPIPE FILED IN CONJUNCTION WITH NB JOB#121185369
|
|
Work on Floor(s): CEL,PT1,PT2,ROF 001 thru 024
|
10/06/2014 |
121185369 |
04 |
NB |
R PERMIT-ENTIRE |
12/09/2015 |
0087988 RA |
DOW |
|
AMENDED 05/31/2024
|
|
STRUCTURE,FOUNDATION, EXCAVATION, SOE FILED IN CONJUNCTION WITH JOB # 121
|
|
Work on Floor(s): CEL,ROF 001 thru 014
|
06/19/2014 |
122044509 |
01 |
DM |
X SIGNED OFF |
09/01/2015 |
0090354 PE |
SIQECA |
|
NOT APPLICABLE
|
|
FULL DEMOLITION OF EXISTING 1-STORY MASONRY COMMERCIAL BUILDING
|
|
Work on Floor(s): 001
|
05/27/2014 |
122020179 |
01 |
A3 |
R PERMIT-ENTIRE |
08/29/2014 |
0034686 RA |
MAKOOI |
|
NOT APPLICABLE
|
|
BPP FILED IN CONJUNCTION WITH NB JOB # 121185369 A TOTAL LINAER FEET OF 20
|
|
Work on Floor(s): 001 thru 015
|
05/20/2014 |
121185369 |
03 |
NB |
J P/E DISAPPROVED |
09/09/2014 |
0065106 PE |
SHARON |
|
AMENDED 05/31/2024
|
|
DOC WITHDRAWN 09/29/2014 SPRINKLER, MECHANICAL, STANDPIPE FILED IN CONJUN
|
|
Work on Floor(s): CEL,ROF 001 thru 015
|
05/09/2014 |
121185369 |
02 |
NB |
J P/E DISAPPROVED |
09/09/2014 |
0065106 PE |
SHARON |
|
AMENDED 05/31/2024
|
|
DOC WITHDRAWN 09/29/2014 STRUCTURE FILED IN CONJUNCTION WITH JOB # 1211853
|
|
Work on Floor(s): CEL,ROF 001 thru 015
|