| 300469589 PL | 12/11/1996 | 12:15 | 300469589 | 3-96-09360 | 300P | INSPECTION OK - NO FURTHER ACTION | |
| 300469589 PL | 02/10/1997 | 10:00 | 300469589 | 3-97-01114 | 300P | INSPECTION OK - NO FURTHER ACTION | |
| 300537667 PL | 12/11/1996 | 12:30 | 300537667 | 3-96-09358 | 300P | INSPECTION OK - NO FURTHER ACTION | Y |
| 300542606 PL | 11/27/2013 | 8:00 | 300542606 | 3-13-21820 | 300P | INSPECTION CONDUCTED | |
| 300542606 PL | 12/05/2013 | TBD | 300542606 | 3-13-23068 | 300P | INSPECTION CONDUCTED | |
| 300542606 PL | 12/06/2013 | TBD | 300542606 | 3-13-23052 | 300P | INSPECTION CONDUCTED | |
| 300657518 PL | 06/09/2015 | TBD | 300657518 | 3-15-11509 | 300P | INSPECTION CONDUCTED | |
| 300657518 PL | 07/21/2015 | TBD | 300657518 | 3-15-14080 | 300P | INSPECTION CONDUCTED | |
| 320051340 PL | 02/08/2010 | 10:00 | 320051340 | 3-10-01850 | 300P | INSPECTION CONDUCTED | Y |
| 320051340 PL | 06/23/2010 | TBD | 320051340 | 3-10-09879 | 300P | INSPECTION CONDUCTED | |
| 320124432 PL | 00/00/0000 | TBD | 320124432 | 3-11-09946 | DOB CANCELLED | ||
| 320124432 PL | 06/10/2011 | 15:00 | 320124432 | 3-11-08954 | 300P | INSPECTION CONDUCTED | |
| 320124432 PL | 06/17/2011 | TBD | 320124432 | 3-11-09776 | 300P | INSPECTION CONDUCTED | |
| 320124432 PL | 06/27/2011 | 8:00 | 320124432 | 3-11-09947 | 300P | INSPECTION CONDUCTED | |
| 320124432 PL | 08/04/2011 | TBD | 320124432 | 3-11-12802 | 300P | INSPECTION CONDUCTED | Y |