| Premises: 1230 FULTON AVENUE BRONX | BIN: 2004241 Block: 2612 Lot: 2 | |
| PERMIT | INSPECTION DATE / TIME |
JOB # | WORK ORDER | BADGE | STATUS | GAS | |
| 220228563 PL | 03/29/2013 | 12:51 | 220228563 | 2-13-01521 | 2155 | INSPECTION CONDUCTED | |
| 220228563 PL | 07/05/2013 | TBD | 220228563 | 2-13-03786 | 200P | INSPECTION CONDUCTED | |
| 240201214 PL | 12/12/2017 | 13:00 | 240201214 | 2-17-17292 | 200P | INSPECTION CONDUCTED | |
| 240201214 PL | 12/18/2017 | 13:54 | 240201214 | 2-17-17294 | 200P | INSPECTION CONDUCTED | |
| 240201214 PL | 02/05/2018 | 11:00 | 240201214 | 2-18-01387 | 200P | INSPECTION CONDUCTED | |
| 240201214 PL | 02/05/2018 | 11:00 | 240201214 | 2-18-01388 | 200P | INSPECTION CONDUCTED | |
| 240201214 PL | 02/07/2018 | 14:44 | 240201214 | 2-18-01389 | 200P | INSPECTION CONDUCTED | |
| 240201214 PL | 02/07/2018 | 14:44 | 240201214 | 2-18-01390 | 200P | INSPECTION CONDUCTED | |
| 201012581 PR | 12/21/2007 | 8:00 | 201012581 | 2-07-09646 | 200P | INSPECTION CONDUCTED | |
| 201012581 PR | 12/21/2007 | TBD | 201012581 | 2-08-00752 | 200P | INSPECTION CONDUCTED | Y |