| Premises: 8 WEST 38 STREET MANHATTAN | BIN: 1075696 Block: 839 Lot: 55 | |
| PERMIT | INSPECTION DATE / TIME |
JOB # | WORK ORDER | BADGE | STATUS | GAS | |
| 103252533 PL | 03/05/2003 | 11:45 | 103252533 | 1-03-03360 | 100P | INSPECTION OK - NO FURTHER ACTION | |
| 120439588 PL | 04/08/2011 | TBD | 120439588 | 1-11-09938 | 100P | INSPECTION CONDUCTED | |
| 122956649 PL | 12/22/2016 | 15:00 | 122956649 | 1-17-03880 | 100P | INSPECTION CONDUCTED | |
| 123103925 SP | 02/18/2019 | 11:28 | 123103925 | 1-19-09975 | 100P | INSPECTION CONDUCTED | |
| 123103925 SP | 02/25/2019 | 8:00 | 123103925 | 1-19-11648 | 100P | INSPECTION CONDUCTED | |
| 123103925 PL | 07/05/2018 | 8:00 | 123103925 | 1-18-46069 | 100P | INSPECTION CONDUCTED | |
| 123103925 PL | 07/30/2018 | 10:18 | 123103925 | 1-18-46070 | 100P | INSPECTION CONDUCTED | |
| 123424758 SP | 06/08/2018 | 13:30 | 123424758 | 1-18-35743 | 100P | INSPECTION CONDUCTED | |
| 123424758 SP | 07/13/2018 | 14:30 | 123424758 | 1-18-42790 | 100P | INSPECTION CONDUCTED | |
| 123424758 PL | 06/08/2018 | 13:00 | 123424758 | 1-18-35741 | 100P | INSPECTION CONDUCTED | |
| 123424758 PL | 06/15/2018 | 14:28 | 123424758 | 1-18-37028 | 100P | INSPECTION CONDUCTED | |
| 123530107 PL | 09/27/2018 | 11:00 | 123530107 | 1-18-59911 | 100P | INSPECTION CONDUCTED | |
| 123530107 PL | 10/29/2018 | 12:25 | 123530107 | 1-18-66740 | 100P | INSPECTION CONDUCTED | |
| 123807531 SP | 07/06/2019 | 18:25 | 123807531 | 1-19-38248 | 100P | INSPECTION CONDUCTED | |
| 123807531 SP | 02/10/2020 | 10:00 | 123807531 | 1-20-05299 | 100P | INSPECTION CONDUCTED | |