| COMMENTS |
| NOT RESOLVED |
11/16/1994 |
GAS TEST TAKEN FROM BSMT.AT METER TO 4TH,5TH & ROOF.SATISFACTORY. |
| NOT RESOLVED |
11/16/1994 |
UP TO 7 CELLINOID VALVES ONLY. |
| NOT RESOLVED |
11/16/1994 |
MUST MERCURY TEST ALL 7 GAS LINES FROM OUTLET TO CELLINOID VALVE. |
| NOT RESOLVED |
11/16/1994 |
FILE TO AMEND PLAN & SCH.B" TO SHOW 9 LAB TABLES & 7 CELLINOID |
| NOT RESOLVED |
11/16/1994 |
VALVE SUPPLIED WITH GAS. |
| NOT RESOLVED |
11/16/1994 |
TO CON ED OK TO INSTALL SERVICE. |
| NOT RESOLVED |
11/16/1994 |
DO NOT SET METER UNTIL FINAL TEST SATISFACTORY.PW2 REQUIRED. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|