BIS Menu  |  Electrical Inspection Work Order   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: Z159186
Premises: 255 WEST 139 STREET MANHATTAN BIN: 1060352     Block: 2025   Lot: 7
   

DOB NOW: Inspections

Application Completed and Certified

Filed: 255 W 139 ST Census Tract:   230 Health Area:  1000
BASEMENT,1,2,3,4 Admin Area:   Z - UPPER MANHATTAN Inspection Area:   B
NEW YORK, NY 10030 Community Board:   110
DOB Cross Street(s):   PEDESTRIAN PATH,    FREDERICK DOUGLASS BOULEVARD
Status:   C - JOB IS SIGNED OFF 10/27/2017
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  02/10/2017 12:11 PM
Application Entered:   02/10/2017 Job Start Date:   02/11/2017
Last Change:   10/27/2017 Job End Date:   02/10/2018
Appointment Status:   
Last Inspection By:   GARY MCCALLA       On     08/28/2017      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 011171 Licensee Name: TREVOR DUNWELL
Firm: 002607 Firm Name: APPROVED ELECTRIC CORP.
Firm Phone: 718-882-3145  Firm Address: 3550 WHITE PLAINS ROAD STE #9 BRONX NY 10467 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
1 - SERVICE WORK/NOTIFY UTILITY
6 - GENERAL WIRING
Total Fee:  $642.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: JOSEPH KALLIMAN
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   Yes
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  1  200 AMPS
C. 201 Up to 600 AMPS  1  400 AMP
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  10  #2
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  1  500 MCM
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  10  12-24 CKT
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
BAS      12    10             
001      38    14  30         
002      38    14  30         
003      38    14  30         
004      38    14  30         
Buildings Total   164    60  130     24           
Total Units : 378 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 9 #4-Wire 0 #10-Wire 0
Existing Meters 4 + New Meters 9 - Removed Meters 4 = Total Meters 9

Power Auth Flag: I - ISSUED Objection Flag:
Power Requested: 02/10/2017 Notice:  
Power Issued: 02/10/2017 Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  

 
Inspection Details
 

INSPECTION FOR APPLICATION #: Z159186
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 08/28/2017 08/28/2017 GYM C (105) (0) Y
INSPECTION COMMENTS: PASS




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Electrical Inspection Work Order