| BUILDING OVERVIEW |
Are Feeders Being Installed? : Yes |
| (If feeders are being installed, provide a wiring diagram and calculations at the time of inspection) |
| Building Overview Work Items |
QUANTITY |
DESCRIPTION |
| SERVICE SWITCHES |
|
| A. Up to 100 AMPS |
0 |
|
| B. 101 Up to 200 AMPS |
0 |
|
| C. 201 Up to 600 AMPS |
0 |
|
| D. 601 Up to 1200 AMPS |
0 |
|
| E. Over 1200 AMPS |
0 |
|
| SER. ENT. & FDR COND (EACH SET) |
|
| A. Up to #2 CONDUCTOR |
0 |
|
| B. Over #2 to 1/0 |
0 |
|
| C. Over 1/0 to 250 MCM |
1 |
4 # 3/0 |
| D. Over 250 MCM |
0 |
|
| PANELS |
|
| A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs |
0 |
|
| B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs |
0 |
|
| C. 3 Phase Up to 225 AMPS |
0 |
|
| D. 3 Phase Over 225 AMPS |
0 |
|
| ELEVATORS / ESCALATORS / MATERIAL LIFTS |
|
| A. Total No. of Elevators / Escalators / Material Lifts |
0 |
|
| B. Each Additional 10 Floors Or Less |
0 |
|
| BOILER CONTROLS |
0 |
|
INSP ID |
FIELD DATE |
DISP DATE |
INSP ID |
FLD DISP |
OBJ DISP |
ENRG REC |
TIME INSP |
REINSP DATE |
NEW OBJ |
APPT FLAG |
| |
| (1) |
08/04/2017 |
08/07/2017 |
MLF |
N |
|
|
(15) |
|
(0) |
Y |
| INSPECTION COMMENTS:
|
CONTRACTOR WILL RESCHEDULE " RUNNING LATE"
|
| |
| (2) |
08/16/2017 |
08/16/2017 |
MQY |
V |
|
|
(34) |
|
(3) |
|
| INSPECTION COMMENTS:
|
ISSUED OBJECTIONS. CONTRACTOR SAID LEADER ELECTRIC INSTALLED THE NEW SERVICE SWITCH INSIDE THE RESTAURANT. CONTRACTOR HAS TO AMEND THIS APPLICATION TO INCLUDE SERVICE SWITCH AND FEEDERS. FULL INSPECTION NEEDED
|
| |
| (3) |
12/12/2017 |
12/12/2017 |
TOR |
H |
X |
|
(30) |
|
(0) |
Y |
| INSPECTION COMMENTS:
|
FAIL
|
| |
| (4) |
02/26/2018 |
02/27/2018 |
STP |
N |
|
|
(20) |
|
(0) |
Y |
| INSPECTION COMMENTS:
|
CONTRACTOR DID NOT SHOW UP.
|
| |
| (5) |
09/30/2019 |
10/01/2019 |
VTC |
V |
Y |
|
(50) |
|
(3) |
|
| INSPECTION COMMENTS:
|
FAIL
|
| |
| (6) |
01/27/2022 |
01/27/2022 |
AGF |
N |
|
|
(35) |
|
(0) |
Y |
| INSPECTION COMMENTS:
|
NO SHOW ... INCOMPLETE INSPECTION , CALLS MADE TO OFFICE , COULD NOT GET IN TOUCH WITH ANYONE .
|
| |
| (7) |
02/15/2022 |
02/16/2022 |
DWB |
V |
R |
|
(66) |
|
(3) |
|
| INSPECTION COMMENTS:
|
INSPECTION COMPLETE,PAA REQUIRED, OBJECTION ISSUED. SEE ATTACHMENT LETTER OF APPROVAL OF SERVICES SWITCHES.
|
| |
| (8) |
10/04/2022 |
10/04/2022 |
TSO |
J |
Y |
|
(0) |
|
(0) |
|
| INSPECTION COMMENTS:
|
CERTIFIED - OBJ-22-000031727
|
| OBJECTION ID |
OBJECTION CODE |
OBJECTION DESCRIPTION & COMMENTS |
STAT |
FIRST |
LATEST |
RESLVD |
| |
| 001 |
(999) |
OTHER (BASEMENT) SERVICE SWITCH NOT GROUPED (230.40) |
RSLV |
08/16/2017 |
08/16/2017 |
02/15/2022 |
| |
| 002 |
(999) |
OTHER (BASEMENT)LOAD SIDE OF SERVICE SWITCH NO EGC IN THE GREENFIELD FEEDERS (PANELSNOT GROUNDED)(250.118) |
RSLV |
08/16/2017 |
08/16/2017 |
09/30/2019 |
| |
| 003 |
(999) |
OTHER (BASEMENT) SERVICE SWITCH NOT GROUNDED OR BONDED AS PER ARTICLE 250) |
RSLV |
08/16/2017 |
08/16/2017 |
09/30/2019 |
| |
| 004 |
(133) |
NO GROUND ROD: BASEMENT OR OUTSIDE (BASEMENT) SUPPLEMENTAL GROUND NOT PROVIDED |
RSLV |
09/30/2019 |
09/30/2019 |
02/15/2022 |
| |
| 005 |
(999) |
OTHER (BASEMENT) KO SEALS MISSING IN TROUGH 110.12 |
RSLV |
09/30/2019 |
09/30/2019 |
02/15/2022 |
| |
| 006 |
(999) |
OTHER (BASEMENT) GREENFIELD NOT PROPERLY SUPPORTED 348.30 |
RSLV |
09/30/2019 |
09/30/2019 |
02/15/2022 |
| |
| 007 |
(999) |
OTHER (ALL FLOORS)PAA REQUIRED, CONTRACTOR NEED TO ADD, SERVICES SWITCHES, 1-201 TO600 AMP, TOTAL 1 INSTALLED,- FEEDERS, 1 SET OVER 250 MCM, TOTAL 2SET INSTALLED. SEE COMMENT. |
OPEN |
02/15/2022 |
02/15/2022 |
|
| |
| 008 |
(176) |
INSTALLATION DOES NOT MEET CODE REQUIREMENTS (BASEMENT)110.16, ARC FLASH LABEL NOT PROVIDED AT NEW ELECTRICAL EQUIPINSTALLED |
OPEN |
02/15/2022 |
02/15/2022 |
|
| |
| 009 |
(176) |
INSTALLATION DOES NOT MEET CODE REQUIREMENTS (BASEMENT) SERVICE DISCONNECTS MUST BE IDENTIFIED AS SUCH 230.70(B) |
RSLV |
02/15/2022 |
02/15/2022 |
10/04/2022 |