BIS Menu  |  Electrical Applications  |  Electrical Inspection Work Order  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: Z154974
Premises: 341 WEST 70 STREET MANHATTAN BIN: 1030926     Block: 1182   Lot: 12
  Printable (PDF) version of this Permit  

DOB NOW: Inspections


Filed: 345 W 70 ST Census Tract:   159 Health Area:  3900
APT 3D Admin Area:   Z - UPPER MANHATTAN Inspection Area:   E
NEW YORK, NY 10023 Community Board:   107
DOB Cross Street(s):   FREEDOM PLACE,    RIVERSIDE BOULEVARD
Status:   E - ABANDONED 08/22/2025
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  05/09/2016 3:24 PM
Application Entered:   05/09/2016 Job Start Date:   05/10/2016
Last Change:   08/22/2025 Job End Date:   04/10/2017
               COMPLETION FEE WAS BILLED
Appointment Status:   
Last Inspection By:   MOSES, DANIEM       On     08/22/2016      
Field Disp:   N - NO ACCESS
Energize Recommendation:  
Objection Disposition:  

License #: 012079 Licensee Name: DARIUSZ GRYGLEWSKI
Firm: 004264 Firm Name: FSM ELECTRICAL CORPORATIO
Firm Phone: 718-482-9151  Firm Address: 11-20 37TH AVENUE LONG ISLAND CITY NY 11101 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
6 - GENERAL WIRING
Total Fee:  $88.75
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: MICHAEL KATZ
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  1  3 #4
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  1  100 AMP
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
MZ3    40  30  11               
Buildings Total 40  30  11                  
Total Units : 85 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up:
Contractor's Comments:  

 
Inspection Details
 

INSPECTION FOR APPLICATION #: Z154974
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 06/27/2016 06/27/2016 UMS N (35) (0) Y
INSPECTION COMMENTS: CONTRACTOR NO SHOW
 
(2) 07/07/2016 07/08/2016 EDB N (26) (0) Y
INSPECTION COMMENTS: NEW AP. # Z155641 ON SAME APARTMENT.
 
(3) 08/01/2016 08/04/2016 CPP N (25) (0) Y
INSPECTION COMMENTS: NEW CONTRACTOR IS DOING WORK HERE SO THIS CONTRACTOR NEEDS TO FILE FOR A WITHDRAWAL. WE HAD NO ACCESS
 
(4) 08/22/2016 08/22/2016 DNM N (15) (0) Y
INSPECTION COMMENTS: ELECTRICIAN DID NOT SHOW.




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Electrical Applications  |  Electrical Inspection Work Order  |  Back