Electrical Application Details for App #: Z133888
Premises: 97 ARDEN STREET MANHATTAN BIN: 1064247     Block: 2175   Lot: 150
   
Application Completed and Certified

Filed: 97 ARDEN ST Census Tract:   287 Health Area:  0222
CELLAR Admin Area:   Z - UPPER MANHATTAN Inspection Area:   A
NEW YORK, NY 10040 Community Board:   112
DOB Cross Street(s):   DONGAN PLACE,    BROADWAY
Status:   C - JOB IS SIGNED OFF 08/15/2012
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  02/26/2012 10:18 AM
Application Entered:   02/26/2012 Job Start Date:   02/27/2012
Last Change:   08/15/2012 Job End Date:   02/27/2012
Appointment Status:   
Last Inspection By:   CAMPBELL, C       On     06/08/2012      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 010055 Licensee Name: TERRENCE REILLY
Firm: 002151 Firm Name: REILLY ELECTRICAL INC
Firm Phone: 718-826-1570  Firm Address: 57 GRAVESEND NECK RD BROOKLYN NY 11223 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
8 - BOILER/BURNER WIRING
Total Fee:  $52.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   L - Five Or More Family
Special Cert Approval:   B - BOILER CONTROLS J-51 CERTIFICATION
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: RICHARD PARKOFF
Owner Business Name: 97ARDEN ASSOC.LLC
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  1  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
Buildings Total                         
Total Units : 0 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  BOILER WIRING

 
Inspection Details
 

INSPECTION FOR APPLICATION #: Z133888
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 05/08/2012 05/22/2012 JSB N (30) (0) Y
INSPECTION COMMENTS: NONE
 
(2) 06/08/2012 06/16/2012 CLC C (30) (0) Y