BIS Menu  |  Elevators  |  Electrical Inspection Work Order  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: Y185324
Premises: 3440 BAILEY AVENUE BRONX BIN: 2129003     Block: 3262   Lot: 17
   

DOB NOW: Inspections

Application Completed and Certified

Filed: 3440 BAILEY AV Census Tract:   279 Health Area:  0310
GROUND FLOOR AND MEZZANINE Admin Area:   Y - BRONX Inspection Area:   H
BRONX, NY 10463 Community Board:   208
DOB Cross Street(s):   BAILEY PLACE,    WEST 238 STREET
Status:   C - JOB IS SIGNED OFF 03/26/2018
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  11/13/2017 7:22 PM
Application Entered:   11/13/2017 Job Start Date:   11/14/2017
Last Change:   03/26/2018 Job End Date:   11/30/2017
Appointment Status:   
Last Inspection By:   DIMAGGIO, PHILLIP       On     03/22/2018      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 010713 Licensee Name: WILLIAM TONELLI,JR
Firm: 000701 Firm Name: IZZO ELECTRIC INC.
Firm Phone: 718-904-0164  Firm Address: 2522 EAST TREMONT AVENUE BRONX NY 10461 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
6 - GENERAL WIRING
Total Fee:  $130.50
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   G - Garage
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: STEVE ZERVOUDIS
Owner Business Name: 3440 BAILEY AVE LLC
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   Yes
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  1  100 AMPS #3 WIRE
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  1  #3 WIRE
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  1  24 CKTS 100 AMPS
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
GND    17  12    17     
MEZ             
ROF                     
Buildings Total 21  21    21            
Total Units : 80 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  INSTALL SUB-PANEL, FIXTURES, HEATERS AND SWITCHES.

 
Inspection Details
 

INSPECTION FOR APPLICATION #: Y185324
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 03/22/2018 03/26/2018 PDI C (45) (0) Y
INSPECTION COMMENTS: PASS




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Elevators  |  Electrical Inspection Work Order  |  Back