| NYC Department of Buildings | ||
| Electrical Application Details for App #: Y185269 | ||
| Premises: 425 EAST 154 STREET BRONX | BIN: 2001389 Block: 2376 Lot: 30 |
| DOB NOW: Inspections | |||||||||||
| Application Completed and Certified | |||||||||||
| Filed: | 425 E 154TH ST | Census Tract: 67 | Health Area: 3900 | |
| BASEMENT TO ROOF | Admin Area: Y - BRONX | Inspection Area: B | ||
| BRONX, NY 10455 | Community Board: 201 | |||
| DOB Cross Street(s): MELROSE AVENUE, ELTON AVENUE | |||
| Status: C - JOB IS SIGNED OFF 01/17/2019 | |||
| Request Type: A - APPLICATION | eFiled: YES | Permit Issued: 11/09/2017 7:40 AM | |
| Application Entered: 11/09/2017 | Job Start Date: 11/09/2017 | ||
| Last Change: 01/17/2019 | Job End Date: 11/08/2018 | ||
| Appointment Status: | |||
| Last Inspection By: RICHARD REED On 11/30/2018 | |||
| Field Disp: C - INSPECTION PASSED | |||
| Energize Recommendation: | |||
| Objection Disposition: R - REMOVED | |||
| License #: | 012486 | Licensee Name: | ANTHONY QUINONES | |
| Firm: | 004300 | Firm Name: | QUEUE ELEC'L CONTRS, INC | |
| Firm Phone: | 718-353-7700 | Firm Address: | 94-02 LINDEN BLVD 1ST FLOOR OZONE PARK NY 11417 | |
| Work Started or Filed by Others: NO | ||||||||
| Work Category: R - REHABILITATION | Work To Be Done:
1 - SERVICE WORK/NOTIFY UTILITY 6 - GENERAL WIRING 7 - HVAC WIRING T - TEMPORARY LIGHT & POWER |
Total Fee: $935.25 | ||||||
| Other Work: | ||||||||
| Work Related to a New or Amended Certificate of Occupancy: NO | ||||||||
| This Job Regulated by the NYC Energy Conservation Code: No | ||||||||
| Building Used As: L - Five Or More Family | |||||||
| Special Cert Approval: | |||||||
| Advisory Board Approval: NOT APPLICABLE | |||||||
| Owner / Occup: | SASHA CATUS | ||||||
| Owner Business Name: | 425 EAST 154TH STREET LLC | ||||||
| Authorized Representative: | |||||||
| Relationship To Owner: | |||||||
|
|
| Floor | Apt. | Number Of Outlets | No. Of Fixtures |
Motors / Generators | Heaters | Transformers | ||||||
| Fixt | Receptacles | Switch | Num | Total HP KW | Num | Total KW | Num | Total KVA | ||||
| ATT | A/C | |||||||||||
| BAS | 10 | 4 | 2 | 10 | 2 | 10 | 3 | 3 | ||||
| 001 | 34 | 36 | 4 | 6 | 34 | 2 | 2 | |||||
| 002 | 34 | 36 | 4 | 6 | 34 | 2 | 2 | |||||
| 003 | 34 | 36 | 4 | 6 | 34 | 2 | 2 | |||||
| 004 | 34 | 36 | 4 | 6 | 34 | 2 | 2 | |||||
| ROF | 2 | 1 | 1 | 2 | 2 | 2 | ||||||
| Buildings Total | 148 | 149 | 16 | 27 | 148 | 20 | 3 | |||||
| Total Units : 511 units | ||||||||||||
| Signs: | Field Connect: | 0 | Field Inspect: | 0 | Tags: | ||
| Meter Request to Utility | #3-Wire | 8 | #4-Wire | 1 | #10-Wire | 0 | |
| Existing Meters | 0 | + New Meters | 9 | - Removed Meters | 0 | = Total Meters | 9 |
| Power Auth Flag: | I - ISSUED | Objection Flag: | |
| Power Requested: | 11/09/2017 | Notice: | 1 - FIRST NOTICE 11/13/2018 |
| Power Issued: | 11/09/2017 | Response: |
| Follow-Up: | K - (CLOSED) | ||
| Contractor's Comments: GUT REHAB & BUILDING EXTENSION | |||
|
|