BIS Menu  |  Comments  |  Electrical Inspection Work Order  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: Y166182
Premises: 406 EAST 161 STREET BRONX BIN: 2113742     Block: 2382   Lot: 7502
   
Application Completed and Certified

Filed: 406 E 161 ST Census Tract:   141 Health Area:  3400
SIDEWALK Admin Area:   Y - BRONX Inspection Area:   C
BRONX, NY 10451 Community Board:   203
DOB Cross Street(s):   MELROSE AVENUE,    ELTON AVENUE
Status:   C - JOB IS SIGNED OFF 01/12/2015
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  10/15/2013 8:05 AM
Application Entered:   10/15/2013 Job Start Date:   11/04/2013
Last Change:   01/12/2015 Job End Date:   11/08/2013
Appointment Status:   
Last Inspection By:   GARY MCCALLA       On     01/09/2015      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 011444 Licensee Name: STEVEN FARKAS
Firm: 002896 Firm Name: STEVEN FARKAS
Firm Phone: 718-612-5490  Firm Address: 42 RICHMOND TERRACE STATEN ISLAND NY 10301 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
W - SIDEWALK SHED WIRING & LIGHTING
Total Fee:  $44.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   Z - Other
Store / Other:   CONDOMINIUM
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: SYLWESTER SERAFIN
Owner Business Name: INTERSYTEMS CORP
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
SWK    25                   
Buildings Total 25                      
Total Units : 26 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  INSTALL SIDEWALK SHED WIRING AND LIGHTING

 
Inspection Details
 

INSPECTION FOR APPLICATION #: Y166182
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 01/09/2015 01/12/2015 GYM C (25) (0) Y
INSPECTION COMMENTS: CERT- SHED REMOVED




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Comments  |  Electrical Inspection Work Order  |  Back