BIS Menu  |  Electrical Inspection Work Order   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: Y159301
Premises: 620 WEST 239 STREET BRONX BIN: 2091890     Block: 5907   Lot: 362
   
Application Completed and Certified

Filed: 620 W 239 ST Census Tract:   307.01 Health Area:  0100
BASEMENT Admin Area:   Y - BRONX Inspection Area:   H
BRONX, NY 10463 Community Board:   208
DOB Cross Street(s):   BLACKSTONE AVENUE,    INDEPENDENCE AVENUE
Status:   C - JOB IS SIGNED OFF 04/16/2012
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  03/14/2012 8:20 AM
Application Entered:   03/14/2012 Job Start Date:   03/15/2012
Last Change:   04/16/2012 Job End Date:   03/14/2013
Appointment Status:   
Last Inspection By:   ASHMAN, K.       On     04/02/2012      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 010515 Licensee Name: JOSEPH BONURA
Firm: 002497 Firm Name: SWITCH ELECTRIC CORP.
Firm Phone: 718-227-7712  Firm Address: 178 INDUSTRIAL LOOP-BAY 2 STATEN ISLAND NY 10309 

Work Started or Filed by Others: YES
Work Category:   R - REHABILITATION Work To Be Done:  
6 - GENERAL WIRING
Total Fee:  $40.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: FRANK CUFFINO
Owner Business Name: T MOBILE
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
BAS  000                     
Buildings Total                       
Total Units : 1 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  REMOVAL OF VIOLATION #Y150099 AND FILED UNDER MINOR WORK #Y159026 BY SWITCH ELECTRIC.

 
Inspection Details
 

INSPECTION FOR APPLICATION #: Y159301
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 04/02/2012 04/16/2012 KAS C (15) (0) Y
INSPECTION COMMENTS: C




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.