Electrical Application Details for App #: Y125682
Premises: 1890 ANDREWS AVENUE BRONX BIN: 2009053     Block: 2879   Lot: 28
   
Application Completed and Certified

Filed: 1890 ANDREWS AV Census Tract:   245 Health Area:  1510
NONE Admin Area:   Y - BRONX Inspection Area:   F
BRONX, NY 10453 Community Board:   205
DOB Cross Street(s):   WEST TREMONT AVENUE,    WEST BURNSIDE AVENUE
Status:   C - JOB IS SIGNED OFF 11/25/2005
Request Type:   A - APPLICATION eFiled:   NO
Application Entered:   03/04/2005 Job Start Date:   02/25/2005
Last Change:   11/25/2005 Job End Date:   04/09/2005
Appointment Status:   
Last Inspection By:   GARY MCCALLA       On     11/21/2005      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  E - ISSUE POWER AUTH
Objection Disposition:  R - REMOVED

License #: 011495 Licensee Name: CLAIRMONT LONDON
Firm: 002966 Firm Name: CLAIRMONT ELEC'L CONTR'G
Firm Phone: 718-676-1537  Firm Address: 4113 AVENUE J,GROUND FLOOR INC. BROOKLYN NY 11210 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
1 - SERVICE WORK/NOTIFY UTILITY
6 - GENERAL WIRING
Total Fee:  $1,543.25
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   Z - Other
Store / Other:   COMM
Special Cert Approval:  
Advisory Board Approval:  
Owner / Occup: LEONARD SCHWARTZ
Owner Business Name: MORRIS HEIGHTS RESTORATIO
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  1  
C. 201 Up to 600 AMPS  2  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  62  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  1  
D. Over 250 MCM  3  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
Buildings Total   133    65  65                
Total Units : 263 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 60 #4-Wire 3 #10-Wire 0
Existing Meters 63 + New Meters 63 - Removed Meters 63 = Total Meters 63

Power Auth Flag: I - ISSUED Objection Flag:
Power Requested: 03/04/2005 Notice: 1 - FIRST NOTICE 09/14/2005
Power Issued: 03/04/2005 Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  

 
Inspection Details
 

INSPECTION FOR APPLICATION #: Y125682
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 09/12/2005 09/14/2005 GYM A E (85) (7) Y
INSPECTION COMMENTS: NONE
 
(2) 11/21/2005 11/25/2005 GYM C R E (80) (0) Y
INSPECTION COMMENTS: NONE