| BUILDING OVERVIEW |
Are Feeders Being Installed? : Yes |
| (If feeders are being installed, provide a wiring diagram and calculations at the time of inspection) |
| Building Overview Work Items |
QUANTITY |
DESCRIPTION |
| SERVICE SWITCHES |
|
| A. Up to 100 AMPS |
0 |
|
| B. 101 Up to 200 AMPS |
0 |
|
| C. 201 Up to 600 AMPS |
1 |
(1) 600A |
| D. 601 Up to 1200 AMPS |
0 |
|
| E. Over 1200 AMPS |
0 |
|
| SER. ENT. & FDR COND (EACH SET) |
|
| A. Up to #2 CONDUCTOR |
0 |
|
| B. Over #2 to 1/0 |
0 |
|
| C. Over 1/0 to 250 MCM |
2 |
(2) 350MCM |
| D. Over 250 MCM |
0 |
|
| PANELS |
|
| A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs |
16 |
(16) 12-POLE SINGLE-PHASE |
| B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs |
0 |
|
| C. 3 Phase Up to 225 AMPS |
0 |
|
| D. 3 Phase Over 225 AMPS |
0 |
|
| ELEVATORS / ESCALATORS / MATERIAL LIFTS |
|
| A. Total No. of Elevators / Escalators / Material Lifts |
0 |
|
| B. Each Additional 10 Floors Or Less |
0 |
|
| BOILER CONTROLS |
0 |
|
| OBJECTION ID |
OBJECTION CODE |
OBJECTION DESCRIPTION & COMMENTS |
STAT |
FIRST |
LATEST |
RESLVD |
| |
| 001 |
(128) |
NEUTRAL IS GROUNDED BEYOND LOAD SIDE OF SERVICE SWITCH (ALL FLOORS) STOVES NEUTRAL ARE BONDED T-OUT. |
RSLV |
12/20/2017 |
12/20/2017 |
02/20/2018 |
| |
| 002 |
(129) |
SERVICE SWITCH NEUTRAL NOT BONDED TO ENCLOSURE (BASEMENT) NO BONDING JUMPER ON SERVICE SWITCH. |
RSLV |
12/20/2017 |
12/20/2017 |
02/20/2018 |
| |
| 003 |
(132) |
EQUIPMENT/MATERIAL IS NOT PROPERLY GROUNDED (BASEMENT) PLP USED AS SERVICE NOT GROUNDED AND BONDED. |
RSLV |
12/20/2017 |
12/20/2017 |
02/20/2018 |
| |
| 004 |
(133) |
NO GROUND ROD: BASEMENT OR OUTSIDE (BASEMENT) NO SUPPLEMENTAL GROUNDING PROVIDED. |
RSLV |
12/20/2017 |
12/20/2017 |
02/20/2018 |
| |
| 005 |
(264) |
SERVICE LATERAL CONDUCTORS NOT OF PROPER SIZE (BASEMENT) SERVICE CONDUCTOR UNDER SIZE FOR EQUIPMENTS. |
RSLV |
12/20/2017 |
12/20/2017 |
02/20/2018 |
| |
| 006 |
( 46) |
PANEL HAS NOT BEEN PROVIDED WITH A DIRECTORY (BASEMENT) NO DIRECTORY ON PLP PANEL. |
RSLV |
12/20/2017 |
12/20/2017 |
02/20/2018 |
| |
| 007 |
( 5) |
SERVICE GROUNDING CONDUCTOR HAS NOT BEEN INSTALLED PROPERLY (BASEMENT)MAIN GEC NOT TERMINATED ON NEUTRAL ON 600A SERVICE SWITCH. |
RSLV |
12/20/2017 |
12/20/2017 |
02/20/2018 |
| |
| 008 |
( 53) |
GFCI HAS NOT BEEN PROVIDED (BASEMENT) RECEPTACLES IN BSMT NOT GFCI PROTECTED. |
RSLV |
12/20/2017 |
12/20/2017 |
03/13/2018 |
| |
| 009 |
( 1) |
SERVICE EQUIPMENT ENCLOSURES ARE NOT BONDED TOGETHER (BASEMENT) AT CON ED BOX |
RSLV |
02/20/2018 |
02/20/2018 |
03/13/2018 |
| |
| 010 |
(999) |
OTHER (BASEMENT) ARC FLASH LABELS NOT PROVIDED ART. 110.16 |
RSLV |
02/20/2018 |
02/20/2018 |
03/13/2018 |
| |
| 011 |
(999) |
OTHER (BASEMENT)WATER MAIN GROUND UNDERSIZE AT 600 AMP SWITCH AS PER TABLE 250.66 |
RSLV |
02/20/2018 |
02/20/2018 |
03/13/2018 |
| |
| 012 |
(999) |
OTHER (BASEMENT) THREE WIRES UNDER SAME LUG AT CON ED BOX ART. 110.14 |
RSLV |
02/20/2018 |
02/20/2018 |
03/13/2018 |